01Chapter 1: Break the work into measurable piecesA project plan cannot measure progress reliably if its work is described only as “build the feature” or “prepare the launch.” Break the scope into pieces that have a clear result, an owner, and a way to verify completion. This structure is called a work breakdown structure (WBS). A WBS is a hier3 min read
02Chapter 2: Fix a baseline to measure againstAssume you know basic project terms such as scope, schedule, budget, task, and milestone. You should also be comfortable reading a task list or Gantt chart and doing simple arithmetic.3 min read
03Chapter 3: Measuring progress: rules for percent completeAssume you know basic project terms such as scope, schedule, budget, task, and milestone. You should also be comfortable reading a task list or sprint board and doing simple arithmetic.3 min read
04Chapter 4: Tracking milestones and the scheduleAssume you know basic project terms such as scope, task, dependency, budget, and schedule. You should also be familiar with a task list, Gantt chart, or sprint board, and be comfortable with simple date calculations.4 min read
05Chapter 5: Reading variance: planned versus actualAssume you know basic project terms such as scope, schedule, budget, task, and milestone. You should also be comfortable reading a task list, Gantt chart, or sprint board and doing simple arithmetic.3 min read
06Chapter 6: Burndown and burnup charts for iterative workAssume you know basic project terms such as scope, task, schedule, and sprint. You should also be comfortable reading a task board and calculating simple differences and ratios.3 min read
07Chapter 7: Earned value: PV, EV, AC, CPI, and SPIAssume you know basic project terms such as scope, schedule, budget, and task. You should also be comfortable reading a task list or Gantt chart and calculating simple ratios.3 min read
08Chapter 8: Forecasting with EAC and ETCAssume you know basic project management terms such as scope, schedule, budget, task, and earned value. This chapter uses simple arithmetic and assumes that the project has a performance measurement baseline.3 min read
09Chapter 9: Turning variances into risks and issuesAssume you know basic project terms such as scope, schedule, budget, task, and baseline. You should also be comfortable reading a task list or sprint board and calculating simple ratios.3 min read
10Chapter 10: Choosing a corrective actionAssume you know basic project terms such as scope, schedule, budget, task, risk, and issue. You should also be able to read a task list or sprint board and calculate simple variances.3 min read
11Chapter 11: Change control and when to rebaselineAssume you know basic project vocabulary, can read a task list or Gantt chart, and can calculate simple variances. This chapter focuses on how to decide whether a difference from the plan needs routine correction, formal approval, or a new baseline.3 min read
12Chapter 12: Reporting status on a steady cadenceAssume you know basic project vocabulary, can read a task list or Gantt chart, and are comfortable with simple arithmetic and ratios. This chapter focuses on turning project data into a status report that supports decisions.3 min read