Sub topic 5
Reading Variance: Planned Versus Actual
Assume you know basic project terms such as scope, schedule, budget, task, and milestone. You should also be comfortable reading a task list, Gantt chart, or sprint board and doing simple arithmetic.
A variance is the difference between what the plan says should have happened and what actually happened. Variance analysis turns a progress update into a decision. A small difference may need monitoring. A persistent or important difference may need corrective action, a change request, or a new baseline.
Compare like with like
Use the approved baseline as the reference point. Compare the same scope, time period, and measurement unit.
For example, a useful weekly comparison might include:
| Measure | Planned by Friday | Actual by Friday | Variance |
|---|---|---|---|
| Design tasks complete | 6 | 5 | -1 task |
| Approved design pages | 20 | 16 | -4 pages |
| Cost spent | $12,000 | $14,000 | +$2,000 |
| Milestones complete | 2 | 1 | -1 milestone |
A negative completion variance means less work is complete than planned. A positive cost variance in this table means more money was spent than planned. The meaning of a positive or negative sign depends on the measure, so always label the direction clearly.
A percentage variance makes different measures easier to compare:
variance percentage = (actual - planned) / planned × 100
If 16 of 20 design pages are complete, the completion variance is:
(16 - 20) / 20 × 100 = -20%
The team has completed 20% less work than planned for that checkpoint.
Read schedule variance
Schedule variance can appear in several forms:
- Date variance: a task or milestone finished later or earlier than its baseline date.
- Duration variance: work took longer or shorter than estimated.
- Completion variance: less or more work is complete than the plan expected.
- Value-based schedule variance: earned value minus planned value.
A milestone planned for May 10 that finishes on May 14 has a four-day delay. That delay matters more if the milestone controls later work or a contractual delivery date.
Do not treat every late task as a late project. Check the schedule logic. A task may be late but have float, which is time available before it delays a successor. A task on the critical path has less or no usable float, so its delay can move the project finish date.
Read cost variance
Cost variance compares the value of completed work with the cost paid for it. In earned value management:
CV = EV - AC
Here, EV is earned value, the budgeted value of completed work. AC is actual cost, the amount spent on that work.
Suppose a work package has a budget of $10,000. The team completed 40% of it, so EV is $4,000. If the team spent $4,500, then:
CV = $4,000 - $4,500 = -$500
The negative result means the team spent $500 more than the budgeted value of the work completed. This is an unfavorable cost variance.
A cost variance can come from higher rates, rework, waste, inaccurate estimates, or scope that was added without approval. Investigate the cause before choosing a response.
Decide whether a variance matters
Use thresholds agreed before execution. For example, a project might investigate any schedule variance greater than five working days or any cost variance greater than 10%.
Also consider impact, trend, and cause:
- Impact: Does the variance affect a key milestone, quality, compliance, or customer commitment?
- Trend: Is the gap shrinking, stable, or growing each reporting period?
- Cause: Is the cause temporary, recurring, or likely to affect other work?
- Recoverability: Can the team recover without changing scope, budget, or the finish date?
A one-time $200 overspend may need only a note. A growing cost gap caused by a supplier rate increase may require a forecast update and a decision from the sponsor.
Use variance in the status report
A useful report states the baseline, the actual result, the size and direction of the gap, the cause, and the decision needed.
Example:
> The payment integration is 20% behind the planned completion level at the end of week four. The main cause is rework from an external API change. The team will add a technical review before the next build. The project manager requests approval to move system testing by three days if the API change is not resolved by Wednesday.
This format connects measurement to action instead of merely reporting bad news.
Exercise
A task had a planned value of $8,000. Its earned value is $6,000, and its actual cost is $7,500. What are the schedule variance and cost variance, and what do they indicate?
Show answer
SV = EV - PV = $6,000 - $8,000 = -$2,000, so less work was completed than planned. CV = EV - AC = $6,000 - $7,500 = -$1,500, so the completed work cost more than its budgeted value.