Earned Value: PV, EV, AC, CPI, and SPI
Assume you know basic project terms such as scope, schedule, budget, and task. You should also be comfortable reading a task list or Gantt chart and calculating simple ratios.
Earned value management (EVM) compares three views of a project:
- What work was planned by a date.
- What work was actually completed by that date.
- What the completed work actually cost.
This makes schedule and cost performance comparable, even when tasks have different prices.
The three basic values
The values use the project performance measurement baseline, which is the approved plan for scope, schedule, and cost.
| Value | Meaning | Question answered |
|---|---|---|
| Planned value (PV) | Budgeted value of work scheduled by a date | How much work should be complete? |
| Earned value (EV) | Budgeted value of work actually complete | How much planned work is complete? |
| Actual cost (AC) | Cost actually paid or incurred for completed work | What did the completed work cost? |
The word value means budgeted value, not market value. For example, if a task has a budget of $10,000 and is 50% complete, its earned value is $5,000, whether the team spent $4,000 or $7,000.
The total approved project budget is called the budget at completion (BAC).
A worked example
Suppose a project has a BAC of $100,000. At the reporting date:
- The plan said that $50,000 of work should be complete, so PV is $50,000.
- The team completed $40,000 worth of planned work, so EV is $40,000.
- The team spent $45,000, so AC is $45,000.
The core formulas are:
- Cost variance (CV) = EV - AC
- Schedule variance (SV) = EV - PV
- Cost performance index (CPI) = EV / AC
- Schedule performance index (SPI) = EV / PV
For this project:
- CV = $40,000 - $45,000 = -$5,000
- SV = $40,000 - $50,000 = -$10,000
- CPI = $40,000 / $45,000 = 0.89
- SPI = $40,000 / $50,000 = 0.80
A negative variance is unfavorable. A positive variance is favorable. A CPI or SPI of 1.00 means performance matches the plan. A value below 1.00 is unfavorable, while a value above 1.00 is favorable.
The project is both over cost and behind schedule. Its CPI says that each $1.00 spent produced about $0.89 of planned work. Its SPI says the team completed work at 80% of the planned rate.
def evm(bac, pv, ev, ac):
cpi = ev / ac
spi = ev / pv
eac = bac / cpi
return {
"CV": ev - ac,
"SV": ev - pv,
"CPI": round(cpi, 2),
"SPI": round(spi, 2),
"EAC": round(eac),
"ETC": round(eac - ac),
"VAC": round(bac - eac),
}
print(evm(bac=100000, pv=50000, ev=40000, ac=45000))
# {'CV': -5000, 'SV': -10000, 'CPI': 0.89, 'SPI': 0.8, 'EAC': 112500, 'ETC': 67500, 'VAC': -12500}Interpreting the results
Schedule variance is expressed in money, even though it describes schedule performance. It does not directly mean that the project is exactly a certain number of days late. Use the schedule network and milestone dates to understand the time impact.
EVM is only as reliable as the progress measurements behind EV. If a task is reported as 90% complete for weeks, its EV may create a misleadingly positive result.
Common errors
- Counting money spent as earned value. Spending $45,000 does not create $45,000 of EV.
- Reporting percent complete without a defined measurement rule.
- Comparing current results with an outdated baseline after approved scope changes.
- Treating all tasks as equally valuable when calculating project-level EV.
- Ignoring scope growth. A burnup chart or change log may show that the target increased.
Use objective rules such as 0/100, weighted milestones, or completed units to calculate EV. Then connect a poor index to a cause, such as rework, late dependencies, inaccurate estimates, or added scope.
Exercise
A project has PV = $60,000, EV = $54,000, and AC = $48,000. Is it ahead or behind schedule and cost? Calculate SV, CV, SPI, and CPI.
Show answer
It is behind schedule because SV = -$6,000 and SPI = 0.90. It is under cost because CV = $6,000 and CPI = 1.125, or about 1.13.