Sub topic 8
Scoring and ranking with a risk matrix
This chapter assumes you can already write a risk statement in cause-event-effect form and that you have defined 1-5 probability and impact scales for your project. It also assumes you know your organization's risk appetite, at least roughly. Here you turn those ratings into a score, place each risk on a matrix, and produce a ranked list the team can act on.
What scoring is for
A register with thirty risks cannot be worked on all at once. Scoring answers one question: which risks get attention first? It does not predict the future. It gives a repeatable way to sort risks so that discussion focuses on the few that matter most.
The usual method has three steps:
- Rate probability (1-5) and impact (1-5) for each risk.
- Multiply the two numbers to get a score from 1 to 25.
- Map the score to a rating band (Low, Medium, High) and sort.
The probability-impact matrix
A matrix lays the same arithmetic out as a grid. Probability runs up the side and impact runs across the top. Each cell shows the score and its band. The bands below match the ones used in the script later in this chapter: 15 or more is High, 8 to 14 is Medium, and below 8 is Low.
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 5 Low | 10 Medium | 15 High | 20 High | 25 High |
| 4 | 4 Low | 8 Medium | 12 Medium | 16 High | 20 High |
| 3 | 3 Low | 6 Low | 9 Medium | 12 Medium | 15 High |
| 2 | 2 Low | 4 Low | 6 Low | 8 Medium | 10 Medium |
| 1 | 1 Low | 2 Low | 3 Low | 4 Low | 5 Low |
The band boundaries are a decision, not a law. Your risk appetite sets them. A cautious organization might make 10 the High threshold. A tolerant one might use 20. Whatever you choose, write the bands down and keep them the same for the whole project, or scores from different months will not be comparable.
Many teams color the cells (green, amber, red). That helps people scan the grid, but never rely on color alone. Print the score or band name in each cell, as in the table above, so the matrix still works in grayscale and for color-blind readers.
Scoring the example register
Here is the register from earlier chapters, saved as register.csv:
id,statement,probability,impact,owner,response,status
R-001,"Because the payment vendor has no sandbox SLA, integration testing may be delayed, causing a two-week slip to launch",4,4,A. Rivera,Mitigate,Open
R-002,"Because the lead designer is the only person who knows the legacy UI, their absence may stall redesign work, causing rework cost",2,3,J. Chen,Mitigate,Open
R-003,"Because the data center contract ends in June, migration may not finish in time, causing extra hosting fees",3,5,M. Okafor,Transfer,OpenThis script scores and ranks it:
import csv
def rating(score):
# Illustrative bands for a 5x5 matrix; each team sets its own.
if score >= 15:
return "High"
if score >= 8:
return "Medium"
return "Low"
with open("register.csv", newline="") as f:
risks = list(csv.DictReader(f))
for r in risks:
r["score"] = int(r["probability"]) * int(r["impact"])
r["rating"] = rating(r["score"])
for r in sorted(risks, key=lambda r: r["score"], reverse=True):
print(r["id"], r["score"], r["rating"], r["owner"])The output is:
R-001 16 High A. Rivera
R-003 15 High M. Okafor
R-002 6 Low J. ChenR-001 scores 4 x 4 = 16. R-003 scores 3 x 5 = 15. R-002 scores 2 x 3 = 6. Two risks land in the High band, and one is Low.
Gotchas in multiplying scales
Multiplication is convenient, but it hides several problems. Know them before you trust a ranked list.
Equal scores are not equal risks
A probability of 5 with impact 3 and a probability of 3 with impact 5 both score 15. The first is a frequent annoyance. The second is a rare disaster. Treating them as the same can be a mistake, because your response strategy will likely differ: you may accept the first and transfer the second.
A simple tie-breaker is to rank by score first and then by impact. Another common rule is to flag any risk with impact 5 for review, whatever its band. The next script applies both ideas:
import csv
def rating(score):
if score >= 15:
return "High"
if score >= 8:
return "Medium"
return "Low"
with open("register.csv", newline="") as f:
risks = list(csv.DictReader(f))
for r in risks:
r["probability"] = int(r["probability"])
r["impact"] = int(r["impact"])
r["score"] = r["probability"] * r["impact"]
r["rating"] = rating(r["score"])
r["flag"] = "REVIEW" if r["impact"] == 5 else ""
ranked = sorted(risks, key=lambda r: (r["score"], r["impact"]), reverse=True)
for r in ranked:
print(f'{r["id"]:6} {r["score"]:3} {r["rating"]:7} {r["owner"]:10} {r["flag"]}')Ordinal scales are not real numbers
The numbers 1 to 5 are labels for ordered levels. They are not measurements. A "4" probability is not necessarily twice as likely as a "2". Multiplying labels gives a useful sort order, but the score has no unit and you should not average or add scores to report "total project risk". If you need real quantities, use the expected monetary value method from the next chapter on cost data.
Scales must be anchored
If one person's "impact 4" means a one-week delay and another's means a one-month delay, the scores are noise. Each level needs a written definition, such as "3 = one to two weeks of schedule slip or up to 5% of budget". Those definitions come from the scale chapter. Without them the matrix looks precise but is not.
Scoring one dimension of impact
Impact can touch schedule, cost, scope, and quality. A common approach is to rate each and take the highest as the single impact value. This keeps a risk that is cheap but devastating to the schedule from being scored down.
Score drift and optimism
People tend to rate risks they own lower than outsiders would. Scoring in a group, with at least one person who does not own the risk, reduces this. Record the date of each scoring, because a score is only valid for the moment it was made.
Using the ranking
The ranked list drives decisions:
- High: needs a named owner, a response plan, and visibility to the sponsor or steering group.
- Medium: needs an owner and a response, usually managed within the project team.
- Low: is watched, often with a simple "accept" response, and reviewed on a slower cycle.
The matrix also supports the next step. Once a risk is ranked, you choose a response strategy for it, and the score tells you how much effort is justified. A response that costs more than the risk's plausible damage is a bad trade.
Score the register after every significant change: a new risk, a finished response action, or a change in scope. A ranking from three months ago is a historical record, not a guide.
Exercise
A project has three risks. R-A has probability 5 and impact 2. R-B has probability 2 and impact 5. R-C has probability 3 and impact 3. Using the bands in this chapter (15 or more High, 8 to 14 Medium, below 8 Low), give each risk's score and band. Then rank them using score first and impact as the tie-breaker, and say which would be flagged for review under the "impact 5" rule.
Show answer
R-A scores 5 x 2 = 10 (Medium). R-B scores 2 x 5 = 10 (Medium). R-C scores 3 x 3 = 9 (Medium). R-A and R-B tie at 10, so impact breaks the tie: R-B ranks first, then R-A, then R-C. R-B is flagged for review because its impact is 5, even though it is only Medium.
Exercise
Why can two risks with the same score need different responses, and what in the register helps you notice this?
Show answer
The score combines probability and impact, so a frequent minor risk and a rare severe risk can both score the same. They call for different responses, such as accepting the minor one and transferring or mitigating the severe one. Keeping the separate probability and impact columns in the register, and using impact as a tie-breaker or review flag, makes the difference visible.