Why Projects Pass Through Tollgate Reviews
Assume you know the basic DMAIC sequence and can interpret simple defect rates and averages. This chapter focuses on how tollgates govern movement between phases.
A tollgate review is a formal decision point at the end of a DMAIC phase. The project team presents its evidence to a reviewer or steering group. The group decides whether the project should continue, continue with conditions, pause, or stop.
Tollgates prevent a team from building solutions on weak assumptions. For example, a team should not search for root causes before it has defined the problem and checked that its measurements are trustworthy.
How the review fits into DMAIC
A project normally has a tollgate after Define, Measure, Analyze, and Improve. Control often includes a final handover review.
Each tollgate asks a different question:
| Phase ending | Main question | Typical evidence |
|---|---|---|
| Define | Are the problem, scope, customer need, and goal clear? | Charter, CTQ statement, SIPOC |
| Measure | Do we trust the data and understand current performance? | Data plan, measurement assessment, baseline |
| Analyze | Have important causes been verified? | Analysis results and cause evidence |
| Improve | Does the selected solution work without unacceptable risks? | Pilot results and implementation plan |
| Control | Can the process owner maintain the gain? | Control plan, response rules, and handover record |
Possible decisions
The review group should make its decision explicit.
- Go: The required evidence is complete, and the project may enter the next phase.
- Conditional go: The project may continue while the team closes specified gaps by a stated date.
- Hold: Work pauses until missing evidence or unresolved risks are addressed.
- Stop: The project ends because the business case changed, the problem is not suitable for DMAIC, or the expected benefit is no longer justified.
A conditional go is useful when a small, low-risk gap does not invalidate the current conclusion. It should never excuse a failed measurement system or an unverified cause.
Running a tollgate
The project leader should send the evidence before the meeting. During the review, the team explains what it learned, shows how conclusions follow from data, and identifies open risks. The Champion or steering group tests whether the work still supports the business goal. The Process Owner confirms that proposed changes can operate in the real process.
Record the decision, required actions, owners, due dates, and the evidence needed to close each gap. A vague action such as “collect more data” is insufficient. State which data, from which process conditions, and by when.
Exercise
A Measure tollgate shows a promising DPMO baseline, but the measurement system has not been assessed. Should the project receive a go decision?
Show answer
No. The project should receive a hold, or at most a conditional go for limited measurement-system work. The baseline cannot support later analysis until the team establishes that the measurement method is reliable.