Sub topic 16
Who Attends a Tollgate and the Possible Decisions
This chapter assumes you know the five DMAIC phases, the project charter, basic process metrics, and the roles of Champion, Black Belt, Green Belt, and Process Owner. A tollgate is a formal review at the end of a DMAIC phase. The team presents evidence, and the organization decides whether the project should proceed.
Who attends a tollgate
Attendance should be large enough to make a sound decision but small enough to support focused discussion. The exact membership depends on the project’s risk, cost, and scope.
| Role | Main responsibility at the review |
|---|---|
| Champion or sponsor | Confirms business priority, removes barriers, and approves resources |
| Black Belt or Green Belt | Presents the work, evidence, risks, and requested decision |
| Process Owner | Confirms that the findings fit the real process and accepts future ownership |
| Subject-matter experts | Explain technical, operational, customer, or compliance issues |
| Finance representative | Checks the financial baseline and expected benefit when required |
| Quality, regulatory, or safety representative | Reviews risks and required controls in regulated processes |
| Tollgate chair or steering committee | Tests the evidence and records the decision |
The project leader should send evidence before the meeting. Attendees should review it in advance, rather than using the tollgate to discover basic facts for the first time.
What the review examines
The review checks whether the phase produced its required outputs and whether the next phase is justified. A review is not only a presentation. It is a decision about evidence, risk, and organizational commitment.
The team should be ready to explain:
- What question the phase answered.
- Which deliverables are complete.
- Which assumptions remain uncertain.
- What data supports the conclusion.
- What risks could affect the next phase.
- What resources or decisions are needed.
For example, at the Measure tollgate, the team may show operational definitions, a data collection plan, measurement-system results, and a baseline such as DPMO or sigma level. If the measurement system is unreliable, the team should not claim that the baseline is trustworthy.
Possible decisions
Go
A go decision means the required evidence is complete, the risks are understood, and the team may begin the next phase. The decision should identify the next phase, owner, and target date.
Conditional go
A conditional go allows limited progress while named gaps are closed. The conditions must be specific, assigned to owners, and given due dates. For example, the team may begin Analyze while completing a missing data-stratification step. A vague condition such as “improve the data” is not controllable.
Hold
A hold pauses the project until important evidence or work is complete. Typical causes include an unacceptable measurement system, unclear scope, missing customer requirements, or an unverified baseline.
Stop
A stop closes or cancels the project. This may be appropriate when the problem has disappeared, the expected benefit is too small, the proposed solution is not feasible, or another project already addresses the same issue. Stopping a project is a valid management decision when the evidence no longer supports continuing.
Exercise
A team has completed its Measure deliverables, but the gage study shows that the measurement system cannot distinguish process differences reliably. What decision is most appropriate, and why?
Show answer
Hold the project at the Measure tollgate. The team should improve or replace the measurement system before using the data to establish a baseline or analyze causes.