Sub topic 5
Avoiding a Threat
This chapter covers the avoid strategy for threats. It assumes you know basic project vocabulary (scope, schedule, budget, stakeholders). It also assumes you can score a risk by probability and impact, and you know a threat is an uncertain event that would hurt project objectives if it happened.
What avoidance means
Avoiding a threat means changing the project so the threat can no longer happen, or so it cannot affect the objectives. Avoidance does not make a risk smaller. It removes the risk, or removes the project's exposure to it.
The avoid strategy aims for a probability of zero, or an impact of zero. Most other threat strategies only reduce one of the two. That makes avoidance the strongest option on paper, and it often has the highest price.
Avoidance can be an answer in three ways:
- Remove the cause. Eliminate the condition that produces the risk.
- Change the plan. Alter scope, schedule, budget, or approach so the risky element is gone.
- Isolate the objectives. Protect a key objective so the event no longer reaches it.
Common ways to avoid a threat
Teams usually avoid a threat by one of these actions:
- Remove the work. Cut a feature or work package that carries the risk.
- Change the approach. Pick a proven technology instead of an untested one.
- Change the supplier or location. Use a vendor with a track record, or move work away from a flood-prone site.
- Extend the schedule. Add time so a hard deadline no longer depends on a fragile step.
- Clarify requirements. Settle an ambiguous requirement early, so late rework cannot happen.
- Gain information first. Run a test, a prototype, or an expert review, then decide. This removes the uncertainty rather than the work.
Some of these overlap with mitigation. The difference is the result. If the risk no longer exists after the action, you avoided it. If it still exists at a lower level, you mitigated it.
A worked example
A team builds a mobile app. The plan uses a new, unreleased payment library from a small vendor. The risk register records this threat:
- Threat: The unreleased library may contain defects or change its interface late in the project.
- Probability: High (4/5).
- Impact: High (4/5).
- Score: 16.
The score is above the team's threshold of 10, so the team must respond. It compares options:
| Option | Strategy | Effect |
|---|---|---|
| Pay for extra testing of the new library | Mitigate | Lowers impact, but the risk remains |
| Buy insurance against delay | Transfer | Moves the cost, but the delay still happens |
| Use a widely adopted payment library instead | Avoid | The defect risk of the new library is gone |
The team chooses to avoid. It replaces the new library with a mature one. The old threat no longer exists in the plan. The cost is a license fee and the loss of two features that only the new library supported. The sponsor agrees because the app's launch date is fixed.
The costs of avoidance
Avoidance is not free. Check these costs before choosing it:
- Lost benefit. Removing a risky feature may remove the value it would have given. Dropping scope can also remove a threat's matching opportunity.
- Lost time or money. A longer schedule or a pricier supplier raises cost.
- Stakeholder agreement. Changes to scope, schedule, or budget often need approval through change control.
- Secondary risks. The new approach can bring new risks. The mature library may have its own licence terms or a slower release cycle.
A useful test is to compare the exposure you remove with the value you give up. If you give up more than the exposure is worth, mitigation or acceptance is likely a better choice.
When avoidance is not possible
Avoidance has limits:
- Early stage only. Avoidance is easiest before work begins. Once a design is built or a contract is signed, changing course costs more.
- Unavoidable work. Some risks sit inside work you cannot drop, such as legal compliance or the core deliverable.
- External events. A storm or a regulation change cannot be avoided. You can only move work out of its way or prepare for it.
- Authority. If the change needs a decision above the project's authority, the team should escalate instead.
Recording an avoidance response
When you choose to avoid, record the following in the risk register:
- The risk ID and a clear description of the threat.
- The strategy: Avoid.
- The exact change to the plan, such as "replace library X with library Y".
- The owner, who makes sure the change is carried out.
- The date by which the change must be made. Late avoidance may no longer be possible.
- Any secondary risk the change creates, entered as its own risk.
After the change is made, update the scope, schedule, or cost baseline as needed. Then set the original risk's status to closed, because it can no longer occur. Keep it in the register as a record of the decision.
Common mistakes
- Calling mitigation "avoidance." If the risk still exists, even at a lower level, it is not avoided.
- Ignoring what was given up. The cost of avoiding must be compared to the threat's exposure.
- Skipping approval. Plan changes need change control.
- Forgetting secondary risks. Every plan change can introduce a new risk.
- Avoiding too late. After commitments are made, avoidance may be too expensive to use.
Exercise
A project team learns that a planned data centre sits in a region with frequent flooding. The team moves the deployment to a data centre in a safer region before any equipment is bought. Which threat strategy is this, and name one secondary risk the team should check.
Show answer
This is avoidance. Moving the deployment removes the flood exposure, so the threat can no longer affect the project. Secondary risks to check include higher hosting costs, added network delay for users, and a new provider the team has not worked with before. The team should record each as its own risk and update the baselines.
Exercise
A threat has a score of 15, above the team's threshold of 10. Avoiding it would mean dropping a feature that makes up most of the product's value. What should the team consider before choosing avoidance?
Show answer
The team should compare the exposure removed against the value lost. Dropping a feature that holds most of the product's value is a large cost and a scope change that needs approval from the sponsor through change control. Mitigation or transfer may protect the value while still lowering the exposure. If the change is beyond the team's authority, the team should escalate.