Prerequisites and purpose
This chapter assumes that you understand the Define, Measure, and Analyze phases, including the project charter, baseline performance, and verified root causes. A solution should address a proven cause, not merely treat a visible symptom.
The Improve phase converts analysis into a tested change. Its purpose is to select a practical solution, test it on a limited scale, and use evidence to decide whether to implement, revise, or reject it.
Select solutions against clear criteria
Begin by listing possible countermeasures for each verified root cause. Then compare them using criteria agreed with the Process Owner and project Champion.
| Criterion | Question |
|---|---|
| Effectiveness | Will the solution reduce the verified cause or the CTQ defect? |
| Feasibility | Can the process implement it with available skills, time, and equipment? |
| Risk | Could it create safety, compliance, quality, or customer problems? |
| Cost | Do the expected benefits justify the implementation cost? |
| Control | Can the process owner monitor and sustain the change? |
A weighted decision matrix can make the choice visible. Assign each criterion a weight, score each option, and calculate the weighted total. Do not let a high score replace engineering judgment. A solution with a strong total score may still fail if it violates a regulatory requirement or creates an uncontrolled risk.
Prefer solutions that prevent errors, simplify work, or make the correct action easier. Training alone is often weak because it depends on people remembering the instruction every time. A physical guide, automatic check, or system control may provide more reliable prevention.
Design and run the pilot
A pilot is a small, controlled implementation used to learn before full deployment. Define the pilot population, location, duration, responsible people, inputs, and success measures. Keep the measurement method consistent with the baseline so that the comparison is valid.
Record both outcome measures and process measures. An outcome measure might be defect rate or cycle time. A process measure shows whether the new method was actually followed, such as checklist completion. Also record unintended effects, exceptions, and implementation problems.
Compare pilot results with the baseline and consider variation, not only the average. If possible, use a control group or a before-and-after comparison with similar operating conditions. A short pilot that coincides with unusual demand, staffing, or equipment may give a misleading result.
> callout note > Do not declare success because the pilot average improved once. Check whether the change is statistically and operationally meaningful, whether the measurement system is trustworthy, and whether risks remain acceptable.
Decide what happens next
At the pilot review, document the evidence and choose one outcome:
- Implement the solution and update the control plan.
- Revise the solution and run another pilot.
- Reject the solution and select another option.
- Stop the project if the expected benefit no longer justifies the effort.
Exercise
A pilot reduces defects, but operators use the new method only 60% of the time. What should the team do before full implementation?
Show answer
Investigate adoption and process measures, remove barriers, and repeat or extend the pilot until consistent use and acceptable results are demonstrated.