Sub topic 12
Triggers, contingency plans, and reserves
This chapter assumes you can write a risk statement, score a risk with probability and impact, and pick a response strategy. It covers what to do when you accept a risk or when a mitigation may not be enough. You prepare a fallback, define a signal that tells you when to use it, and set aside money or time to pay for it.
Why a response strategy is not enough
Mitigation, transfer, and avoidance act before a risk happens. Some risks stay possible after those actions, and some are not worth acting on in advance. For these you plan a reaction instead of an action.
- Contingency plan: a set of steps you carry out only if a specific risk event occurs or is about to occur.
- Trigger: an observable condition that tells you a risk is happening or about to happen. Some teams call it a warning sign or risk indicator.
- Contingency reserve: an amount of money, time, or capacity set aside to pay for contingency plans and to absorb the cost of identified risks that occur.
- Fallback plan: a second option for when the contingency plan itself does not work. It is often kept for high-rated risks only.
A contingency plan without a trigger is a document nobody opens. A trigger without a plan produces an alarm and no response. A plan and a trigger without a reserve may be impossible to pay for. The three have to be designed together.
Writing good triggers
A trigger must be something a person can check without judgment. "The vendor seems slow" is an opinion. "The vendor has not delivered the sandbox account five working days after the agreed date" is a trigger.
A good trigger has these properties:
- Observable. It is a fact, a number, or a date, not a feeling.
- Early enough to act. It fires while the contingency plan can still work. A trigger that fires on the day of the failure leaves no time.
- Cheap to check. It can be read from a status report, a dashboard, or a meeting, so it will actually be checked.
- Owned. A named person watches it, usually the risk owner.
Common sources of triggers:
| Risk area | Example trigger |
|---|---|
| Schedule | A critical-path task is more than three days late |
| Budget | Spending reaches 80% of a work package budget with under 60% of the work done |
| Vendor | A supplier misses a milestone or fails to confirm a delivery date |
| People | A key person's leave request overlaps a deadline |
| Quality | Defect count in a test cycle exceeds an agreed limit |
| Scope | More than a set number of change requests arrive in one sprint |
Add the trigger to the register as its own field, next to the risk. Without it, reviews tend to ask only "has this happened yet?", which is too late.
Writing a contingency plan
A contingency plan is a short, specific procedure. It should be usable by the owner under pressure, so it names who does what and how long it takes.
Include:
- The trigger that starts it.
- The steps, in order, with the person responsible for each.
- The time and cost it needs, so the reserve can be sized.
- A decision point: who has authority to start it.
- What happens if it fails (the fallback), where the risk is high enough to justify one.
For risk R-001 from the sample register (the payment vendor has no sandbox SLA), a contingency plan might read:
- Trigger: The vendor's sandbox is not available five working days after the agreed date.
- Plan: Switch integration testing to a mock payment service built by the test team. Estimated effort: 8 days. Estimated cost: 12,000.
- Authority: The project manager can start the plan without further approval if the cost is within the contingency reserve.
- Fallback: Escalate to the sponsor to ask for a launch date change.
A planned response in advance saves the hours that would otherwise be spent debating options while the schedule slips.
Reserves
A reserve is an allowance for uncertainty. Two kinds are usually distinguished.
| Row | Contingency reserve | Management reserve |
|---|---|---|
| Covers | Identified risks in the register | Unknown risks, "unknown unknowns" |
| Controlled by | The project manager | Senior management or the sponsor |
| Part of the project baseline | Yes | No, though it is part of the total budget |
| Used when | A trigger fires and a contingency plan runs | A genuinely unforeseen event needs funding or time |
| Changes the baseline when used | No, it was already included | Yes, a baseline change is approved |
Reserves can be money, schedule time (a buffer before the deadline), or capacity (spare staff hours). Names and rules vary between organizations and standards, so check your own governance rules for who approves each draw.
Sizing a contingency reserve from the register
When cost data exists, expected monetary value (EMV) gives a starting figure. EMV is the probability of the risk times its cost if it occurs. Summing EMVs across the register estimates the reserve for those risks.
