Sub topic 10
Choosing a Corrective Action
Assume you know basic project terms such as scope, schedule, budget, task, risk, and issue. You should also be able to read a task list or sprint board and calculate simple variances.
A variance is a difference between the plan and the current result. A corrective action is a change to the way the team works so that the project can move closer to its approved targets. Good corrective action addresses the cause of the variance, not only its visible symptom.
For example, adding people to a late task may help, but it may not solve the problem if unclear requirements caused the delay. First understand the variance. Then choose the smallest action that can correct it without creating a larger problem.
Diagnose before acting
Review these questions:
- What changed from the baseline?
- Is the difference real, or is the progress data late or measured inconsistently?
- What caused the difference?
- Is the cause temporary, or will it continue?
- Which project target is affected: scope, schedule, cost, quality, or risk?
- Can the project manager act within the approved plan?
Separate a risk from an issue. A risk is an uncertain event that may happen. An issue is a problem that has already happened. A late supplier delivery is an issue. The possibility of another late delivery is a risk.
Use a cause-and-effect review, a short team discussion, or the “five whys” technique. The five whys repeatedly ask why a problem occurred until the team reaches a process or planning cause.
Match the action to the cause
Common corrective actions include:
| Cause or condition | Suitable action |
|---|---|
| Work is blocked by a missing decision | Assign a decision owner and set a decision date |
| A task is larger than expected | Split the task and revise the near-term sequence |
| A specialist is overloaded | Reassign work or adjust resource priorities |
| Requirements are unclear | Hold a clarification session and update acceptance criteria |
| The delivery method is inefficient | Remove the bottleneck or change the workflow |
| Approved scope has grown | Raise a change request before committing more work |
Do not treat every unfavorable variance as a reason to add resources. Extra people can increase coordination time, cost, and defects. A schedule recovery plan should state the action, owner, due date, expected effect, and measure that will show whether the action worked.
A useful action record looks like this:
Variance: Testing is five days behind plan.
Cause: Test data was not available when testing began.
Action: The data owner will provide an approved test-data set by Wednesday.
Owner: Priya
Expected effect: Testing resumes Thursday and finishes within the current release window.
Check: Review completed test cases at Friday's status meeting.Decide whether control is needed
Corrective action stays within the approved baseline when it changes execution without changing the agreed scope, budget, or target dates. Examples include resequencing tasks, removing a bottleneck, or assigning an available team member.
Use change control when the proposed response changes an approved commitment. A change request may be needed to:
- Add or remove deliverables.
- Extend a deadline.
- Increase the budget.
- Change acceptance criteria.
- Accept a reduction in quality or performance.
- Move work to a later release.
A change request should explain the reason, options, impact, recommendation, and decision required. Do not quietly update the plan to make a variance disappear. That hides the project's real condition.
Rebaseline only after an authorized change has been approved. A rebaseline creates a new approved plan for future measurement. Keep the old baseline so the team can explain the original variance.
Check that the action worked
Track the action at the next agreed reporting point. Compare the new result with the same measurement rule used before. If the variance is shrinking, continue monitoring. If it is unchanged or growing, reassess the cause and choose another response.
A status report should state the variance, cause, action, owner, expected result, and decision needed. This gives sponsors enough information to support the project without turning the report into a list of unexplained numbers.
Exercise
A project is two weeks late because a newly requested feature was added informally. Should the team simply work longer hours, or should it use change control? Explain.
Show answer
It should use change control because the added feature changes approved scope and may affect schedule and cost. The team should document the impact and obtain an authorized decision before updating the plan.