Sub topic 5
Inventory: stock and work waiting to be used
This chapter assumes you know the basic idea of Lean waste (activity that uses resources without adding value the customer will pay for) and the TIMWOODS list. It also assumes you can read simple time and quantity figures. Here you look closely at the "I" in TIMWOODS: inventory.
What counts as inventory
In Lean, inventory is any material, information, or work that has been paid for or started but is not yet being used to serve a customer. It sits and waits. The cost has been spent, but the value has not been delivered.
Inventory takes three common forms in a process.
- Raw materials: parts or supplies bought before they are needed.
- Work in progress (WIP): items that have been started but are not finished. They sit between steps.
- Finished goods: completed output that has not yet been sold or delivered.
The idea is not limited to physical goods. The same pattern shows up in offices and software.
| Setting | Example of inventory |
|---|---|
| Manufacturing | Pallets of parts between machining and assembly |
| Office | A stack of unprocessed invoices or a full approval inbox |
| Software | A backlog of 400 tickets, or code branches waiting for review |
| Healthcare | Patients waiting in a corridor for a test result |
A quick test is to ask whether anything is waiting between two steps. If something is, you have found inventory.
Why inventory is a waste
Many people see stock as an asset. Lean sees it as a cost, and as a cover for other problems. Inventory is waste for several reasons.
- It ties up cash. Money spent on materials or started work earns nothing until the customer pays.
- It needs space and handling. Storage, shelving, counting, and moving all cost money. These costs often feed into transportation and motion waste.
- It can become obsolete or damaged. Food expires, parts rust, and a feature request may no longer matter by the time it is built.
- It lengthens lead time. The more work sits in the system, the longer each new item waits. Little's Law (covered below) makes this precise.
- It hides problems. Large buffers let a broken machine, a slow step, or a poor supplier go unnoticed. Defects found late are expensive because a whole batch may be affected.
The last point is the most important. Lean often compares inventory to water covering rocks in a river. When the water level drops, the rocks appear. Reducing inventory exposes the real problems so that you can fix them.
Little's Law: inventory and lead time
Lead time is the total elapsed time from when a request enters a process to when the customer receives the result. Little's Law links it to inventory:
average lead time = work in progress ÷ throughput
Throughput is how many items the process completes per unit of time. If throughput stays the same, cutting WIP cuts lead time in direct proportion.
def lead_time_days(wip_items, throughput_per_day):
"""Little's Law: average lead time = work in progress / throughput."""
return wip_items / throughput_per_day
print(lead_time_days(60, 20)) # 3.0 days
print(lead_time_days(30, 20)) # 1.5 days after halving WIPWith 60 items in progress and 20 finished per day, each item takes 3 days on average. Halve the WIP to 30 and the average falls to 1.5 days. Nothing about the speed of the work changed. The items simply stopped waiting in line.
The law holds for a stable process, where the long-run average arrival rate roughly equals the completion rate. If work piles up faster than it leaves, the averages keep drifting and the simple calculation will understate the delay.
Seeing inventory in a value stream
Inventory shows up on a value stream map as a triangle between steps, usually labeled with a quantity or a number of days. It also shows up in the numbers. The earlier waiting example in this tutorial had a process with 400 minutes of lead time and only 35 minutes of value-added work. Most of the remaining time was work sitting in queues. A queue is inventory measured in time.
You can estimate days of inventory with a simple ratio:
days of inventory = items on hand ÷ items used per day
A warehouse holding 900 units that ships 30 per day has 30 days of stock. A support team with 150 open tickets that closes 25 per day has 6 days of queue. Both figures tell you how long a new item waits before anyone touches it.
Common causes
Inventory rarely appears by accident. Typical causes include the following.
- Large batch sizes. Processing 500 items at a time means 499 wait while one is worked on.
- Overproduction. Making more than the next step needs creates a pile immediately.
- Long setup or changeover times. If switching tasks is slow, people batch work to avoid switching.
- Unreliable processes or suppliers. Teams build a "just in case" buffer to protect against breakdowns and late deliveries.
- Poor forecasting or bulk-buying discounts. Buying a year of supply to save a few percent can cost more in storage and risk than it saves.
- Unbalanced steps. If step B is slower than step A, work accumulates in front of B.
Edge cases and common errors
Not all inventory is removable, and zero inventory is not the goal. Watch for these points.
- Some buffer is necessary. A small safety stock may protect the customer from a real, known risk, such as a single-source part with a long supply line. Treat it as necessary non-value-added activity, size it with data, and review it regularly. Do not cut it blindly.
- Moving inventory is not removing it. Pushing stock to a supplier, a hidden shelf, or "someone else's backlog" hides the cost without eliminating it. Measure the whole flow.
- Reducing stock without fixing causes backfires. If you cut buffers while setups are still long and machines still break, the customer will see stockouts. Work on the causes first, or in step with the cuts.
- Digital inventory is still inventory. A long list of "almost done" tasks looks harmless but carries the same lead time and risk. Half-finished work in software is a common blind spot.
- Counting only finished goods. Most inventory in a factory or office is WIP, which is easy to overlook because it looks like activity.
Countermeasures
Several Lean tools address inventory directly.
- Pull systems and kanban. Work is started only when the next step signals that it is ready for it. A WIP limit caps how many items can be in a stage.
- Smaller batches and one-piece flow. Moving items one at a time, or in small groups, reduces waiting.
- Faster changeovers. Shorter setups make small batches affordable.
- Better balance between steps. Matching the pace of each step to customer demand prevents pile-ups.
- Supplier reliability and shorter lead times. If deliveries are dependable, large buffers are unnecessary.
- 5S. Organizing the workplace makes excess stock visible and easy to spot.
A diagram can show how a WIP limit changes the flow.
When Review holds three items, Build stops and helps clear the queue instead of adding more. The visible limit forces the team to find out why Review is slow.
Putting it into practice
A simple approach for a first inventory reduction looks like this.
- Walk the process and note every place where items wait.
- Count the items and compute days of inventory at each point.
- Pick the largest pile and ask why it exists, using the 5 Whys.
- Choose a countermeasure, such as a smaller batch or a WIP limit.
- Re-measure lead time after the change to confirm it fell.
Exercise
A claims team has 120 open claims and completes 15 claims per day. (a) What is the average lead time by Little's Law? (b) The team adopts a WIP limit that holds the system to 60 claims at the same throughput. What is the new average lead time? (c) Name one risk of setting the limit without first studying why claims wait.
Show answer
(a) 120 ÷ 15 = 8 days. (b) 60 ÷ 15 = 4 days. (c) If the real causes of waiting, such as slow approvals or missing information, are not fixed, the limit can starve downstream steps or leave people idle, or the team may be tempted to push work to a hidden queue elsewhere. The limit exposes the problem but does not solve it.
Exercise
A warehouse holds 1,200 units of a part and uses 40 per day. A supplier offers a 5% discount for buying three times the usual order. Give two reasons the discount might still be a poor choice from a Lean view.
Show answer
Current stock is 1,200 ÷ 40 = 30 days. Tripling orders would raise stock and tie up more cash, require more space and handling, and raise the risk of damage or obsolescence. Larger stock can also hide supplier or quality problems, and the saving may be smaller than these combined carrying costs.