Sub topic 10
Choosing a response strategy
This chapter assumes you can write a risk statement, score probability and impact, and read a risk matrix. Those steps give you a ranked list. Here you decide what to do about each risk on it.
What a response strategy is
A response strategy is the overall approach you take to a risk. It differs from the response actions that carry it out, which a later chapter covers. "Mitigate" is a strategy. "Book the vendor's paid sandbox by 15 March" is an action.
Choose the strategy first. Without it, people write actions that don't match the intent, such as a long mitigation plan for a risk the sponsor has already decided to accept.
The four threat strategies
| Strategy | What you do | Typical example | What remains |
|---|---|---|---|
| Avoid | Remove the cause or change the plan so the risk cannot occur | Drop the unreliable vendor and build the feature in-house | Usually nothing, but you may create new risks |
| Mitigate | Reduce probability, impact, or both | Pay for a test environment and start integration earlier | Residual risk |
| Transfer | Shift the financial consequence to a third party | Insurance, a fixed-price contract, a warranty | The risk itself, and often some management effort |
| Accept | Take no action now, or prepare a fallback | Note a low-scoring risk and monitor it | The full risk |
Two points tend to catch people out:
- Transfer moves the cost, not the risk. If a subcontractor misses a deadline under a fixed-price contract, you may recover money, but your launch date still slips.
- Accept comes in two forms. Passive acceptance means you do nothing and deal with the outcome if it happens. Active acceptance means you set aside time or money, or write a contingency plan, to use if it happens. The chapter on triggers and contingency covers the active form.
Some frameworks add a fifth threat response, escalate. You use it when the risk sits outside your authority or would affect other projects. Escalation hands ownership to someone with the authority to respond. It does not make the risk go away.
Strategies for opportunities
A register can also hold positive risks. Each threat strategy has a mirror image:
| Threat strategy | Opportunity strategy | Meaning |
|---|---|---|
| Avoid | Exploit | Make sure the opportunity happens |
| Mitigate | Enhance | Raise its probability or benefit |
| Transfer | Share | Partner with someone better placed to capture it |
| Accept | Accept | Take it if it comes, without chasing it |
If you track opportunities, use the same fields and the same scoring scales. Keep the strategy names distinct so a reader can tell "mitigate" (threat) from "enhance" (opportunity).
A decision path
Start with the score and the appetite, then ask the questions in order. The diagram shows one workable sequence. Treat it as a prompt for discussion, not a rule.
The appetite check connects this chapter to the earlier one on risk appetite. A risk that scores 6 on a matrix where "Low" means under 8 can be accepted without debate. A risk that scores 16 usually needs a stronger response than acceptance.
Matching strategy to the risk
Several factors decide between strategies. Consider them together.
- Score and band. High risks need an active strategy. Low risks are usually accepted. The middle band is where judgment matters.
- Cost of the response against the exposure. Spending 30,000 to prevent a 20,000 exposure rarely makes sense.
- Time to impact. A risk that could hit next week leaves no room for a slow mitigation. You may need to avoid it or accept it with a fallback.
- Controllability. If you cannot influence the cause, such as a regulator's decision, mitigation is weak. Transfer, acceptance, or a contingency plan fit better.
- Side effects. Every response can create a new risk. Avoiding the vendor can create a staffing risk. That is a secondary risk, covered in a later chapter.
Comparing options with expected value
When cost data exists, you can compare options using expected monetary value (EMV), which is probability multiplied by the cost if the risk occurs. The benefit of a response is the drop in EMV it buys, minus what it costs. The script below compares three options for R-001 from the sample register, where the payment vendor's missing sandbox could cost 50,000.
def net_benefit(prob_before, prob_after, cost_if_occurs, response_cost):
"""Reduction in expected loss, minus the cost of the response."""
reduction = (prob_before - prob_after) * cost_if_occurs
return reduction - response_cost
# name, probability now, probability after response, cost if it occurs, response cost
options = [
("Mitigate: pay for a vendor sandbox", 0.40, 0.15, 50000, 8000),
("Avoid: replace the vendor", 0.40, 0.0, 50000, 30000),
("Accept: do nothing", 0.40, 0.40, 50000, 0),
]
for name, before, after, cost, response in options:
print(f"{name}: {net_benefit(before, after, cost, response):.0f}")The output is:
Mitigate: pay for a vendor sandbox: 4500
Avoid: replace the vendor: -10000
Accept: do nothing: 0Mitigation wins here. Avoidance removes the whole risk but costs more than the exposure it removes.
Recording the decision
Record the strategy as its own field in the register. This is the response column in the sample CSV. Use a fixed list of values so you can filter and count, for example Avoid, Mitigate, Transfer, Accept, and Escalate. Keep the reasoning in a separate note field or the review minutes. A strategy with no stated reason is hard to challenge at the next review.
Common errors
- Defaulting to Mitigate. Teams often write "mitigate" for every risk, which hides the real decision. If a risk is truly accepted, say so.
- Treating Transfer as Avoid. After you buy insurance, you still have a schedule risk. Keep the risk open if non-financial effects remain.
- Accepting a high risk without sign-off. Acceptance above appetite should be recorded with a named decision-maker, not left to the risk owner alone.
- Strategy without action. A line that says "Mitigate" with no actions is an intention, not a response. The next chapter covers how to attach owners and actions.
- Never revisiting the strategy. A risk accepted in month two may deserve mitigation in month six, once the date gets closer. The review cadence chapter covers this.
Exercise
A risk statement reads: "Because the regulator may change reporting rules next quarter, our compliance module may need rework, causing a four-week delay." It scores 20 (High). The team cannot influence the regulator and the rework cost cannot be insured. Which strategy or strategies fit, and why is plain Accept a poor choice?
Show answer
The team cannot remove the cause, so Avoid is out. Transfer is not available because no insurer or contract will take the delay. Mitigation is limited because the cause is outside the team's control, but it can still reduce the impact, for example by designing the module so the reporting rules sit in configuration and can change without a rewrite. If the delay would affect other programs or need budget beyond the team's authority, Escalate as well. Plain Accept is a poor choice because the score is above appetite. If acceptance is used at all, it should be active acceptance with a contingency plan and a named approver.
Exercise
Option A costs 12,000 and lowers a risk's probability from 0.50 to 0.20. Option B costs 3,000 and lowers it from 0.50 to 0.40. The cost if the risk occurs is 60,000. Which option has the higher net benefit?
Show answer
Option A: (0.50 - 0.20) x 60,000 = 18,000, minus 12,000 gives 6,000. Option B: (0.50 - 0.40) x 60,000 = 6,000, minus 3,000 gives 3,000. Option A has the higher net benefit.