Sub topic 12
Improve: Designing and Testing Solutions
Assume you know the DMAIC phases, can read a basic process map, and understand simple statistics such as averages, defect rates, and variation. This chapter focuses on turning verified causes into tested process changes.
From verified cause to solution
The Improve phase addresses the causes confirmed during Analyze. A root cause is not simply a suspected explanation. It is a factor whose relationship with the problem has been supported by data or a controlled test.
Start by converting each important cause into a design requirement. For example:
- Cause: the approval form often lacks a required field.
- Requirement: prevent submission when the field is blank.
- Possible solutions: add validation, redesign the form, or move the check earlier in the process.
Generate several possible solutions before choosing one. A solution should reduce the target defect without creating unacceptable effects elsewhere.
Selecting a solution
Use criteria that reflect both performance and practicality. A simple decision matrix can compare options consistently.
| Criterion | Question |
|---|---|
| Effectiveness | How much should the solution reduce the verified cause? |
| Feasibility | Can the team implement it with available technology, skills, and time? |
| Risk | Could it create safety, quality, compliance, or customer problems? |
| Cost | What investment and ongoing cost does it require? |
| Sustainability | Can process owners maintain it after the project ends? |
Score each option against the criteria. Weight criteria when they have different importance. A low-cost change that does not address the verified cause should not outrank a more effective solution merely because it is easy to install.
Designing a pilot
A pilot is a limited test of a proposed change before full deployment. Define the pilot before starting it:
- State the hypothesis. For example, “Adding form validation will reduce incomplete submissions.”
- Identify the population, process step, and time period.
- Record the baseline and the same performance measures after the change.
- Keep measurement definitions and sampling rules consistent.
- Define success criteria in advance.
- Check for side effects, such as longer cycle time or more workarounds.
If practical, compare the changed process with a similar unchanged process. This comparison helps separate the solution's effect from seasonal demand, staffing changes, or other factors.
Reviewing the result
Compare pilot performance with the baseline using the measures defined in Measure. Review both the primary outcome and unintended effects. A solution may reduce defects while increasing rework, cost, or customer waiting time.
At the Improve tollgate, present the verified cause, options considered, selection criteria, pilot design, results, risks, and recommendation. The team may proceed, run another test, revise the solution, or stop the project if the expected benefit is not achievable. A successful pilot moves into Control with documented ownership, monitoring, and response rules.
Exercise
A pilot lowers the defect rate but increases cycle time beyond the customer requirement. Should the team implement it immediately?
Show answer
No. Investigate the trade-off, revise or replace the solution, and run another test unless the customer requirement is formally changed.