# Contingency reserve estimated as the sum of EMVs of open, accepted risks.
risks = [
{"id": "R-001", "probability": 0.40, "cost": 50000},
{"id": "R-003", "probability": 0.30, "cost": 20000},
]
for r in risks:
r["emv"] = r["probability"] * r["cost"]
reserve = sum(r["emv"] for r in risks)
print(reserve) # 26000.0The result, 26,000, does not mean any single risk will cost that. It is a pooled allowance. If R-001 occurs, it costs 50,000, which is more than the entire reserve. Over many risks the average cost tends toward the sum of EMVs, but a project has a small number of risks, so the actual outcome varies widely.
Limits of EMV-based reserves
- A small number of large risks. One big risk occurring can exceed the whole reserve. Some teams add a margin, or size the reserve to a higher confidence level using a simulation, which is beyond this chapter.
- Poor inputs. Probabilities in a register are estimates. A reserve is only as good as those estimates.
- Opportunities. Positive risks can reduce the total. Include them only if your organization's rules allow netting them off.
- Double counting. If a task estimate already contains padding for a risk, adding the same risk to the reserve counts it twice. Padding hidden inside estimates also makes reserves harder to manage.
Using and tracking the reserve
A reserve is only useful if its use is visible. Treat it like a small budget with its own ledger.
- Record the opening reserve and how it was derived.
- When a trigger fires, record which risk is drawing on the reserve and how much.
- When a risk expires without occurring, say so, and decide whether its share of the reserve is released or kept for others.
- At each review, compare the remaining reserve with the exposure of the open risks.
A simple check is the remaining reserve against the remaining EMV. If open risks have a combined EMV of 30,000 and the reserve holds 18,000, the plan is underfunded and the sponsor should be told (see the chapter on reporting and escalating).
reserve_remaining = 18000
open_risks_emv = 30000
gap = open_risks_emv - reserve_remaining
if gap > 0:
print(f"Reserve is short by {gap}")
else:
print("Reserve covers open risk exposure")Common mistakes
- Triggers that are really outcomes. "The launch is late" is the effect, not a warning of it.
- No owner for the trigger. Everyone assumes someone else is watching.
- Plans nobody has tested. A plan that depends on a person or tool that is not available on the day will fail. Check that the resources exist.
- A reserve that is quietly spent. Using it for scope growth or ordinary overruns hides real risk exposure.
- A single large reserve with no link to risks. Without the link, nobody can explain what it is for or when to release it.
- Contingency plans for every risk. Low-rated risks often need only monitoring. Plan in detail for the risks at the top of the matrix.
Adding the fields to the register
Extend the CSV register with trigger and contingency columns:
id,statement,probability,impact,owner,response,status,trigger,contingency
R-001,"Because the payment vendor has no sandbox SLA, integration testing may be delayed, causing a two-week slip to launch",4,4,A. Rivera,Mitigate,Open,"Sandbox not available 5 working days after agreed date","Switch to mock payment service; 8 days; 12000"
R-003,"Because the data center contract ends in June, migration may not finish in time, causing extra hosting fees",3,5,M. Okafor,Transfer,Open,"Migration less than 60% complete on 1 May","Negotiate short extension with current provider"A review can then list open risks whose trigger condition needs checking, and the owner reports "fired" or "not fired" for each.
Exercise
A project's register has two accepted risks. Risk A has probability 0.20 and cost 40,000 if it occurs. Risk B has probability 0.50 and cost 10,000. The contingency reserve is 12,000. (1) Calculate the combined EMV. (2) Is the reserve enough for the expected exposure? (3) Is it enough if Risk A occurs? (4) Rewrite the vague trigger "the supplier is behaving badly" so it is observable.
Show answer
(1) Risk A EMV = 0.20 x 40,000 = 8,000. Risk B EMV = 0.50 x 10,000 = 5,000. Combined EMV = 13,000. (2) No. The reserve of 12,000 is 1,000 short of the expected exposure. (3) No. Risk A costs 40,000 if it occurs, far more than the 12,000 reserve, so a larger reserve, a transfer or mitigation of Risk A, or an escalation path to the sponsor is needed. (4) For example: "The supplier has missed two consecutive agreed delivery dates" or "The supplier has not confirmed the next delivery date within three working days of our request."