Sub topic 7
Defining Probability and Impact Scales
This chapter covers how to define the scales you use to rate each risk. It assumes you can write a cause-event-effect risk statement and know the register fields (id, owner, response, status). It also assumes you are comfortable with a spreadsheet. Scoring and the matrix come in the next chapter. Here you build the scales that feed them.
Why scales need definitions
A rating of "4 out of 5" means nothing until the team agrees what a 4 is. Without a shared definition, one person's "likely" is another person's "possible", and the register ends up ranking opinions instead of risks.
A scale is a short ordered list of levels. Each level has a label, a number, and a plain-language definition. You need two scales:
- Probability is how likely the risk event is to occur.
- Impact is how much the effect hurts the project if the event does occur.
The scales do three jobs. They make ratings comparable between people. They make ratings repeatable between review meetings. They make the ranking defensible when a sponsor asks why one risk outranks another.
Probability scales
Probability can be described in words, in percentages, or in both. The most useful scales pair a label with a numeric range, so people can anchor on either.
| Level | Label | Probability range | Rough meaning |
|---|---|---|---|
| 1 | Very unlikely | Under 10% | Would be a surprise |
| 2 | Unlikely | 10% to under 30% | Could happen, but not expected |
| 3 | Possible | 30% to under 50% | About as likely as not, slightly less |
| 4 | Likely | 50% to under 70% | Expected more often than not |
| 5 | Very likely | 70% or more | Expected to happen |
These bands are illustrative. Some teams use equal-width bands (20% each). Others use narrower bands near the extremes. Choose bands that separate the risks you actually have.
Make the ranges mutually exclusive and gap-free. A scale where level 2 ends at 30% and level 3 starts at 35% leaves a risk at 32% with nowhere to go.
Probability over what period?
A probability is meaningless without a time frame. A 30% chance of a vendor failing this week is very different from a 30% chance over the whole two-year project. State the frame in the scale header, for example "probability of occurring before the end of the project", or "before the next phase gate". Be consistent across the register.
Impact scales
Impact is harder than probability because projects care about several things at once. A single risk may threaten the budget, the schedule, the scope, or quality. The usual approach is one scale with a row per impact dimension, so each risk is rated against whichever dimension it hurts most.
| Level | Label | Cost | Schedule | Quality or scope |
|---|---|---|---|---|
| 1 | Very low | Under 1% of budget | Under 2 days | Barely noticeable |
| 2 | Low | 1% to under 3% | 2 days to under 1 week | Minor features affected |
| 3 | Moderate | 3% to under 7% | 1 to under 3 weeks | Some requirements not met |
| 4 | High | 7% to under 15% | 3 weeks to under 2 months | Major requirements not met |
| 5 | Very high | 15% or more | 2 months or more | Product fails its purpose |
Again, the numbers are examples. A project with a 50,000 budget and one with a 50 million budget cannot share absolute dollar thresholds, which is why percentages of budget or schedule travel better. Some organizations add rows for safety, legal compliance, reputation, or customer satisfaction. Add a row only if you will really use it, because every row is something reviewers must interpret.
Rate against the worst dimension
When a risk touches several dimensions, rate each one and take the highest. Take the vendor example from the CSV register used in this tutorial: a two-week slip is a schedule impact of 3, but if the slip also forces paid overtime worth 8% of budget, the cost impact is 4. The risk's impact is 4.
Choosing the number of levels
Three, four, five, and ten levels are all in use. The trade-offs are practical.
- Three levels are quick to apply but crowd most risks into the middle and give the matrix little resolution.
- Five levels are the common compromise. They separate risks well and still fit on one page.
- Even numbers (four or six) remove the middle option, which forces raters to lean one way. Some teams prefer this to discourage defaulting to "medium".
- Ten or more levels imply a precision that estimates rarely have. Disagreements over whether a risk is a 6 or a 7 waste meeting time.
Whatever you pick, use the same number of levels for probability and impact if you plan a square matrix. The example scripts in this tutorial use five on both.
