Sub topic 7
Waiting: idle people, machines, and work
Prerequisites and scope
This chapter assumes you know the Lean definition of waste from earlier chapters: activity that consumes resources without adding value the customer will pay for. It also assumes you can read the TIMWOODS list and simple time figures. Here we look at one waste, Waiting, in detail. We cover what it is, where it hides, how to measure it, and the mistakes people make when they try to remove it.
What Waiting means in Lean
Waiting is time during which people, machines, materials, or information are ready to be used but are not being used. Nothing is being transformed. The clock runs, the customer's order ages, and no value is added.
Waiting has three forms. Which one you see depends on what you watch.
- Idle people. An operator or analyst has nothing to do because upstream work has not arrived, a approval is pending, or a system is slow.
- Idle machines. Equipment sits stopped during changeovers, breakdowns, or because no material is available.
- Idle work. The item itself waits in a queue, in an inbox, or in a ticket backlog. This is the most common form and the easiest to miss, because nobody looks idle.
The third form matters most for lead time. In many office and software processes the people are busy all day, yet each work item spends most of its life sitting in a queue.
Examples in three settings
| Setting | Idle people or machines | Idle work |
|---|---|---|
| Manufacturing | Operator waits for a forklift to deliver parts. A press stops for a 45-minute die change. | Finished housings wait two days for the paint line. |
| Office | A clerk waits for a manager's signature before continuing. | A purchase request sits in an approval inbox over a weekend. |
| Software | A developer waits for a build or test environment. | A pull request waits 26 hours for a reviewer. |
Why Waiting hides in plain sight
People tend to count only the steps where someone is working. A step list for a quote process may show five boxes, but the time between the boxes is where most of the delay lives. Two habits keep Waiting hidden.
- Busy is not the same as productive. If every person is fully occupied, the process looks healthy. High utilization of people usually causes long queues, because any small variation leaves no spare capacity to absorb it.
- Queues are invisible. A pile of parts is visible. A list of 80 emails or 40 open tickets is not.
Waiting is measured against the whole timeline of the work item, not against the effort of any one person.
Measuring Waiting
The key measure is process cycle efficiency (PCE): value-added time divided by total lead time. A low PCE tells you that most elapsed time is waiting. The example below uses a quote process with five steps.
steps = [
{"name": "Receive request", "minutes": 5, "value_added": False},
{"name": "Wait in queue", "minutes": 240, "value_added": False},
{"name": "Prepare quote", "minutes": 30, "value_added": True},
{"name": "Wait for approval", "minutes": 120, "value_added": False},
{"name": "Send quote", "minutes": 5, "value_added": True},
]
lead_time = sum(s["minutes"] for s in steps)
value_added_time = sum(s["minutes"] for s in steps if s["value_added"])
pce = value_added_time / lead_time
print(f"Lead time: {lead_time} min")
print(f"Value-added time: {value_added_time} min")
print(f"Process cycle efficiency: {pce:.1%}")The output is a lead time of 400 minutes, value-added time of 35 minutes, and a PCE of 8.8%. Of the 400 minutes, 360 are the two waiting steps. That is 90% of the elapsed time. Speeding up "Prepare quote" by 10 minutes would barely change the result. Cutting the queue wait in half would remove 120 minutes.
The sample data also shows a common classification choice. "Receive request" is not value-added in this model, but it is necessary. Lean separates necessary non-value-added activity from pure waste. Waiting is almost always pure waste, though some waits are forced by rules, such as a cooling period or a legally required review. Treat those as constraints to challenge later, not as the first target.
Waiting and Little's Law
Little's Law links the amount of work in a system to how long it stays there. For a stable process, average lead time equals work in progress divided by throughput.
def lead_time_days(wip_items, throughput_per_day):
"""Little's Law: average lead time = work in progress / throughput."""
return wip_items / throughput_per_day
print(lead_time_days(60, 20)) # 3.0 days
print(lead_time_days(30, 20)) # 1.5 days after halving WIPWith 60 items in progress and 20 finished per day, the average item takes 3 days. Halve the work in progress and, at the same throughput, the average item takes 1.5 days. The practical lesson is that the queue is the wait. To shorten waiting, limit how much work you let into the process at once.
