Sub topic 1
What Counts as a Risk
Prerequisites
This chapter assumes you already have the following:
- Basic familiarity with how projects are organized: scope, schedule, budget, and stakeholders.
- Experience working in or alongside a project team.
- Comfort with a spreadsheet or a simple tracking tool.
You do not need any risk management training. This chapter sets up the vocabulary that the rest of the tutorial uses.
Why the definition matters
A risk register is only as useful as the entries in it. If the register mixes real risks with current problems, guesses, and fixed limits, the team cannot score or manage the entries consistently. Most registers that go stale were cluttered from the start.
A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective, such as scope, schedule, cost, or quality. Three parts of that definition do the work:
- Uncertain. The event may happen or may not. You can assign it a probability between 0 and 100 percent, but not exactly 0 or 100.
- Future. It has not happened yet. Once it happens, it is no longer a risk.
- Tied to an objective. It matters only if it changes something the project is trying to achieve.
Risks that help the project are called opportunities, for example a vendor delivering early. This tutorial focuses on threats, which are the negative risks. Most registers are built around them, and the same fields work for opportunities.
Risk, issue, assumption, constraint
Four terms are often confused. Each one belongs in a different place in your project records.
| Term | Definition | Certainty | Where it belongs |
|---|---|---|---|
| Risk | An uncertain future event that could affect objectives | May or may not happen | Risk register |
| Issue | A risk that has occurred, or a problem that exists now | Already happening | Issue log |
| Assumption | A condition taken as true for planning, without proof | Believed, not verified | Assumption log |
| Constraint | A fixed limit on the project | Certain | Project charter or plan |
Risks and issues
An issue is a problem you must deal with now. A risk is a problem you might have later. "The test server crashed this morning" is an issue. "The test server may crash during load testing" is a risk.
A risk becomes an issue when it occurs. At that point, move it out of the register's open list. Record the change, assign the issue to someone, and track it in the issue log. If the risk had a contingency plan, this is when you run it.
Assumptions
An assumption is something you treat as true so that planning can go ahead. "The vendor will deliver the API by March" is an assumption. Assumptions are not risks, but each one hides a risk: the chance that it is wrong.
To find risks in your assumptions, ask of each one: "What if this is false, and how likely is that?" If the answer matters, write a risk. For the vendor example, the risk might be that the API arrives late and integration testing slips.
Constraints
A constraint is a limit you cannot change, such as a fixed launch date, a budget cap, or a regulation. A constraint is certain, so it is not a risk. But constraints make risks more serious. A fixed launch date means any schedule slip hits you harder, because you have no room to move the date.
The test: is this a risk?
You can sort most candidates with a few questions, asked in this order.
- Has it already happened, or is it happening now? If yes, it is an issue.
- Is it certain, fixed, or a rule you must follow? If yes, it is a constraint.
- Is it something you believe but have not confirmed? If yes, it is an assumption. Then ask what happens if it is wrong, and write a risk if the answer matters.
- Is it uncertain, in the future, and able to affect an objective? If yes, it is a risk.
Worked example
Suppose a team is planning a website launch. Here are six statements from a planning meeting, sorted with the test above.
| Statement | Classification | Reason |
|---|---|---|
| "The payment vendor's sandbox went down yesterday." | Issue | It has already happened. |
| "We must launch before the end of Q2." | Constraint | It is a fixed limit. |
| "The lead designer will stay on the project." | Assumption | It is believed but not verified. |
| "The lead designer may leave, stalling redesign work." | Risk | It is uncertain, future, and affects the schedule. |
| "Launch will go well." | Not a risk | It is vague and names no event or objective. |
| "Traffic may exceed our hosting capacity on launch day." | Risk | It is uncertain, future, and affects quality and cost. |
Notice the fourth row. It comes straight from the assumption in the third row. Turning assumptions into risks is one of the most productive ways to fill a register.
Edge cases
Some candidates do not sort cleanly. These are the ones that cause arguments in review meetings.
- Near-certain events. If something is 95 percent likely, it is still a risk in theory. In practice, many teams plan for it directly. Put it in the schedule or budget instead of leaving it as a risk. A team that is sure a vendor will be late should plan for the delay.
- Recurring problems. If a supplier has been late on every past delivery, the next late delivery is likely. Keep it as a risk with a high probability, and record the past pattern as the evidence for that rating.
- Causes versus risks. "Staff shortage" is a condition, not an event. It is a cause. The risk is what the shortage might lead to, such as missed deadlines. Section later in this tutorial on risk statements covers how to write cause, event, and effect together.
- General worries. "The economy might get worse" is too broad to act on. Narrow it to something the project can respond to, such as "a rise in contractor rates may push the labour budget over its cap".
- Positive uncertainty. An uncertain good outcome is an opportunity. Keep it in the register only if your team has agreed to track opportunities. Otherwise you will mix two kinds of entries that need different responses.
- Issues that carry new risks. An issue can create future uncertainty. If the sandbox outage continues, integration testing may slip. The outage goes in the issue log, and the possible slip goes in the register as a risk.
Common mistakes at this stage
- Logging issues as risks. The register fills with problems that need action today. Reviews turn into status meetings, and real risks get no attention.
- Logging vague worries. Entries such as "poor communication" cannot be scored, assigned, or closed.
- Ignoring assumptions. Unchecked assumptions are a common source of surprises, and they cost nothing to check at planning time.
- Treating constraints as risks. You cannot lower the probability of a rule. You can only plan around it, and you should plan for the risks it makes worse.
- Never reclassifying. A risk that has occurred must be moved to the issue log. If it stays in the register, its score is meaningless.
Summary of the working model
Keep the register for items that are uncertain, in the future, and linked to an objective. Send what has happened to the issue log, record fixed limits as constraints, and test every assumption by asking what happens if it is false. The next chapters build on this: why a register is worth keeping, which fields it needs, and how to write each entry clearly.
Exercise
Classify each statement as a risk, issue, assumption, or constraint: (a) "The client's budget cannot exceed $200,000." (b) "The database migration failed last night." (c) "The migration may fail during cutover and delay go-live." (d) "The client will approve the design within one week."
Show answer
(a) Constraint, because it is a fixed limit. (b) Issue, because it has already happened. (c) Risk, because it is uncertain, in the future, and affects the schedule. (d) Assumption, because it is believed but not verified. For (d), you could also write a risk such as "The client may take longer than a week to approve the design, delaying the build phase."
Exercise
A risk in your register, "The test server may crash during load testing," has just occurred. What should you do with the entry, and why might you still add a new risk afterward?
Show answer
Move the entry out of the open risk list and log it as an issue with an owner, running any contingency plan that was prepared. You might add a new risk because the crash can cause further uncertain effects, for example "Repairing the server may take longer than planned, delaying the load test and the launch."