Sub topic 11
Change Control and When to Rebaseline
Assume you know basic project vocabulary, can read a task list or Gantt chart, and can calculate simple variances. This chapter focuses on how to decide whether a difference from the plan needs routine correction, formal approval, or a new baseline.
The baseline is a controlled promise
A baseline is the approved version of the project plan used for comparison. It normally records:
- The scope baseline: approved deliverables and requirements.
- The schedule baseline: planned dates, sequencing, and milestones.
- The cost baseline: approved budget spread across the work and time.
Progress measurements such as schedule variance and cost variance are meaningful only when compared with a stable baseline. If team members quietly change planned dates or budget values, the project can appear healthy without actually improving.
A variance is a difference between the current result and the baseline. A variance does not automatically mean the plan should change. First determine whether the difference comes from execution, an approved scope change, a planning error, or an external event.
Change control protects the plan
Change control is the process for evaluating and approving changes to the project. A change request should explain what is changing and why. It should also show the effect on scope, schedule, cost, quality, resources, risks, and dependencies.
A practical change-control flow looks like this:
The decision maker may be a project sponsor, change control board, product owner, or another role defined by the organization. The person who notices a change should not necessarily be the person who approves it.
Corrective action is different from a change request
Use corrective action when the approved scope and target remain valid but execution is off track. For example, a delayed task might require another engineer, a simpler implementation, or resequenced work. These actions try to return performance to the existing baseline.
Use a change request when someone wants to alter the approved project. Examples include adding a feature, removing a deliverable, moving a contractual deadline, or changing an acceptance criterion.
| Situation | First response | Baseline action |
|---|---|---|
| Work is late but scope and deadline remain valid | Corrective action | Keep the baseline |
| Sponsor adds a required feature | Analyze a change request | Update after approval |
| A regulatory rule changes the required output | Analyze external change | Rebaseline approved impact |
| Team discovers an arithmetic error before execution | Correct the plan through governance | Replace the faulty baseline with approval |
Do not rebaseline simply because performance is poor. Rebaselining can hide the original variance and remove useful accountability.
When to rebaseline
Rebaseline when an approved change makes the current plan no longer a valid representation of the work. Common triggers include:
- Approved scope added or removed.
- A major dependency or milestone changes.
- A contract, law, or business objective changes.
- The original estimate is proven materially wrong and the organization approves a revised plan.
- A recovery decision changes the authorized budget or completion date.
Before rebaselining, preserve the old baseline. Record the approval, effective date, reason, and exact changes. The old baseline provides an audit trail and explains why earlier reports showed different forecasts.
A rebaseline should be complete enough to maintain internal consistency. If the deadline moves but task dates and resource assumptions do not, the new baseline will still produce misleading variance. Update all affected scope, schedule, cost, and measurement rules together.
A disciplined decision
Use this sequence when a variance appears:
- Confirm the measurement and its source data.
- Identify the cause and whether it is inside the team's control.
- Estimate the effect of corrective action.
- Check whether the proposed response changes approved scope, dates, or budget.
- Submit a change request if it does.
- Apply the decision, update plans, and communicate the effective baseline.
- Report both the previous result and the new approved target.
The status report should distinguish actual performance before the change from performance measured against the new baseline. This prevents a baseline update from erasing the project history.
Exercise
A project is two weeks late because a supplier failed to deliver a component. The sponsor approves replacing the component with a more expensive alternative and moves the release date by one week. Should the team only take corrective action, or should it request a rebaseline?
Show answer
It should document and submit a change request. The approved component and release date change scope, cost, and schedule. After approval, the affected baselines should be updated, while the original baseline and the supplier-related variance remain in the project record.