Sub topic 13
Finding waste: gemba walks and value stream maps
This chapter assumes you know the eight wastes in TIMWOODS and the Lean definition of value: an activity the customer would pay for. It also assumes you can read simple time and quantity figures. You will learn two ways to find waste. The first is to go and watch the work. The second is to draw the flow of work and material on one page.
Why you have to look
Reports and meetings describe a process as people believe it runs. The real process often differs. Workarounds, hidden queues, and extra checks rarely appear in a procedure document. Lean therefore asks you to go to the gemba, a Japanese word for "the real place": the shop floor, the office desk, or the team's board and pipeline, wherever the work happens.
Two methods turn this into a habit:
- A gemba walk is a planned visit to the place of work to observe, ask questions, and learn.
- A value stream map (VSM) is a diagram of every step, queue, and information flow needed to deliver one product or service to a customer.
The walk gives you the facts. The map organizes them so you can see where time goes.
Gemba walks
Purpose and ground rules
The aim of a walk is to understand the work, not to inspect people. If staff think they are being judged, they will hide problems, and you will see a polished version of the process.
- Choose one process or area and a clear question, such as "Where do orders wait?"
- Walk the path of the work, in the order the work moves.
- Watch first, then ask open questions: "What happens next?" "What do you do when this is missing?"
- Take notes on what you see, not on what you assume.
- Thank people and report back what you learned and what you will do.
What to look for
Use TIMWOODS as a checklist of visible signs.
| Waste | Signs you can see |
|---|---|
| Transportation | Carts, handoffs, files emailed between teams, data copied between systems |
| Inventory | Piles of parts, full inboxes, long backlogs, many open pull requests |
| Motion | Walking to a shared printer, searching for tools, switching between many screens |
| Waiting | People idle until a part, approval, or build finishes |
| Overproduction | Reports nobody reads, batches made "to be safe", features nobody asked for |
| Over-processing | Repeated approvals, extra polish, tighter tolerances than the customer needs |
| Defects | Rework areas, correction stickers, bug reopen counts |
| Skills | Skilled people doing clerical work, suggestions that never get an answer |
Common mistakes on a walk
- Walking too fast. Stand in one spot for ten or fifteen minutes. Many wastes show up only on the second or third repeat of a task.
- Fixing on the spot. Jumping to solutions skips root cause analysis, which a later chapter covers.
- Blaming people. Most waste comes from the design of the process, not from careless workers.
- Going once. One visit shows one day. Repeat walks at different times and on different shifts.
- Watching only the busy parts. The longest delays are usually between steps, where nothing visibly happens. Look for the places where work sits.
Value stream maps
What a map contains
A current-state VSM follows one product family or request type from the customer's order back to the start, then forward again. It records for each step:
- Process time (P/T): the time spent actually working on one item. This is sometimes called touch time.
- Wait time: the time the item sits before the step starts.
- Lead time (L/T): the total elapsed time from start to finish, which equals process time plus wait time across all steps.
- Other data: number of people, batch size, defect or rework rate, and how often the step is available.
The map also shows information flow: how the customer's demand reaches each step, such as a schedule, an email, or a ticket. Mapping both flows shows whether work is pushed by a forecast or pulled by real demand.
Steps to draw one
- Pick one product or request type and state the start and end points.
- Walk the process (a gemba walk) from end to start, then confirm it from start to end.
- List each step in order and record its process time from direct observation, not from a standard.
- Record the queue in front of each step: how many items, and how long they wait.
- Draw the information flow from the customer.
- Add a timeline along the bottom: process time in the raised sections, wait time in the lowered sections.
- Total both rows, and mark the wastes you can see.
The next diagram shows the same quote process used in the example below.
Worked example
The quote process has five steps: receive request (5 min), wait in queue (240 min), prepare quote (30 min), wait for approval (120 min), and send quote (5 min). The code below tags each step as value-added or not, finds the largest delays, and prints them.
steps = [
{"name": "Receive request", "minutes": 5, "value_added": False},
{"name": "Wait in queue", "minutes": 240, "value_added": False},
{"name": "Prepare quote", "minutes": 30, "value_added": True},
{"name": "Wait for approval", "minutes": 120, "value_added": False},
{"name": "Send quote", "minutes": 5, "value_added": True},
]
lead_time = sum(s["minutes"] for s in steps)
value_added_time = sum(s["minutes"] for s in steps if s["value_added"])
print(f"Lead time: {lead_time} min")
print(f"Value-added time: {value_added_time} min")
print(f"Process cycle efficiency: {value_added_time / lead_time:.1%}")
print("Largest non-value-added steps:")
non_value = [s for s in steps if not s["value_added"]]
for s in sorted(non_value, key=lambda s: s["minutes"], reverse=True)[:2]:
share = s["minutes"] / lead_time
print(f"- {s['name']}: {s['minutes']} min ({share:.0%} of lead time)")The lead time is 400 minutes and only 35 are value-added, so process cycle efficiency is 8.8%. The queue and the approval wait together take 360 minutes, which is 90% of the total. The map points the team at waiting, and behind it inventory (requests piled up) and possibly over-processing (an approval that may not be needed). Making the 30-minute preparation step faster would barely change the result.
Classifying each step
For each step, ask whether the customer would pay for it. Then sort it into one of three groups:
- Value-added: it changes the product or service in a way the customer wants.
- Necessary non-value-added: the customer does not value it, but it is needed now, for example a legal check or a safety inspection. Reduce it, but do not simply delete it.
- Waste: neither of the above. Remove it.
Be careful with the middle group. Teams often label a step "necessary" because it has always been done. Ask what rule or risk requires it, and who would notice if it stopped.
Common mapping errors
- Mapping the ideal process. Draw what happens, including rework loops and exceptions.
- Using standard times. Use measured times. Standards hide variation.
- Mapping too wide. A map of the whole company is unreadable. Start with one family.
- Ignoring information flow. Many delays come from waiting for a decision or data, not for material.
- Stopping at the map. The map is only useful if it leads to a future-state design and a short list of actions.
From finding to acting
After the walk and the map, rank the wastes by how much lead time they hold. Then pick one or two to study. The next steps are to measure them (lead time, process cycle efficiency, Little's Law), trace the cause with the 5 Whys, and choose a countermeasure. Fixing the largest delay first gives the most gain for the effort.
Exercise
A team maps a purchase-order process. Steps: enter order (10 min), wait for manager (180 min), check price (20 min), wait for supplier confirmation (600 min), send confirmation to customer (10 min). The customer values the price check and the confirmation. What are the lead time and process cycle efficiency, and which waste should the team investigate first?
Show answer
Lead time = 10 + 180 + 20 + 600 + 10 = 820 minutes. Value-added time = 20 + 10 = 30 minutes. Process cycle efficiency = 30 / 820 = about 3.7%. The supplier wait (600 min, 73% of lead time) is the largest, so the team should investigate waiting first, then the manager wait (180 min). On the walk they should also look for inventory, meaning orders piled up while they wait.
Exercise
During a gemba walk, a supervisor sees an operator searching for a tool and immediately orders a new tool cabinet. Name two things that went wrong with this approach and what the supervisor should do instead.
Show answer
The supervisor jumped to a solution without finding the cause (the tool may be misplaced, shared, or missing a fixed home), and they acted without asking the operator. Instead, the supervisor should watch several repeats, ask open questions about what happens when the tool is missing, note it as motion waste, and trace its cause with the 5 Whys before choosing a countermeasure such as 5S.