Preparing Tollgate Evidence and Checklists
Assume you know the basic DMAIC cycle and common Lean Six Sigma roles. This chapter focuses on the evidence needed to make a tollgate decision, not on performing every analysis in each phase.
What counts as tollgate evidence
A tollgate is a structured review between DMAIC phases. The team shows that the current phase produced reliable results and that the next phase is ready to begin. Evidence should answer three questions:
- What did the team plan to do?
- What did the team actually learn or deliver?
- What risks or gaps remain?
Evidence normally includes:
| Evidence type | Example |
|---|---|
| Scope and alignment | Approved charter, problem statement, goal, and project boundaries |
| Analysis or data | Data collection plan, measurement-system results, baseline, or verified causes |
| Deliverables | SIPOC, CTQ requirements, root-cause analysis, pilot results, or control plan |
| Decisions and risks | Open issues, owners, due dates, and the requested tollgate outcome |
The evidence must match the phase. A Measure tollgate should not rely only on opinions about the problem. It should include operational definitions, data, and an assessment of whether the measurement system is trustworthy. An Improve tollgate should include pilot results and evidence that the proposed change addresses a verified cause.
Build a phase checklist
A useful checklist has three properties:
- Each item is observable. “Understand the process” is vague; “SIPOC reviewed by the process owner” is testable.
- Each item has an owner and a status.
- Each item identifies the evidence location, such as a report, chart, or approved document.
Use statuses such as complete, incomplete, blocked, or not applicable. Do not silently treat missing evidence as complete.
MEASURE_TOLLGATE = [
"Operational definitions written for the Y and key Xs",
"Measurement system assessed and acceptable",
"Data collection plan executed",
"Baseline performance calculated",
"Goal in the charter confirmed or revised",
]
def review(checklist, completed):
missing = [item for item in checklist if item not in completed]
return ("go", []) if not missing else ("hold", missing)
completed = set(MEASURE_TOLLGATE[:4])
decision, gaps = review(MEASURE_TOLLGATE, completed)
print(f"Decision: {decision}")
print("Gaps:", gaps)This simple model returns a hold when one required item is missing. A real review can add evidence links, owners, due dates, and risk ratings.
Present the decision clearly
The project team should request one of four outcomes:
- Go: Required evidence is complete, and the next phase may start.
- Conditional go: The next phase may start while specific low-risk gaps are closed by named owners and dates.
- Hold: The team must complete important missing work before proceeding.
- Stop: The project should be cancelled, redesigned, or escalated because the business case, data, scope, or risk is unacceptable.
Common checklist errors
Teams often copy the same checklist into every tollgate. This creates paperwork without testing readiness. Other common errors include accepting analysis without clear data definitions, allowing unowned actions, and confusing activity with evidence. “Workshop completed” proves that a workshop occurred; it does not prove that a root cause was verified.
Exercise
A team has completed its Measure activities, but the measurement-system assessment shows inconsistent results. Which tollgate outcome is appropriate, and why?
Show answer
Hold, unless the inconsistency is proven low risk and a conditional-go plan names an owner and deadline for resolving it. The baseline cannot be trusted until the measurement system is acceptable.