Sub topic 7
Mitigating a Threat
This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders). It also assumes you can rate a risk's probability and impact on a simple scale and multiply them into a score. The chapter covers mitigation: what it is, the three ways to do it, how to cost it, and the mistakes teams make with it.
What mitigation means
To mitigate a threat is to take action now so that the threat becomes less likely, less damaging, or both. The risk stays in the project. You shrink it.
Mitigation differs from the other threat strategies in what it does to the risk:
- Avoid removes the threat by changing the plan so the cause no longer applies.
- Transfer moves the financial consequence to a third party, such as an insurer or a fixed-price contractor. The event can still happen.
- Mitigate keeps the risk and reduces its probability, its impact, or both.
- Accept takes no action in advance.
Mitigation is the most common response for threats that score above the threshold but cannot be avoided or transferred at a sensible price.
Three levers
Every mitigation acts on one of three things.
| Lever | Question it answers | Example |
|---|---|---|
| Probability | How can we make the event less likely? | Qualify a second supplier so one supplier's failure matters less often. Run a prototype to find design faults early. |
| Impact | If it happens, how can we make the damage smaller? | Order a first batch early so a later delay hurts less. Keep a backup of the database. |
| Detection or proximity | Can we see it sooner, or push it later? | Add weekly checkpoints so a slipping supplier is noticed in days, not months. |
The third lever is not always listed in textbooks, but it is useful in practice. Earlier detection leaves more time to respond, which indirectly lowers impact.
Reducing probability usually works on causes. Reducing impact usually works on consequences. When you write a response, name which of the two you are targeting. "Improve supplier relations" is vague. "Hold a fortnightly delivery review so slippage is seen two weeks sooner" names a cause and a result you can check.
Worked example
Take the register entry for a late supplier delivery.
ID: R-07
Type: Threat
Description: Key supplier may deliver the payment terminals late.
Probability: Medium (3/5) Impact: High (4/5) Score: 12
Strategy: Mitigate
Response: Order a first batch early and qualify a second supplier.
Owner: Procurement lead
Trigger: Supplier misses the first confirmed shipping date
Contingency: Switch to the second supplier for the remaining batches
Residual risk: Second supplier's quality is unproven (secondary risk R-15)
Status: OpenThe score is 3 × 4 = 12. With a threshold of 10, the risk needs a response. The team considered the alternatives:
- Avoid: drop the terminal feature. This conflicts with the project scope, so it was rejected.
- Transfer: add late-delivery penalties to the contract. The supplier would not agree to them, and a penalty would not bring the terminals sooner.
- Mitigate: act on both levers. Ordering early reduces the chance that a delay stops the launch. A second qualified supplier reduces the impact if the first one fails.
The response has two parts, and each acts on a different lever. After mitigation the team might re-rate the risk as Low probability (2/5) and Medium impact (3/5), a score of 6. That new number is the residual risk, and it is below the threshold.
Costing a mitigation
Mitigation costs money, time, or effort, and the cost has to make sense compared with the risk. A simple check is expected loss before and after.
- Estimate the cost of the impact in money, for example 40,000.
- Convert probability to a rough percentage, for example 50 percent before and 20 percent after.
- Expected loss before is 20,000. Expected loss after is 8,000. The reduction is 12,000.
- Compare that reduction with the mitigation cost. If the mitigation costs 15,000, it is poor value on these numbers alone.
def mitigation_worth_it(impact, p_before, p_after, cost, impact_after=None):
impact_after = impact if impact_after is None else impact_after
loss_before = impact * p_before
loss_after = impact_after * p_after
benefit = loss_before - loss_after
return benefit, benefit > cost
print(mitigation_worth_it(40000, 0.5, 0.2, 15000))
print(mitigation_worth_it(40000, 0.5, 0.2, 5000, impact_after=25000))The first call prints (12000.0, False). The second prints (15000.0, True), because the mitigation also reduces the impact from 40,000 to 25,000 (so the loss after is 25,000 × 0.2 = 5,000, and the benefit is 20,000 − 5,000 = 15,000).
Treat these figures as rough. Probabilities in project risk work are judgments, not measurements. Still, the check catches mitigations that cost more than the risk is worth. It also shows when a cheaper action, or acceptance, is the better choice.
Writing a good mitigation action
A mitigation that is not written as an action tends not to happen. Check each response against these points:
- It is specific. Someone else could read it and know what to do.
- It has an owner, a person and not a team.
- It has a date or a milestone.
- It has its own budget or effort, added to the project plan.
- It states the expected effect on probability or impact.
Mitigation actions are real work. Add them to the schedule and the budget like any other task. If they only live in the risk register, they are easy to forget when the project is busy.
Residual and secondary risks
Mitigation rarely removes a risk completely. What is left is the residual risk. In R-07, some chance of delay remains even with an early order.
Mitigation can also create new risks, called secondary risks. Qualifying a second supplier introduces the chance that the second supplier's quality is poor. That is R-15 in the example. Secondary risks need their own entry, score, and response. If you skip this step, the project fills up with unrecorded exposure while the register looks tidy.
Common errors
- Calling any action a mitigation. Escalating a risk or doing nothing is not mitigation. The action must change probability or impact.
- No measurable effect. If you cannot say how the score should change, you cannot tell later whether it worked.
- Mitigating below the threshold. Spending on a low-scoring risk takes effort from larger ones. Acceptance is often the right call.
- Forgetting the cost. The mitigation budget must be approved. Without it, the plan exists only on paper.
- Ignoring secondary risks. A fix that creates a larger problem has not helped.
- Never re-scoring. After the action is done, rate the risk again. If the score has not fallen, the mitigation is not working and the response needs to change.
Edge cases
- Several risks, one action. A single mitigation can reduce more than one risk, such as a training course that lowers both defect risk and staff turnover risk. Link the action to every risk it affects, so its value is not undercounted.
- Mitigation that conflicts with another objective. Adding more testing lowers quality risk but may push the schedule. Record the trade-off as a secondary risk.
- Mitigation beyond your authority. If the action needs a decision or funding the project manager does not control, escalate. Do not quietly leave it undone.
- Partial mitigation. When full mitigation costs more than the risk, a cheaper partial action plus a contingency plan can be the right choice.
Exercise
A threat has probability 4/5 and impact 5/5. The team plans a prototype test that should lower the probability to 2/5, with no change in impact. The test creates a possible two-week delay to the schedule. What is the score before, the expected residual score, and what should be recorded about the delay?
Show answer
Before: 4 × 5 = 20. Residual: 2 × 5 = 10. The two-week delay is a secondary risk (or a direct schedule effect of the response), so it gets its own register entry with probability, impact, score, owner, and response. The prototype action also needs an owner, date, and budget in the project plan.
Exercise
A mitigation costs 9,000. The threat has an impact of 30,000. It reduces the probability from 40 percent to 15 percent and leaves the impact unchanged. Is it worth it on expected loss alone?
Show answer
Loss before is 30,000 × 0.40 = 12,000. Loss after is 30,000 × 0.15 = 4,500. The benefit is 7,500, which is less than the 9,000 cost. On these numbers alone it is not worth it, so the team should look for a cheaper action or consider acceptance with a contingency plan.