Ordinal numbers are labels, not quantities
The numbers 1 to 5 are ranks. The step from 4 to 5 is not necessarily the same size as the step from 1 to 2. In the impact table above, level 5 begins at 15% of budget, while level 2 covers a band only 2 percentage points wide. Multiplying ranks to get a score (done in the next chapter) is a convenient ranking device, not arithmetic on real quantities. Do not read a score of 20 as "twice as bad" as a score of 10.
If you later need real money figures, switch to expected monetary value for the risks that matter most. This is covered in a later chapter.
Linking scales to risk appetite
Scales are where your organization's appetite for risk becomes concrete. If the sponsor says a one-month delay is intolerable, then one month should sit at a high impact level. If a 3% cost overrun is routine, it should sit low. Agree the impact thresholds with the sponsor, not just inside the project team. Thresholds set by the team alone tend to drift toward whatever makes the register look manageable.
Calibrating the scales
A scale on paper is not yet a scale in use. Test it before you rely on it.
- Pick five to ten risks from your register or from a past project.
- Have each reviewer rate them independently, without discussion.
- Compare ratings. Where two people differ by two or more levels, find out which words in the definition they read differently.
- Reword the definition, then rate again.
Common problems this finds include overlapping bands, undefined words like "significant", and impact rows that nobody can estimate at the time of rating.
Biases to watch for
- Optimism bias: raters underrate the probability of risks in their own work.
- Anchoring: the first number spoken in a meeting pulls the rest toward it.
- Recency: a risk that bit the team last month is rated higher than its real odds justify.
Independent rating before discussion reduces the first two. A short note beside each rating explaining why helps reviewers challenge it later.
Recording the scales
Put the scales where everyone using the register will see them, ideally on a tab in the same workbook or a page linked from the register. Include the date or version and who approved them. When the scales change mid-project, re-rate existing risks, or you will compare scores made under different rules.
Here is a small script that makes the probability bands executable. It maps a percentage estimate to a level, so a spreadsheet export can be checked for consistency.
BANDS = [
(10, 1), # under 10% -> level 1
(30, 2), # 10% to under 30% -> level 2
(50, 3), # 30% to under 50% -> level 3
(70, 4), # 50% to under 70% -> level 4
]
def probability_level(percent):
if percent < 0 or percent > 100:
raise ValueError("percent must be between 0 and 100")
for upper, level in BANDS:
if percent < upper:
return level
return 5
for p in (5, 10, 29.9, 30, 65, 70, 100):
print(p, probability_level(p))The boundary values in the loop show the half-open bands at work: 10 falls in level 2, and 70 falls in level 5.
Common errors
- Giving probability bands that overlap or leave gaps.
- Leaving the time frame out of the probability scale.
- Rating impact on one dimension only, usually schedule, and missing a larger cost impact.
- Using absolute dollar thresholds that do not fit the project's size.
- Treating the product of two ranks as a measured quantity.
- Changing scales mid-project without re-rating existing risks.
Exercise
A risk has a 35% chance of occurring before project end. If it occurs, it would delay delivery by 4 weeks and add 2% to the budget. Using the tables in this chapter, what are its probability level and impact level, and why?
Show answer
Probability is level 3 (Possible), because 35% falls in the 30% to under 50% band. Impact is rated per dimension and the highest is used. The 4-week delay falls in the 3 weeks to under 2 months band, so schedule impact is 4 (High). The 2% cost increase falls in the 1% to under 3% band, so cost impact is 2. The highest is 4, so the risk's impact level is 4.
Exercise
Your team's probability scale has level 2 as "10% to 30%" and level 3 as "35% to 50%". Name two problems with this scale and how to fix them.
Show answer
First, the range 30% to 35% belongs to no level, so a risk estimated at 32% cannot be rated. Second, 30% is ambiguous only if the bands also share an endpoint, so the boundaries should be written as half-open ranges. Fix both by making each band start exactly where the previous one ends, for example "10% to under 30%" and "30% to under 50%", and by stating the time frame the percentages cover.