Sub topic 14
Keeping the register alive: review cadence
This chapter assumes you can already write risk statements, score risks on a probability-impact matrix, and pick a response strategy. Here we cover what happens after the first version of the register exists: how often to look at it, what to do in each review, and how to notice when it has gone stale.
Why a register decays
A register is a snapshot of what the team knew on the day it was written. Every week afterward, the project changes in ways that affect the entries:
- Probabilities shift as work proceeds. A vendor risk drops once the contract is signed.
- New risks appear that nobody listed at the start.
- Response actions finish, slip, or fail.
- Some risks occur and become issues.
If nobody revisits the register, scores stop matching reality. Stakeholders then either distrust the numbers or stop reading the register. A fixed review cadence prevents this. A cadence is a repeating schedule with a defined agenda and a named person responsible for running it.
Choosing a cadence
There is no universal interval. Set it from how fast the project changes and how severe the exposure is. The table shows common starting points.
| Project situation | Full register review | Top-risk check |
|---|---|---|
| Short project, fast change (sprints, launches) | Every 2 weeks | Weekly or in each stand-up |
| Typical multi-month project | Monthly | Weekly or every 2 weeks |
| Long, slow-moving program | Quarterly | Monthly |
| Any project entering a critical phase (go-live, cutover) | Temporarily more frequent | Daily or weekly |
Use two layers. A short, frequent check covers only the highest-rated risks and any risks with an approaching trigger. A fuller, less frequent review covers every open entry. You can also tie review frequency to rating: High risks weekly, Medium every two weeks, Low monthly. This keeps effort on the risks that matter and still guarantees that low-rated entries get looked at.
Event-driven reviews
Calendar reviews are not enough. Some events should trigger an immediate review regardless of schedule:
- A risk occurs, or a trigger condition is observed.
- A major scope, schedule, or budget change is approved.
- A phase gate or milestone is reached.
- A key person, vendor, or sponsor changes.
- An incident or near miss happens, on this project or a similar one.
Treat the calendar as the minimum and these events as extra reviews on top of it.
The review cycle
A review follows the same steps each time, so the output is predictable. The diagram shows one pass.
Step 1: Check actions and triggers
For each risk, ask the owner whether the planned actions are on schedule. Also ask whether any trigger has fired. An overdue action is itself a signal: the risk's residual exposure is probably higher than the register says.
Step 2: Reassess scores
Re-rate probability and impact using the same scales as before. Change a score only when you can name what changed, and write that reason in a notes or history field. Scores that move with no stated reason make trends impossible to trust.
Step 3: Scan for new risks
Spend a few minutes asking what has changed since last time. Prompts that work well:
- What did we learn in the last two weeks that surprised us?
- Which assumptions have we not checked yet?
- Did any response action create a secondary risk?
New entries get a full risk statement, an owner, and an initial score before the meeting ends.
Step 4: Decide on escalation or closure
Risks that exceed your authority or tolerance go up to the sponsor or steering group. Risks that can no longer happen, or have already occurred and moved to the issue log, are closed with a recorded reason. Chapters on reporting and closure cover these decisions in detail.
Step 5: Update and publish
Make the register changes during the meeting, not afterward. Updates written from memory a day later lose detail. Publish the new version where stakeholders look for it and note the review date.
Fields that support the cadence
The core register from earlier chapters needs a few extra columns to run reviews well:
last_reviewed: the date someone last confirmed or re-scored the entry.next_review: optional, derived from the rating-based interval.notesor history: why a score changed and what was decided.trigger: the observable sign that the risk is about to occur.
A version history, even just dated copies or a change log, lets you show how the risk profile moved over time.
Detecting stale entries automatically
An entry that nobody has reviewed within its interval is stale. You can find these with a short script. This one reads a register with a last_reviewed column and lists open risks that exceed the interval for their rating band.
import csv
import io
from datetime import date
# Sample data stands in for a real file; replace with open("register.csv").
DATA = """id,score,owner,status,last_reviewed
R-001,16,A. Rivera,Open,2026-11-02
R-002,6,J. Chen,Open,2026-10-01
R-003,15,M. Okafor,Open,2026-11-20
"""
# Illustrative bands and intervals; each team sets its own.
INTERVAL_DAYS = {"High": 7, "Medium": 14, "Low": 30}
def rating(score):
if score >= 15:
return "High"
if score >= 8:
return "Medium"
return "Low"
today = date(2026, 11, 28)
for row in csv.DictReader(io.StringIO(DATA)):
if row["status"] != "Open":
continue
band = rating(int(row["score"]))
age = (today - date.fromisoformat(row["last_reviewed"])).days
limit = INTERVAL_DAYS[band]
if age > limit:
print(f'{row["id"]} {band} {age} days since review '
f'(limit {limit}) owner {row["owner"]}')With the sample data, all three risks are overdue:
R-001 High 26 days since review (limit 7) owner A. Rivera
R-002 Low 58 days since review (limit 30) owner J. Chen
R-003 High 8 days since review (limit 7) owner M. OkaforRun a check like this before each meeting and send the list to the owners, so the review starts with the overdue entries.
Common errors
- Reviewing only the top of the list. Low-rated risks can rise unnoticed. Keep a slower pass over everything.
- Rubber-stamping. Changing
last_reviewedwithout discussing the risk makes the register look current while it isn't. Require a note or a decision for each entry touched. - The facilitator is also the only owner. If the project manager answers for every risk, owners stop engaging. Ask each owner to report their own entries.
- Rescoring without evidence. Lowering scores to make the dashboard look better hides exposure. Tie each change to an observed fact.
- Skipping reviews under pressure. The weeks when the project is under the most stress are when risks move fastest. Shorten the review instead of cancelling it.
Practical checklist
- Decide the cadence and write it into the risk management approach.
- Name the person who runs the review and the one who maintains the file.
- Add
last_reviewedand history fields to the register. - Prepare an overdue list before each meeting.
- Record decisions in the meeting, then publish the updated version.
Exercise
Your project has a High risk last reviewed 12 days ago, with a weekly interval for High risks. The owner says nothing has changed. What should you do in the review, and what should you record?
Show answer
Review it anyway, because it is overdue. Ask the owner for evidence: are the response actions on schedule, and has the trigger been checked? If the score stays the same, record that the risk was reassessed on the current date, with a short note stating why it is unchanged (for example, "vendor contract still unsigned; actions on track"). Update last_reviewed. Do not just change the date without a discussion and a note.
Exercise
Name two events that should trigger a review outside the normal calendar, and explain why waiting for the next scheduled review is risky for one of them.
Show answer
Examples: a risk occurs or its trigger fires, a major scope or schedule change is approved, a key vendor or team member changes, or a phase gate is reached. If a trigger fires and the team waits two weeks, the contingency plan may be started late, so the impact grows before anyone acts.