Sub topic 17
Common pitfalls and good practices
This chapter assumes you can write a cause-event-effect risk statement, score risks on a probability-impact matrix, and pick a response strategy. It also assumes you have run at least one review cycle. The chapter collects the ways registers fail and the habits that prevent those failures.
Why registers fail
A register rarely fails because someone chose the wrong template. It fails because it stops being used. The usual path is that the team builds a thorough register at kickoff, files it, and opens it again only when an auditor or sponsor asks. By then the scores are months old, several owners have left, and the risks that actually hurt the project were never written down.
The diagram shows how this decay happens and where each good practice interrupts it.
Pitfalls and fixes
| Pitfall | What you see | Good practice |
|---|---|---|
| Built once, never reviewed | Last-modified date is months old | Put the review on the calendar and treat it as a standing meeting |
| Vague statements | Entries like "Budget risk" or "Vendor problems" | Require the cause-event-effect form for every entry |
| Issues mixed with risks | Rows describing things that have already happened | Move them to the issue log and keep only uncertain future events |
| No real owner | Owner field says "Team" or is blank | One named person per risk, who agrees to the role |
| Everything rated High | Most rows sit in the top band | Calibrate scales and bands against defined cost and schedule thresholds |
| Scores never change | Same numbers for many cycles | Re-score at each review and record why scores moved |
| Responses without actions | "Mitigate" with no next step | Attach a concrete action, a date, and a trigger where relevant |
| Register as paperwork | Only the project manager edits it | Make owners update their own rows and use the register in planning |
| Closed risks vanish | No record of what happened | Keep closed rows with an outcome and feed lessons learned |
Treating the register as a one-time deliverable
Risk exposure changes as work progresses. A risk about vendor sandbox access matters in the integration phase and is irrelevant after launch. Decide the review frequency up front. Many teams review the top risks weekly and the full register monthly. Tie the review to an existing meeting so it does not depend on anyone remembering. Reviews also need to produce changes. A review where nothing is edited usually means nobody looked closely.
Confusing risks, issues, assumptions, and constraints
If a row says "The vendor is late," the event has already happened, so it is an issue. It needs an action plan, not a probability. An assumption such as "the test environment will be ready by March" is a candidate for a risk, because you can ask what happens if it is false. A constraint such as a fixed launch date is not a risk, though it raises the impact of many risks. Audit the register for rows that fail the test "might this happen, and do we not know yet?"
Score inflation and score deflation
Teams that fear being blamed tend to inflate scores. Teams under schedule pressure tend to deflate them. Both distort ranking. Two habits help.
- Anchor the impact scale to numbers. For example, impact 3 means a slip of one to three weeks or a cost overrun of 2 to 5 percent, as defined in your scales.
- Record who scored the risk and the reasoning in a notes field. A score that cannot be explained cannot be challenged.
Also watch for optimism in a single owner's estimate. A second reviewer who questions the probability costs little.
Responses that do not change anything
"Mitigate" is a strategy, not a plan. A good response states an action that lowers probability or impact, who does it, and by when. After the action is done, re-score the risk. If the score does not drop, the action did not work and you need another one. Also check for secondary risks, because a response such as adding a second vendor creates new risks of its own.
A register nobody reads
If reports contain the whole register, readers skim and miss what matters. Report the top risks, the changes since last time, risks that crossed an escalation threshold, and decisions needed. A report that asks for a specific decision gets read. A report that only informs does not.
Automating a health check
A short script can catch the mechanical problems every cycle. This one assumes the register from earlier chapters, with one extra column, last_reviewed, holding an ISO date. Here is a sample file saved as register.csv:
id,statement,probability,impact,owner,response,status,last_reviewed
R-001,"Because the payment vendor has no sandbox SLA, integration testing may be delayed, causing a two-week slip to launch",4,4,A. Rivera,Mitigate,Open,2026-11-20
R-002,"Lead designer absence",2,3,,Mitigate,Open,2026-08-15
R-003,"Because the data center contract ends in June, migration may not finish in time, causing extra hosting fees",3,5,M. Okafor,Transfer,Open,2026-10-01The script flags missing owners, statements that are not in cause-event-effect form, and open risks not reviewed within 30 days.
import csv
from datetime import date
MAX_AGE_DAYS = 30
def problems(row, today):
found = []
if not row["owner"].strip():
found.append("no owner")
statement = row["statement"].lower()
if not (statement.startswith("because") and "causing" in statement):
found.append("not in cause-event-effect form")
if row["status"] == "Open":
age = (today - date.fromisoformat(row["last_reviewed"])).days
if age > MAX_AGE_DAYS:
found.append(f"stale ({age} days since review)")
return found
today = date(2026, 11, 28) # use date.today() in real use
with open("register.csv", newline="") as f:
for row in csv.DictReader(f):
issues = problems(row, today)
if issues:
print(row["id"], "; ".join(issues))With the sample file, R-001 passes. R-002 is reported for all three problems, and R-003 is reported as stale (58 days). The script cannot judge whether a statement is good. It only catches structure, and a person must still read the content.
Good practices to adopt
- Keep the register short enough to discuss. If it holds hundreds of rows, merge duplicates and move low-scoring items to a watch list.
- Ask for new risks at every review. A standing agenda item such as "what has changed or what are we newly worried about" keeps identification going after kickoff.
- Record decisions, not only scores. Note why a risk was accepted, escalated, or closed.
- Use the register in planning. Check it when you estimate, set reserves, or sequence work. If planning never refers to it, the register is not doing its job.
- Close risks explicitly. Mark each as occurred, expired, or retired, with a date and a short outcome note.
- Capture lessons while memory is fresh. Which risks occurred, which responses worked, and which risks were missed all feed the next project's checklist.
- Make it safe to report bad news. If raising a risk gets someone blamed, they will stop raising risks.
Exercise
A register row reads "Server outage" with owner "IT", probability 5, impact 5, response "Mitigate", and a last-reviewed date four months ago. Name four problems with this row and describe how to fix each.
Show answer
(1) The statement is vague and not in cause-event-effect form; rewrite it, for example "Because the primary server has no failover, a hardware fault may take the service offline, causing missed customer commitments." (2) The owner is a group, not a person; assign one named individual who accepts the role. (3) The 5/5 scores look inflated or unexplained; re-score against the defined scale thresholds and note the reasoning. (4) The row is stale and has no concrete action; review it now, add a specific action with a date, and re-score after the action. If the outage has already occurred, move it to the issue log instead.
Exercise
Your weekly review keeps ending with "no changes." Give two possible causes and one change you would make to the meeting.
Show answer
Possible causes: attendees are not looking for new risks, and owners are not updating their rows before the meeting. Another valid cause is that scores are too coarse to move. One change: add a standing agenda item asking for new or changed risks, and require owners to update their rows beforehand so the meeting reviews changes rather than reading the list.