Measuring waste: lead time, cycle efficiency, and Little's Law
This chapter assumes you can read a simple process map and know the eight wastes in TIMWOODS. You do not need statistics. You need to be comfortable dividing one number by another and reading times in minutes or days.
Spotting waste by walking the process tells you where to look. Measurement tells you how big the problem is and whether a fix worked. Three measures do most of the work: lead time, process cycle efficiency, and Little's Law.
Lead time and the time that adds value
Lead time is the elapsed time from the moment a request enters a process to the moment the customer gets the result. It includes every minute, whether someone is working on the item or it is sitting in a queue.
Value-added time is the part of lead time when the work changes the product or service in a way the customer would pay for. Preparing a quote adds value. Waiting for a manager to approve it does not.
Three terms are easy to confuse:
| Term | What it measures | Typical use |
|---|---|---|
| Lead time | Entry to delivery, including waiting | What the customer experiences |
| Cycle time | Time one person or machine spends on one unit of work | Capacity and balancing steps |
| Value-added time | Part of the work the customer values | Finding waste |
Lead time is the one customers feel. Most processes have a lead time many times larger than their value-added time. The gap is waste, and most of it is Waiting and Inventory.
Process cycle efficiency
Process cycle efficiency (PCE) is value-added time divided by total lead time. It shows what share of the elapsed time is spent on work that matters.
The script below lists the steps of a quoting process and computes PCE.
steps = [
{"name": "Receive request", "minutes": 5, "value_added": False},
{"name": "Wait in queue", "minutes": 240, "value_added": False},
{"name": "Prepare quote", "minutes": 30, "value_added": True},
{"name": "Wait for approval", "minutes": 120, "value_added": False},
{"name": "Send quote", "minutes": 5, "value_added": True},
]
lead_time = sum(s["minutes"] for s in steps)
value_added_time = sum(s["minutes"] for s in steps if s["value_added"])
pce = value_added_time / lead_time
print(f"Lead time: {lead_time} min")
print(f"Value-added time: {value_added_time} min")
print(f"Process cycle efficiency: {pce:.1%}")The output is a lead time of 400 minutes, value-added time of 35 minutes, and a PCE of 8.8%. About 91% of the elapsed time is waiting or handling.
Notice what the numbers say. The two waits take 360 of the 400 minutes. Making the quote preparation 10 minutes faster would change PCE very little. Cutting the queue is where the gain is.
How to read a PCE value
A low PCE is normal in processes that have never been examined. Office and service processes often sit in the single digits. Many Lean sources describe 25% or more as a good result for a transactional process. Treat these as rough guides, not targets. Compare a process with its own past values and with similar processes in your organization.
Where PCE misleads
- The classification is a judgment. If you count "Receive request" as value-added, PCE rises without any real improvement. Agree on the definition before you measure.
- It ignores quality. A process with a fast first pass and 30% rework can show a good PCE if the rework is counted as value-added. Count rework time as non-value-added.
- Necessary non-value-added steps count against it. A legal review or a safety check may be required, so you cannot remove it. It still lowers PCE. Keep these steps in a separate group so you do not chase them as pure waste.
- It uses averages. One average hides the slow cases that customers complain about. Look at the longest lead times too.
Little's Law
Little's Law links three quantities in a stable process:
- Work in progress (WIP): the number of items started but not finished.
- Throughput: the number of items finished per unit of time.
- Lead time: the average time an item spends in the process.
The relationship is: average lead time = WIP ÷ throughput.
def lead_time_days(wip_items, throughput_per_day):
"""Little's Law: average lead time = work in progress / throughput."""
return wip_items / throughput_per_day
print(lead_time_days(60, 20)) # 3.0 days
print(lead_time_days(30, 20)) # 1.5 days after halving WIPWith 60 items in progress and 20 finished per day, an item takes 3 days on average. Halve the WIP at the same throughput and the lead time halves to 1.5 days.
This is why Lean treats Inventory as a waste even when it looks harmless. Every item in the pile adds time for every other item behind it. You can shorten lead time without making anyone work faster. You limit how much work is allowed in.
Conditions and limits
Little's Law is exact only under certain conditions. Know them before you quote it.
- The process must be stable. Over the measuring period, the amount of WIP at the start and end should be about the same. If the backlog is growing, the formula describes the past, not the future.
- Units must match. Count WIP and throughput in the same item type, and use the same time unit.
- It describes averages. It does not predict the lead time of one item.
- It does not say that cutting WIP is free. If you cut WIP too far, people and machines run out of work and throughput drops. The law holds, but your throughput value no longer stays the same.
The last point is the usual trap. The example assumes throughput stays at 20 per day. In practice, a limit that is too low can starve a bottleneck. Reduce WIP in steps and watch throughput.
Putting the three measures together
Use the measures in sequence on one process:
- Map the steps and record the time for each, including queue time.
- Add all times to get lead time. Add the value-added steps to get value-added time.
- Divide to get PCE. Note which wastes the non-value-added time belongs to.
- Count WIP and throughput. Check that Little's Law roughly matches your measured lead time. A large mismatch means a measurement error or an unstable process.
- Choose a change aimed at the largest block of waiting. Measure again with the same rules.
The check in step 4 is useful. If WIP is 60 and throughput is 20 per day, the expected lead time is 3 days. If your sampled items show 6 days, some items are probably hidden in a queue you did not count, or some old items are skewing the average.
Common errors
- Measuring only the work steps and leaving out queues. This makes lead time look short and PCE look high.
- Mixing item types, such as small and large orders, in one WIP count.
- Using Little's Law while the backlog is growing.
- Comparing PCE values from different processes that used different classification rules.
- Declaring success from one week of data. Collect enough cases to cover normal variation.
Exercise
A claims team has 90 claims in progress and finishes 30 claims per day. A claim takes 45 minutes of actual handling, spread over the process. (a) What is the average lead time in days? (b) If a working day is 450 minutes and the handling time is the only value-added time, what is the PCE, treating the lead time as measured in working days? (c) The team limits WIP to 45 claims and throughput stays at 30 per day. What is the new lead time and PCE?
Show answer
(a) Lead time = 90 ÷ 30 = 3 days. (b) 3 working days = 1,350 minutes. PCE = 45 ÷ 1,350 = 3.3%. (c) Lead time = 45 ÷ 30 = 1.5 days = 675 minutes. PCE = 45 ÷ 675 = 6.7%. Halving WIP doubled PCE because the value-added time did not change while the lead time halved. This holds only if throughput really stays at 30 per day.
Exercise
A team reports a PCE of 40% after it reclassified "wait for customer reply" as value-added. Name two problems with this result and what you would do instead.
Show answer
First, the wait does not change the product in a way the customer pays for, so the reclassification inflates PCE without improving the process. Second, the new value cannot be compared with earlier measurements that used the old rule. Recalculate PCE with the original classification, and if the wait is outside the team's control, report it as a separate necessary non-value-added group.