Residual and secondary risks
This chapter assumes you can write a risk statement, score a risk on a probability-impact matrix, and pick a response strategy. It covers what remains after you respond to a risk (residual risk) and the new risks your response can create (secondary risks). Both belong in the register. If you leave them out, the register shows a safer project than the one you are running.
Why a response does not end a risk
A response rarely removes a risk completely. Mitigation lowers probability or impact, but not to zero. Transfer shifts the financial burden, but the schedule and reputation effects often stay with you. Even avoidance can leave something behind, because dropping a feature to dodge a technical risk may create a gap with the customer.
Two terms describe what is left over:
- Residual risk is the risk that remains after a response has been carried out. It is the same risk, re-scored.
- Secondary risk is a new risk that arises because of the response. It is a different risk, with its own cause, event, and effect.
A third idea is often confused with these. The inherent risk is the exposure before any response, the score you assigned when you first rated the risk. Residual risk is measured against it.
Residual risk
Record residual risk by adding a second set of ratings to the register. The original probability and impact stay as they are. The new columns hold your estimate of what the ratings will be once the response works.
Here is the payment vendor risk (R-001) from the earlier register, with residual ratings added:
id,statement,probability,impact,response,res_probability,res_impact
R-001,"Because the payment vendor has no sandbox SLA, integration testing may be delayed, causing a two-week slip to launch",4,4,Mitigate,2,3The response here is to negotiate a test environment and start integration earlier. The team expects probability to drop from 4 to 2 and impact from 4 to 3. The inherent score is 16 (High). The residual score is 6 (Low).
The script below computes both scores and the reduction. It reads the CSV above, saved as residual.csv.
import csv
def rating(score):
# Illustrative bands for a 5x5 matrix; each team sets its own.
if score >= 15:
return "High"
if score >= 8:
return "Medium"
return "Low"
with open("residual.csv", newline="") as f:
risks = list(csv.DictReader(f))
for r in risks:
inherent = int(r["probability"]) * int(r["impact"])
residual = int(r["res_probability"]) * int(r["res_impact"])
print(
r["id"],
"inherent", inherent, rating(inherent),
"residual", residual, rating(residual),
"reduction", inherent - residual,
)For R-001 this prints R-001 inherent 16 High residual 6 Low reduction 10.
Planned versus actual residual risk
The residual rating you write on day one is a forecast. It assumes the response will be carried out and will work. Until that happens, the real exposure is still the inherent score. Two practices keep this honest:
- Track the current score separately from the target residual score. The current score reflects the response's progress today. The target is where you expect to land.
- Do not lower the current score until the response action is complete or there is evidence it is working. A negotiated test environment that has not been delivered has not reduced anything.
Residual risk and appetite
The target residual score is where risk appetite enters the picture. If the residual score still sits above your tolerance, the response is not enough. You then have three options: strengthen the response, add a second response, or escalate the risk to someone with authority to accept it. Accepting a residual risk is a decision, and it should be recorded with the name of the person who made it.
Secondary risks
A secondary risk is created by the cure. The response action changes the project, and the change carries its own uncertainty.
Typical examples:
| Original risk | Response | Secondary risk |
|---|---|---|
| Data center contract ends before migration finishes | Transfer: pay a vendor to run the migration | Because the vendor is new to our systems, they may misconfigure access controls, causing a security incident |
| Lead designer is the only person who knows the legacy UI | Mitigate: add a second designer | Because a new designer needs onboarding, the lead may lose time to training, causing slower redesign progress |
| Vendor has no sandbox SLA | Avoid: switch to a different payment vendor | Because the new vendor has no track record with us, integration may expose unknown defects, causing a delay |
Each row follows the cause, event, effect format. A secondary risk is an ordinary risk. It gets its own ID, probability, impact, owner, and response.
Link secondary risks to their parent
Add a parent_id column, or a note in the statement, so a reader can trace the chain. Without the link, someone may later cancel the response without realizing a secondary risk depends on it, or close the parent and forget the child.
id,statement,probability,impact,owner,response,status,parent_id
R-004,"Because the replacement vendor has no track record with us, integration may expose unknown defects, causing a one-week delay",3,3,A. Rivera,Mitigate,Open,R-001When the secondary risk is worse
Sometimes the response costs more risk than it removes. Compare before you commit. Score the original risk, score the likely secondary risks, and ask whether the combined exposure goes down. Swapping a score-16 risk for a score-20 risk is not a response.
Adding the exposure to the numbers
Expected monetary value works for residual risk as well. Compute the EMV before and after the response. The difference is the value the response buys. Compare it with the cost of the response itself.
# EMV = probability x cost if the risk occurs
inherent_emv = 0.40 * 50000 # before response
residual_emv = 0.15 * 30000 # after response
response_cost = 8000
benefit = inherent_emv - residual_emv
print(inherent_emv) # 20000.0
print(residual_emv) # 4500.0
print(benefit) # 15500.0
print(benefit - response_cost) # 7500.0The response costs 8,000 and removes 15,500 of expected loss, so it is worth doing on these numbers. If the benefit were smaller than the cost, accepting the risk or choosing a cheaper response would be a better choice. Remember to include the EMV of any secondary risks in the comparison.
Common errors
- Scoring residual risk optimistically. Teams write a low target and treat it as current. Keep current and target separate.
- Forgetting secondary risks. The response plan is read as good news and nobody asks what it disturbs. Ask "what could this action cause?" every time you approve a response.
- Overwriting the inherent score. If you replace the original rating, you lose the evidence of what the response achieved and cannot judge whether it was worth the cost.
- Leaving secondary risks unowned. The person who owns the response action is often the best owner of its side effects.
- Treating residual risk as zero. Some risks stay Medium after every sensible action. Record that and get it accepted explicitly.
Review habits
At each review cycle, check these for every risk with a response in progress:
- Has the response action been completed, and is there evidence it worked?
- Does the current score match that evidence?
- Is the residual score within tolerance?
- Have any secondary risks been added, linked, and assigned?
Exercise
A team's risk R-010 has inherent probability 4 and impact 5. They plan to mitigate it by adding a backup supplier, and they rate the target residual as probability 2 and impact 5. They also notice that qualifying the backup supplier may overload the quality team and delay other deliveries. The backup supplier contract has been signed but no orders have been placed. What is the inherent score, the target residual score, and what should the current score be? What else must be added to the register?
Show answer
The inherent score is 4 x 5 = 20. The target residual score is 2 x 5 = 10. The current score should stay at 20 (or very close to it), because the response has not yet shown any effect: a signed contract with no orders placed does not yet reduce the chance of a supply failure. Add a secondary risk for the quality team overload, written as cause, event, and effect, with its own owner, scores, and response, and link it to R-010 through a parent ID.
Exercise
A response costs 12,000. It lowers a risk's EMV from 30,000 to 21,000. Is the response worth it on EMV alone, and what should you check before deciding?
Show answer
The benefit is 30,000 - 21,000 = 9,000, which is less than the 12,000 cost, so on these numbers it is not worth it. Before deciding, check whether the response creates secondary risks that add to the exposure, whether a cheaper response gives a similar reduction, and whether non-monetary factors such as safety or reputation justify the spend.