Forecasting with EAC and ETC
Assume you know basic project management terms such as scope, schedule, budget, task, and earned value. This chapter uses simple arithmetic and assumes that the project has a performance measurement baseline.
Forecasting uses current project data to estimate the final result. Two important forecasts are:
- Estimate at completion (EAC): the expected total cost when all work is finished.
- Estimate to complete (ETC): the expected cost of the remaining work.
These forecasts help a project manager decide whether the approved budget is still realistic.
The values used in a forecast
Earned value management uses four main cost and progress values.
| Value | Meaning |
|---|---|
| BAC | Budget at completion, the approved budget for all planned work |
| PV | Planned value, the budgeted value of work scheduled by a date |
| EV | Earned value, the budgeted value of work actually completed |
| AC | Actual cost, the money actually spent by a date |
The most common forecast starts with the cost performance index (CPI):
CPI = EV / AC
A CPI below 1.0 means the project is receiving less planned work value for each unit of cost. A CPI above 1.0 means cost performance is better than planned.
When current cost performance is expected to continue, use:
EAC = BAC / CPI
Then calculate:
ETC = EAC - AC
The remaining budget is not always a reliable ETC. If the project has been inefficient so far, the remaining work may cost more than its original budget.
Worked example
Suppose a project has these values:
- BAC = $100,000
- PV = $50,000
- EV = $40,000
- AC = $45,000
The CPI is:
CPI = 40,000 / 45,000 = 0.89
The project is earning about 89 cents of planned value for every dollar spent. If that performance continues:
EAC = 100,000 / 0.89 = $112,500
ETC is:
ETC = 112,500 - 45,000 = $67,500
The project needs about $67,500 more, and the final cost is forecast to be $112,500. The variance at completion (VAC) is:
VAC = BAC - EAC = 100,000 - 112,500 = -$12,500
The negative VAC means the project is forecast to exceed its approved budget by $12,500.
def evm(bac, pv, ev, ac):
cpi = ev / ac
spi = ev / pv
eac = bac / cpi
return {
"CV": ev - ac,
"SV": ev - pv,
"CPI": round(cpi, 2),
"SPI": round(spi, 2),
"EAC": round(eac),
"ETC": round(eac - ac),
"VAC": round(bac - eac),
}
print(evm(bac=100000, pv=50000, ev=40000, ac=45000))
# {'CV': -5000, 'SV': -10000, 'CPI': 0.89, 'SPI': 0.8, 'EAC': 112500, 'ETC': 67500, 'VAC': -12500}Choosing the right EAC formula
The CPI formula assumes that past cost efficiency predicts future cost efficiency. That is useful when the cause of the variance is likely to continue.
Use a re-estimated remaining cost when the past variance was unusual and the remaining work has been reviewed. In that case:
EAC = AC + new ETC
A common alternative is:
EAC = AC + (BAC - EV)
This assumes the remaining work will finish exactly at its original budget rate. It is reasonable when the current problem was a one-time event.
A combined schedule-and-cost forecast is sometimes written as:
EAC = AC + (BAC - EV) / (CPI × SPI)
Use this cautiously. Schedule delay affects cost only when the delay creates additional spending, such as overtime, extended contracts, or extra staffing.
Using the forecast
Review EAC and ETC with the cause of the variance. A forecast alone does not explain what management should do. Check whether the issue comes from inaccurate estimates, scope growth, low productivity, a supplier problem, or a risk that has occurred.
Then decide whether to improve performance, request a scope or budget change, or accept the forecast. Record the assumption, owner, date, and next review point in the status report.
Exercise
A project has BAC = $80,000, EV = $30,000, and AC = $36,000. Assuming current cost performance continues, what are CPI, EAC, and ETC?
Show answer
CPI = 30,000 / 36,000 = 0.83. EAC = 80,000 / 0.83, or $96,000 when rounded. ETC = $96,000 - $36,000 = $60,000.