Recording Responses in the Risk Register
A response plan that lives only in a meeting, or in one person's head, will not be carried out. The risk register is the project's shared record of each risk and what the team will do about it. This chapter covers which response fields to record, how to write them so people can act on them, and the errors that make a register useless.
This chapter assumes you know the basic project vocabulary (scope, schedule, budget, stakeholders), that a risk is an uncertain event affecting project objectives, and how to rate probability and impact on a qualitative scale. It also assumes you have met the threat and opportunity strategies from earlier chapters.
What the register has to do
By the time you record a response, the register already holds the identification and analysis fields: an ID, a description, probability, impact, and score. Response planning adds the fields that turn a rated risk into a managed one.
The register serves three readers:
- The risk owner, who needs to know what to do and when.
- The project manager, who needs to see which risks have no plan yet and what the plans cost.
- Stakeholders and sponsors, who need to see which risks are inside the project's authority and which have been escalated to them.
If an entry cannot serve all three, it is incomplete.
The response fields
Record these fields for every risk that gets a response.
| Field | What it holds | Why it matters |
|---|---|---|
| Type | Threat or opportunity | Decides which strategies are valid |
| Strategy | One named strategy, such as Mitigate or Enhance | Shows the intent in one word |
| Response | The specific actions, written as steps | Makes the strategy executable |
| Owner | One named person or role | Gives someone accountability |
| Trigger | The observable event that signals action is needed | Tells people when to act |
| Contingency | The plan to run if the trigger fires | Used with active acceptance and as a backup to other strategies |
| Residual risk | What remains after the response works | Shows the exposure the team is living with |
| Secondary risk | A new risk the response creates | Gets its own entry and its own owner |
| Status | Open, Closed, Occurred, or Escalated | Shows where the risk stands |
Cost and schedule effects of the response also belong here, or in a linked field. Responses are not free, and the register should show what each one costs so that the budget and schedule can absorb it.
A worked threat entry
The first entry records a threat that the team chose to mitigate.
ID: R-07
Type: Threat
Description: Key supplier may deliver the payment terminals late.
Probability: Medium (3/5) Impact: High (4/5) Score: 12
Strategy: Mitigate
Response: Order a first batch early and qualify a second supplier.
Owner: Procurement lead
Trigger: Supplier misses the first confirmed shipping date
Contingency: Switch to the second supplier for the remaining batches
Residual risk: Second supplier's quality is unproven (secondary risk R-15)
Status: OpenRead the entry as a chain. The score of 12 is above the team's threshold, so a response is needed. Mitigation reduces the probability of late delivery. The trigger is a fact anyone can check: a missed shipping date. The contingency says what happens if the mitigation fails. The residual risk points to R-15, so the quality worry becomes a risk with its own owner and does not stay a note inside R-07.
A worked opportunity entry
Opportunities use the same structure with different strategies.
ID: R-11
Type: Opportunity
Description: A larger customer may adopt the pilot early, giving a bulk-purchase discount.
Probability: Low (2/5) Impact: High (4/5) Score: 8
Strategy: Enhance
Response: Offer an early-adopter incentive and schedule a demo for the customer's decision makers.
Owner: Sales manager
Trigger: Customer requests a pricing proposal
Status: OpenHere the response raises the probability by strengthening the conditions that cause the opportunity. The trigger tells the sales manager when to prepare the proposal. Note that this entry has no contingency, because there is no failure path to cover. Not every field applies to every risk, and a blank field should be a deliberate choice.
How the strategy relates to the score
A score and a threshold help choose a starting strategy, which the team then refines by judgment. The function below is deliberately simplified. It captures the first decision: whether the risk is within the project's authority, and whether it clears the threshold.
def pick_strategy(kind, score, within_authority, threshold=10):
if not within_authority:
return "escalate"
if kind == "threat":
return "mitigate" if score >= threshold else "accept"
return "enhance" if score >= threshold else "accept"
print(pick_strategy("threat", 12, True))
print(pick_strategy("opportunity", 6, True))
print(pick_strategy("threat", 20, False))It prints mitigate, accept, and escalate. A real team would also consider avoid, transfer, exploit, and share, along with cost and risk appetite. Whatever the team decides, the register records the outcome and the reasoning behind it.
Linking the register to reserves
Responses draw on money and time. Record the cost of each planned response and tie it to the right reserve:
- Contingency reserve covers identified risks that the team has accepted or planned a contingency for. It is usually held at project level and released when a trigger fires.
- Management reserve covers unidentified risks. It sits outside the project baseline, and using it normally needs approval from management.
If a register entry has an active contingency plan and no funding trail, the plan may fail at the moment it is needed. The register should make it possible to add up the contingency costs and compare the total with the reserve.
Keeping the register alive
An entry is a snapshot. Update it when:
- A trigger fires. Change the status and note which plan is running.
- A response finishes. Re-score the risk to record the residual exposure.
- A response creates a secondary risk. Add a new entry and link it to the original.
- The risk occurs or expires. Close it and record what happened.
Review responses on a regular schedule, and ask whether each one is working, not only whether it was done. If the score has not fallen after a mitigation, the response was either ineffective or incomplete.
Common errors
- Vague responses. "Monitor supplier" is not a response. Write steps with a verb, an object, and a date where possible.
- Owner is a team. A team cannot be held accountable. Name one person or role.
- No trigger. Without a trigger, a contingency plan runs late or never.
- Strategy and actions do not match. An entry labelled Transfer that contains only internal tasks is really Mitigate. Check that the actions do what the strategy name says.
- Residual risk left blank. A blank field implies the response removes the risk completely, which is rarely true.
- Secondary risks buried in notes. They need their own entries so they get scored, owned, and reviewed.
- Entries never updated. A register that is filled in once and never reviewed gives false comfort.
Exercise
A risk entry reads: "Type: Threat. Strategy: Transfer. Response: Team will test the vendor's software more carefully. Owner: Dev team. Trigger: none. Residual risk: none." List the problems with this entry and rewrite the response and owner fields.
Show answer
Problems: (1) The response describes extra testing by the project team, which is Mitigate, not Transfer, so the strategy and actions do not match. (2) The owner is a team, not a named person or role. (3) There is no trigger, so nobody knows when to act. (4) Residual risk is blank, though more testing will not remove all defects. A corrected version: Strategy: Mitigate. Response: Run integration tests on the vendor's software at each release, starting in week 3, and log defects. Owner: QA lead. Trigger: More than five high-severity defects found in one release. Residual risk: Defects not found by testing may still reach production.
Exercise
Why should a secondary risk created by a response get its own register entry, rather than a note inside the original entry?
Show answer
A separate entry gives the secondary risk its own probability, impact, score, owner, and response, and it is included in regular reviews. A note inside the original entry is easy to overlook, has no owner, and is not scored or tracked. Linking the two entries by ID keeps the connection visible.