Sub topic 6
Burndown and Burnup Charts for Iterative Work
Assume you know basic project terms such as scope, task, schedule, and sprint. You should also be comfortable reading a task board and calculating simple differences and ratios.
What the charts show
A burndown chart shows how much work remains over time. The horizontal axis shows time, such as sprint days. The vertical axis shows remaining work, such as story points, tasks, or hours. A successful trend usually moves downward toward zero.
A burnup chart shows how much work has been completed over time. It often includes a second line for total scope. Completed work moves upward, while the scope line shows how much work the team is expected to deliver.
The two charts answer slightly different questions:
| Chart | Main question | Useful signal |
|---|---|---|
| Burndown | How much work remains? | Whether the team is on track to reach zero |
| Burnup | How much work has been completed? | Whether delivery is increasing and scope is changing |
Burndown charts are compact and easy to read. Burnup charts make scope growth visible. If new work is added, a burndown can appear to stall even when the team is delivering. A burnup chart shows completed work rising while the total-scope line rises too.
Build and read a burndown
Suppose a 10-day sprint starts with 40 story points. A straight ideal line would remove 4 points per day. At the end of day 4, the ideal remaining work is 24 points.
The team records 30 points remaining. The gap is:
30 - 24 = 6 points
The positive gap means more work remains than the ideal plan expected. It is a warning, not a final prediction. The team might recover by reducing work in progress, removing a blocker, splitting a large item, or negotiating scope.
This Python example compares actual remaining work with the ideal line:
total_points = 40
sprint_days = 10
actual_remaining = [40, 38, 35, 33, 30]
for day, remaining in enumerate(actual_remaining):
ideal = total_points - (total_points / sprint_days) * day
gap = remaining - ideal
print(f"day {day}: remaining={remaining}, ideal={ideal:.0f}, gap={gap:+.0f}")
# day 0: remaining=40, ideal=40, gap=+0
# day 1: remaining=38, ideal=36, gap=+2
# day 2: remaining=35, ideal=32, gap=+3
# day 3: remaining=33, ideal=28, gap=+5
# day 4: remaining=30, ideal=24, gap=+6Read the chart as a trend rather than as a daily judgment. A flat section can mean that work is blocked, that items are too large to finish incrementally, or that the team updates status only when work reaches done. A sharp drop can mean several items were completed together. It does not necessarily mean work happened only on that day.
Use burnup charts when scope changes
A burnup chart is often better for projects where requirements can change. Track at least two lines:
- Completed work
- Total committed scope
If completed work rises from 20 to 30 points while total scope rises from 40 to 50 points, the team delivered 10 points but still has 20 points remaining. Looking only at completed work could hide the effect of added scope.
Use the same unit throughout the iteration. Mixing hours, task counts, and story points makes the chart misleading. Define what counts as complete, and update the chart from completed work rather than partially finished work.
Common errors and responses
- Changing estimates mid-sprint: Record the change and explain it. Do not silently rewrite the original trend.
- Counting started work as completed: Count only work that meets the agreed definition of done.
- Ignoring scope additions: Show additions on a burnup chart or annotate the burndown.
- Using too many measures: Pick one primary unit and keep it stable.
- Reacting to one data point: Look for a pattern across several updates and inspect the underlying tasks.
- Updating irregularly: Set a daily update time so the chart reflects the current state.
The chart should lead to a conversation about delivery, blockers, assumptions, and scope. It should not replace those conversations.
Exercise
A sprint has 50 points of planned work. On day 5 of a 10-day sprint, the team has 32 points remaining. What is the ideal remaining work, and what does the gap indicate?
Show answer
The ideal remaining work is 25 points, because 50 - (50 / 10 × 5) = 25. The gap is 7 points, so the team is behind the straight-line trend and should inspect blockers, work size, and scope changes.