Sub topic 17
Residual and secondary risks
This chapter assumes you know what a risk is, how to score probability and impact, and the main response strategies for threats and opportunities (avoid, transfer, mitigate, accept, exploit, share, enhance). It explains what is left over after a response, and what new problems a response can create.
Why a response does not end a risk
A response changes a risk. It rarely removes it completely. Two kinds of risk remain after you act.
- Residual risk is the risk that stays after a response has been carried out. It is the same risk, at a lower (or, for opportunities, adjusted) level.
- Secondary risk is a new risk that the response itself creates. It did not exist before the response.
Teams often mix these up. A quick test: if the risk would exist even without your response, it is residual. If it exists only because of your response, it is secondary.
| Aspect | Residual risk | Secondary risk |
|---|---|---|
| Origin | The original risk | The response action |
| Exists without the response? | Yes | No |
| Typical cause | The response only reduces probability or impact | The response adds a supplier, a change, a cost or a dependency |
| Handling | Accept it, or add a further response | Analyze it like any new risk, with its own owner and response |
Residual risk
How it arises
Each strategy leaves something behind, except full avoidance of a risk whose cause is truly removed.
- Mitigate lowers probability or impact but seldom to zero. Testing a component twice still leaves a small chance of failure.
- Transfer moves the financial consequence to another party. The event can still happen, and the schedule delay or reputation damage often stays with you. The other party may also fail to pay.
- Avoid can leave residual risk if the cause is only partly removed. Dropping one feature may not remove every dependency on the same technology.
- Enhance and share raise the chance of an opportunity but do not guarantee it.
Deciding whether it is acceptable
Compare the residual score to the project's risk threshold (the level above which a risk needs action). Three outcomes are common.
- The residual score is below the threshold. Accept it, usually passively, and record it.
- The residual score is still above the threshold. Add a further response, or escalate if the risk is beyond the project's authority.
- The residual score is close to the threshold. Accept it actively with a contingency plan and a trigger.
Estimate the residual score at planning time, before you commit to a response. A response that reduces a score from 16 to 15 rarely justifies its cost.
Secondary risk
How it arises
Every response is a project change, and changes carry uncertainty. Typical sources:
- A new supplier or contractor whose quality or reliability is unproven.
- Insurance or a contract that adds exclusions, disputes, or counterparty risk.
- Extra testing or rework that consumes schedule and may delay other work.
- A technical workaround that is less well understood than the original design.
- Added cost that depletes the contingency reserve.
Example
In the supplier risk used earlier in this tutorial, the team mitigated late delivery of payment terminals by ordering a first batch early and qualifying a second supplier. The response worked on the original risk, but it created a new one: the second supplier's quality is unproven. The register records it as secondary risk R-15.
ID: R-07
Type: Threat
Description: Key supplier may deliver the payment terminals late.
Probability: Medium (3/5) Impact: High (4/5) Score: 12
Strategy: Mitigate
Response: Order a first batch early and qualify a second supplier.
Owner: Procurement lead
Trigger: Supplier misses the first confirmed shipping date
Contingency: Switch to the second supplier for the remaining batches
Residual risk: Second supplier's quality is unproven (secondary risk R-15)
Status: OpenNotice that the contingency plan (switching suppliers) also depends on the second supplier. If R-15 is not managed, the fallback for R-07 is weak. Secondary risks often undermine the contingency plan of the original risk.
The response loop
Responses are planned, then re-analyzed. You repeat this until the remaining exposure is acceptable.
Common errors
- Treating the response as the finish line. The risk is marked "closed" when the action is done, though residual exposure remains.
- Ignoring secondary risks because they look small. A secondary risk can be larger than the original. Score it honestly.
- Not giving secondary risks an owner. An unowned risk is not managed. Assign an owner at the time it is logged.
- Merging residual and secondary risks into one line. They are handled differently, so keep separate register entries and link them by ID.
- Forgetting reserves. Residual and secondary risks that are accepted actively need money or time set aside. See the chapter on contingency and management reserves.
- Overlooking opportunity responses. Enhancing an opportunity can also create secondary risks. An early-adopter incentive may cut margin if too many customers claim it.
Recording them in the register
Record residual risk as a field on the original entry, with its expected score. Record each secondary risk as its own entry with a new ID, and refer to it from the original. Keep these items together:
- The expected residual probability, impact, and score.
- The ID of every linked secondary risk.
- The owner of each secondary risk.
- The reserve set aside, if any.
This keeps the register a complete picture of exposure rather than a list of actions taken.
def residual_score(prob, impact):
return prob * impact
original = residual_score(3, 4)
after_response = residual_score(2, 4)
threshold = 10
print("Original score:", original)
print("Residual score:", after_response)
print("Needs further action:", after_response >= threshold)Here, mitigation lowers probability from 3 to 2, so the residual score is 8, under the threshold of 10. The team can accept it. They must still analyze any secondary risk separately, because this calculation does not account for it.
Exercise
A team transfers the risk of data loss by buying cyber insurance. The policy excludes losses caused by unpatched software, and the team still fears reputation damage after a breach. Identify one residual risk and one secondary risk.
Show answer
Residual risk: reputation damage after a breach, because insurance moves only the financial consequence and the event can still happen. Secondary risk: a claim may be refused under the unpatched-software exclusion (a new counterparty and contract risk that exists only because of the policy).
Exercise
A mitigation reduces a risk's score from 15 to 9. The threshold is 10. The response requires hiring a contractor the team has not worked with before. What should the team do next?
Show answer
The residual score of 9 is under the threshold, so it can be accepted. The team must still log the unproven contractor as a secondary risk, score it, assign an owner, and plan a response. If the secondary risk's score is above the threshold, they should add a response for it or escalate it.