Sub topic 4
Writing a Project Charter
Assume you understand process variation, basic defect rates, and the Lean Six Sigma roles of Champion, Black Belt, Green Belt, and Process Owner. This chapter focuses on the project charter, a Define-phase document that aligns the team before detailed measurement begins.
What a project charter does
A project charter is a short agreement about why the project exists, what it covers, and how success will be judged. It prevents the team from solving an unclear problem or expanding into unrelated work.
The charter is not a detailed project schedule. It records the project’s business purpose and boundaries. The team can revise it when Measure-phase evidence changes the understanding of the problem, but revisions should be explicit and approved.
A useful charter connects these elements:
Core charter sections
Include enough detail for a sponsor to approve the project and for the team to begin collecting evidence.
| Section | What to record | Example |
|---|---|---|
| Business case | Why the issue matters | Late shipments increase customer complaints |
| Problem statement | Observable current condition, location, and time period | 18% of domestic orders shipped late from January to March |
| Goal statement | Measurable target and deadline | Reduce late shipments to 5% or less by September 30 |
| Scope | Processes, products, sites, and dates included or excluded | Include order release through carrier pickup at Site A |
| Measures | Primary outcome and possible constraints | Late-shipment rate; overtime and damage rate as constraints |
| Team and governance | Sponsor, project lead, process owner, and review cadence | Champion sponsors; Green Belt leads; Logistics Manager owns process |
Writing strong statements
A problem statement describes what is happening without guessing at its cause. “The dispatch team does not follow the scheduling procedure” is a suspected cause, not a problem statement. Prefer a statement containing a baseline, population, location, and period.
A goal statement describes the desired result, not the solution. “Install barcode scanners” names an intervention. “Reduce picking errors from 4.2% to 1% by December 1” defines a result and leaves Analyze and Improve open to evidence.
Define the primary metric precisely enough that different people would calculate it the same way. State the numerator, denominator, unit of analysis, and time window when practical.
Common charter errors
- Starting with a solution instead of a measurable problem.
- Setting a goal without a baseline or deadline.
- Using vague terms such as “improve quality” or “reduce delays.”
- Making the scope so broad that the team cannot finish.
- Assigning accountability without giving the Process Owner authority to implement changes.
- Treating the initial charter as permanent when verified data contradicts its assumptions.
At the first tollgate, the team should be able to show the approved charter, agreed definitions, named roles, and a feasible project boundary.
Exercise
A sponsor asks for a project to “improve invoice processing.” What must the team add before approving the charter?
Show answer
Add a measurable problem statement with a population, period, and baseline; a numeric goal and deadline; defined scope boundaries; agreed measures; and named sponsor, project lead, and Process Owner.