Define: Agreeing on the Problem and the Goal
Assume you understand basic process improvement, defect rates, and variation. You should also know the Lean Six Sigma roles of Champion, Black Belt, Green Belt, and Process Owner.
The Define phase establishes why the project exists, what process it covers, and what success means. The team converts a broad complaint into a specific, measurable problem. It also confirms that the problem is important enough to justify project effort.
Start with the problem, not a solution
A useful problem statement describes the current condition without guessing at its cause or proposing a fix.
Weak statement:
- “The team needs a new order-entry system.”
Better statement:
- “During the last quarter, 18% of customer orders required correction after entry, causing an average two-day delay and approximately $24,000 in rework.”
The better statement identifies the process outcome, the size of the gap, the time period, and the business impact. It does not claim that a new system is the answer.
A goal statement describes the desired future condition and its deadline. For example:
- “Reduce order-entry corrections from 18% to 5% or less by the end of September, without increasing processing time.”
The goal should be challenging but realistic. It should use the same operational definition as the problem statement.
Build the project charter
The project charter is the agreement that guides the project. It normally includes:
- Business case: why the issue matters.
- Problem statement: what is wrong now.
- Goal statement: the target and deadline.
- Scope: where the project starts and stops.
- Team: Champion, project leader, Process Owner, and subject-matter experts.
- Milestones: expected dates for each DMAIC phase.
- Expected benefits: financial, customer, quality, or capacity benefits.
The charter is a working agreement, not a final report. The team may revise the goal or scope when Measure produces reliable baseline data.
Connect customer needs to CTQs
The voice of the customer is what customers say, expect, or experience. A critical-to-quality requirement, or CTQ, translates that need into a measurable condition.
For example:
| Customer need | CTQ requirement | Measure |
|---|---|---|
| “My order should be correct” | Order contains no entry errors | Percentage of orders without errors |
The CTQ must define what counts as acceptable. Terms such as “fast,” “accurate,” and “responsive” are not measurable until the team sets a threshold and a measurement method.
Scope the process with SIPOC
SIPOC summarizes Suppliers, Inputs, Process, Outputs, and Customers. It prevents the team from solving a problem outside its authority or collecting data from the wrong part of the process.
A Define tollgate is ready when the sponsor and team agree on the problem, goal, scope, customer requirement, and ownership.
Exercise
Why should a problem statement avoid naming a solution?
Show answer
Naming a solution assumes the cause before the team collects and analyzes evidence. A neutral statement keeps the project open to verified causes and suitable solutions.