Common causes of Waiting
Most waiting traces back to a small set of causes.
- Batching. Work moves in groups, so each item waits for the rest of its batch.
- Unbalanced steps. One step is slower than the one before it, so work piles up in front of it.
- Long changeovers or setups. Machines stop while they are reconfigured.
- Approvals and handoffs. Work waits for one person's attention, often someone with many other demands.
- Unreliable equipment or systems. Breakdowns and slow tools stop everyone downstream.
- Missing information or materials. Work starts, stalls, and returns to the queue.
- Overproduction upstream. A step that produces too much floods the next step with a queue.
Common errors when attacking Waiting
- Filling idle time with extra work. Giving an idle operator more parts to make creates overproduction and inventory. Idle capacity is a signal to fix the flow, not an invitation to build stock.
- Pushing utilization to 100%. A fully loaded step has no room for variation, so its queue grows without limit.
- Optimizing one step. Speeding up a step that is not the bottleneck only moves the queue.
- Measuring touch time only. If you track how fast each person works and ignore the time between steps, the largest delays never appear in your data.
- Treating every wait as equal. A wait for a required test is different from a wait because nobody noticed the request. Sort them before you act.
Typical countermeasures
Match the countermeasure to the cause.
| Cause | Countermeasure |
|---|---|
| Batching | Reduce batch size toward one-piece flow |
| Long changeovers | Quick changeover (SMED): prepare setup steps while the machine still runs |
| Unbalanced steps | Level the workload; use takt time to set the pace |
| Approval delays | Delegate authority, set approval limits, and use clear service times |
| Breakdowns | Preventive maintenance and operator checks |
| Large queues | Limit work in progress with pull and kanban boards |
| Missing information | Standard request forms with required fields |
Later chapters cover pull, kanban, and standard work in more detail.
Worked example: the quote process
Return to the quote process. The first step is to find where time goes, which the PCE calculation already did: the 240-minute queue and the 120-minute approval account for 360 of 400 minutes.
- Queue. Requests arrive all day but are handled in one batch after lunch. Handling each request as it arrives, with a limit of three open requests per person, removes most of the queue.
- Approval. Every quote needs a manager's sign-off. Quotes under a set value can be approved by the preparer, with the manager reviewing a sample afterward.
- Re-measure. If the queue falls to 30 minutes and approval to 20 minutes, lead time becomes 5 + 30 + 30 + 20 + 5 = 90 minutes. PCE rises to 35 / 90, about 38.9%.
The work content did not change. Only the waiting did.
Key points
- Waiting covers idle people, idle machines, and idle work. Idle work is the most often missed.
- PCE shows how much of lead time is waiting. Little's Law shows that less work in progress means shorter waits.
- Do not fill idle time with unneeded output. Fix the flow instead.
- Choose the countermeasure by cause: batch size, changeover time, step balance, approvals, or reliability.
Exercise
A support team has 48 tickets open and closes 12 tickets per day. (a) Using Little's Law, what is the average time a ticket spends in the system? (b) The team limits open tickets to 24 and throughput stays at 12 per day. What is the new average? (c) A ticket needs 20 minutes of hands-on work. Roughly what is its process cycle efficiency in case (a), assuming 8-hour working days?
Show answer
(a) 48 / 12 = 4 days. (b) 24 / 12 = 2 days. (c) 4 days at 8 hours is 1,920 minutes, so PCE is 20 / 1,920, about 1.0%. Almost all the elapsed time is waiting.
Exercise
An operator on a packing line is often idle because the machine before it is slow. The supervisor suggests that the operator pack extra boxes in advance during idle time. Why is this a poor fix, and what should be examined instead?
Show answer
Packing extra boxes creates overproduction and inventory that the customer has not requested, and it hides the real problem. The team should examine the slow upstream machine, for example its changeover time, breakdowns, or imbalance with the packing step, and balance the line to the takt time.