Monitoring Whether Responses Work
This chapter assumes you know how to rate probability and impact, how a risk register is laid out, and the response strategies for threats and opportunities covered earlier. It covers what happens after a response is agreed: checking whether it is working, and what to do when it isn't.
Why a response is not finished when it is written
A response plan is a prediction. It says that if the team does X, the probability or impact of a risk will change. Nobody knows whether that is true until the work is done and the project reacts. Monitoring tests the prediction.
Monitoring risk responses answers four questions:
- Was the response actually carried out, and on time?
- Did it change the probability or impact as expected?
- Did the response create new problems (secondary risks)?
- Has the situation changed so that the chosen strategy no longer fits?
A response can fail at any of these points. A mitigation can be late. It can be on time but too weak. It can work but cost more than the risk was worth. Each failure needs a different fix, so monitoring has to tell them apart.
What to watch
Response actions
Each response has actions with owners and dates. Track them like any other task. An overdue action on a high-scoring risk is an early warning, because the risk is still at its original exposure while the team believes it is being handled.
Triggers
A trigger is an observable event that signals a risk is about to happen or has begun. Active acceptance and contingency plans depend on triggers. If nobody checks the trigger, the contingency plan never starts. In the register example from earlier chapters, the trigger for the late-terminal risk was "supplier misses the first confirmed shipping date". The owner must be told the moment that happens, not at the next monthly review.
Residual exposure
After a response, compare the new probability and impact with the original. Record the new score next to the old one. The gap between them is the evidence that the response worked.
| Risk | Score before | Expected after | Actual after | Reading |
|---|---|---|---|---|
| R-07 late terminals | 12 | 6 | 6 | Response worked |
| R-09 data migration errors | 16 | 8 | 12 | Response only partly worked |
| R-11 early adopter | 8 | 12 | 8 | Enhance had no visible effect |
Comparing "expected after" with "actual after" is more useful than comparing only before and after. A risk that dropped from 16 to 12 looks like progress, but if the plan promised 8, something is wrong.
Secondary risks and new risks
Responses change the project. Qualifying a second supplier, for example, introduced the unproven-quality risk R-15. Check that every secondary risk has been entered, scored, and given an owner. Also look for risks unrelated to your responses, since the environment keeps changing.
Reserves
Reserves are the budget and time set aside for risks. When a contingency plan runs, the cost is drawn from the contingency reserve. Track the draw-down against what remains of the risk exposure. If the reserve is being spent faster than the risks are closing, the remaining plan is under-funded. Management reserve should only be touched for risks nobody identified, and any use needs the approval your governance requires.
The monitoring cycle
The loop is deliberate. A risk stays in the cycle until it is closed, because a response that works today can stop working when conditions change.
When a response is not working
Match the fix to the failure.
- The action was late or not done. This is an execution problem. Re-plan, add resources, or change the owner. The strategy may still be right.
- The action was done but the score barely moved. The strategy is weak for this risk. Try a stronger action, combine strategies, or switch strategy. For example, move from mitigate to transfer if an insurer will take the exposure.
- The score fell but the cost outweighed the benefit. Compare the cost of the response with the reduction in expected loss. If a response costs 40,000 to cut an expected loss of 10,000, accepting would have been better.
- The risk went beyond the team's authority. Escalate it. An exposure that now exceeds the threshold or the owner's authority belongs with someone who can decide.
- The trigger fired. Start the contingency plan. If that also fails, start the fallback plan.
Measuring over time
Teams usually track a few simple indicators:
- Number of open risks above the threshold, by week.
- Percentage of response actions completed on time.
- Total exposure (sum of scores, or expected monetary value) for open risks.
- Reserve remaining compared with exposure remaining.
- Number of risks that occurred, and whether they had been identified in advance.
The last one is the most revealing. If most problems that hit the project were not in the register, the weakness is in risk identification, not in responses.
The script below compares planned and actual scores and flags responses that need attention. It is simplified, but it shows the logic.
risks = [
{"id": "R-07", "before": 12, "expected": 6, "actual": 6, "actions_late": 0},
{"id": "R-09", "before": 16, "expected": 8, "actual": 12, "actions_late": 0},
{"id": "R-11", "before": 8, "expected": 12, "actual": 8, "actions_late": 2},
{"id": "R-15", "before": 9, "expected": 4, "actual": 9, "actions_late": 3},
]
def review(risk, threshold=10):
if risk["actions_late"] > 0:
return "fix execution"
if risk["actual"] <= risk["expected"]:
return "on plan"
if risk["actual"] >= threshold:
return "strategy not working: rethink or escalate"
return "partly working: watch"
for r in risks:
print(r["id"], "->", review(r))Running it prints:
R-07 -> on plan
R-09 -> strategy not working: rethink or escalate
R-11 -> fix execution
R-15 -> fix executionNote that late actions are checked first. A response that was never carried out cannot be judged on its results.
Common errors
- Reviewing only the register, not the work. The register may say "mitigation in progress" while nothing has happened. Ask for evidence.
- Closing a risk too early. A risk whose date has not passed, or whose trigger can still fire, is not closed. Move it to a watch list instead.
- No re-scoring. If scores never change after responses, the register shows no learning and nobody can tell whether the work paid off.
- Ignoring secondary risks. They are often found only when someone looks for them after the response is running.
- Holding the review too rarely. Review high-scoring risks more often than low ones, and tie reviews to schedule events such as milestones and phase gates.
Closing a risk
A risk can be closed when one of these is true: its window has passed without it occurring, it occurred and was dealt with, or its score is reduced to a level where nothing more is needed. Record the outcome and any lessons, such as which response worked, how much it cost, and whether the estimate was right. These notes improve probability and impact estimates on later projects.
Exercise
Risk R-09 had a score of 16 before its mitigation. The plan expected the score to fall to 8. After the actions were finished on time, the score is 12, and the threshold is 10. What does this tell you, and what are two reasonable next steps?
Show answer
The response was carried out but is only partly effective, because 12 is lower than 16 but above both the planned 8 and the threshold of 10. This is a strategy problem, not an execution problem. Reasonable next steps are to strengthen the mitigation with additional actions, to change strategy (for example, transfer part of the exposure through insurance or a contract), or to escalate if the remaining exposure is beyond the project's authority. Also check for secondary risks created by the mitigation, and update the register with the new score and the reason for it.
Exercise
A team's register shows "mitigation in progress" for a high-scoring risk for three months with no change in score. Which monitoring checks would you apply first?
Show answer
First check whether the response actions were actually done and on time, by asking for evidence such as completed tasks or deliverables, because a late or missing action is an execution problem. Then check whether the risk was re-scored after the actions. If actions were done and the score truly did not move, the strategy is weak and should be revised or the risk escalated. Also confirm that the trigger is being watched and that the risk has an active owner.