Sub topic 6
Transferring a threat
This chapter assumes you can already score a risk from probability and impact. It also assumes you know what a threat is and have met the idea of a response strategy. It covers one of the four threat strategies: transfer.
What transfer means
Transferring a threat means shifting the financial consequences of a threat, and the responsibility for handling them, to a third party. The third party is usually an insurer, a supplier, or a contractor. In exchange, the project normally pays a fee or accepts a higher price.
Transfer does not change the probability that the event happens. It does not remove the event either. If a supplier's factory floods, the flood still happens. What changes is who pays for the damage and who has to deal with it.
This is the main difference from the other threat strategies:
| Strategy | What it changes |
|---|---|
| Avoid | Removes the cause, so the threat can no longer occur |
| Mitigate | Lowers probability, impact, or both |
| Transfer | Moves the impact (and often the handling) to another party |
| Accept | Changes nothing, and the project bears the outcome |
Common transfer mechanisms
Most transfers rely on a contract. The contract is what makes the other party's obligation enforceable. Typical mechanisms are:
- Insurance. The project pays a premium. The insurer pays for losses covered by the policy, usually above a deductible (the first slice of loss the project still pays itself).
- Fixed-price contracts. The seller carries the risk of cost overruns. This works best when the scope is well defined.
- Warranties and guarantees. The supplier repairs or replaces defective work at its own cost for a stated period.
- Performance bonds and surety bonds. A third party pays the project if the contractor fails to deliver.
- Indemnification clauses. One party agrees to cover the other's losses from specified events, such as third-party claims.
- Outsourcing a specialist task. A firm with the right skills and licenses takes on work that is risky for your team, such as hazardous installation.
Transfer works best for some risks
Transfer is most useful for threats with a low to medium probability and a high financial impact. These are the "rare but expensive" events, such as fire, theft, liability claims, or a contractor going bankrupt. A single loss of this kind can exceed what the project can absorb, and an insurer can pool the risk across many customers.
Transfer is a poor fit when:
- The damage is mainly to reputation, safety, or stakeholder trust. Money can compensate for these only partly.
- The threat is a schedule delay that cannot be bought back.
- The other party is not financially able to pay when the event happens.
- The cost of transfer is higher than the exposure it removes.
Checking whether transfer is worth the price
Compare the expected cost of keeping the risk with the total cost of transferring it. Expected cost is probability multiplied by impact. The script below assumes the transfer covers everything above a deductible.
def expected_cost_retained(probability, impact):
return probability * impact
def expected_cost_transferred(probability, impact, premium, deductible):
own_share = min(impact, deductible)
return premium + probability * own_share
probability = 0.05
impact = 200_000
premium = 6_000
deductible = 20_000
keep = expected_cost_retained(probability, impact)
transfer = expected_cost_transferred(probability, impact, premium, deductible)
print(f"Keep the risk: {keep:,.0f}")
print(f"Transfer the risk: {transfer:,.0f}")The output is 10,000 for keeping the risk and 7,000 for transferring it. On expected cost alone, transfer wins here.
Expected cost is only a starting point. A project may still buy cover that costs more than the expected loss, because it cannot survive the worst case. The risk appetite you met earlier decides how much weight the worst case gets.
Residual and secondary risks
Transfer almost always leaves something behind. Look for these:
- Retained risk. The deductible, policy limits, and exclusions stay with the project.
- Counterparty risk. The insurer or contractor may fail to pay or perform.
- Contract risk. Vague wording can lead to a dispute about whether the event was covered.
- Reputation and schedule effects. Compensation arrives after the event. The delay or the damaged relationship has already happened.
- New threats. A fixed-price contract can push a seller to cut corners on quality to protect its margin.
The last point is a secondary risk, meaning a risk created by the response itself. Record it as its own entry in the register, with its own owner and strategy.
Choosing and documenting a transfer
Once you pick transfer, write it down so the response can be checked later. A register entry for a transferred threat looks like this:
ID: R-21
Type: Threat
Description: Fire or flood at the staging warehouse may destroy delivered equipment.
Probability: Low (2/5) Impact: High (5/5) Score: 10
Strategy: Transfer
Response: Buy property insurance covering equipment value, with a deductible of 20,000.
Owner: Finance manager
Trigger: Equipment arrives at the warehouse
Residual risk: Deductible and policy exclusions remain with the project
Secondary risk: Insurer may dispute the claim (R-22)
Status: OpenThe owner is the person who confirms that the cover is in place and that it matches the risk. Here the trigger is a date or event by which the cover must already be active, because cover bought after the loss is worthless. Also check that the cost of the transfer is in the budget, since a premium or a price uplift is a real project cost.
Common mistakes
- Treating transfer as if the risk had gone. The risk is still on the register, with a lower exposure to the project.
- Assuming a contract covers everything. Read exclusions, caps, and notice deadlines.
- Never checking the other party's ability to pay.
- Forgetting the cost of transfer in the budget.
Exercise
A project faces a threat with a 4% chance of a 500,000 loss. An insurer offers cover for a 15,000 premium and a 25,000 deductible. Compare the expected cost of keeping the risk with the expected cost of transferring it, then name one residual risk of the transfer.
Show answer
Keeping the risk costs 0.04 × 500,000 = 20,000. Transferring costs 15,000 + 0.04 × 25,000 = 16,000. Transfer is cheaper on expected cost. Residual risks include the 25,000 deductible, policy exclusions, or the insurer disputing or failing to pay the claim.
Exercise
A team replaces a time-and-materials contract with a fixed-price contract to push cost overrun risk to the supplier. Name a secondary risk this creates.
Show answer
The supplier may cut quality or resist change requests to protect its margin. This secondary risk needs its own register entry, owner, and response.