Sub topic 2
From probability and impact to a risk score
Prerequisites
This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders). It also assumes you know that a risk is an uncertain event that can affect project objectives, and that you have seen qualitative assessment with probability and impact. Here we turn those two inputs into a single score you can use to choose a response.
Why a score is needed
A risk register can hold dozens of risks. The team cannot plan a detailed response for every one. A score gives each risk a number so the team can rank them and decide where to spend effort first.
The score does not predict the future. It is a shared way to compare risks. Treat it as a starting point for judgment, not a replacement for it.
The two inputs
- Probability is how likely the risk event is to happen. It is often rated on a 1 to 5 scale, from very unlikely to almost certain.
- Impact is the effect on a project objective if the event happens. It uses the same 1 to 5 scale, from negligible to severe.
Impact has a direction. A threat has a negative impact, such as extra cost or delay. An opportunity has a positive impact, such as savings or earlier delivery. Teams usually score both on the same scale of size and track the direction in a separate "Type" field. That lets threats and opportunities be ranked with the same method.
Defining the scales
A rating such as "High" means little unless the team defines it. Agree on what each level means before you score anything. Here is an example impact scale for cost and schedule.
| Rating | Value | Cost impact | Schedule impact |
|---|---|---|---|
| Very low | 1 | Under 1% of budget | Under 1 day |
| Low | 2 | 1% to 3% | 1 to 3 days |
| Medium | 3 | 3% to 7% | 3 days to 2 weeks |
| High | 4 | 7% to 15% | 2 to 6 weeks |
| Very high | 5 | Over 15% | Over 6 weeks |
The exact numbers belong to your project. What matters is that everyone reads "4" the same way.
Calculating the score
The most common method multiplies the two ratings.
Score = Probability × Impact
With 1 to 5 scales, scores run from 1 to 25. For example, risk R-07 from the register example has probability 3 and impact 4, so its score is 3 × 4 = 12. Risk R-11 has probability 2 and impact 4, so its score is 8.
The same calculation in code makes the rule explicit and lets you rank many risks at once.
risks = [
{"id": "R-07", "kind": "threat", "probability": 3, "impact": 4},
{"id": "R-11", "kind": "opportunity", "probability": 2, "impact": 4},
{"id": "R-03", "kind": "threat", "probability": 5, "impact": 2},
]
for risk in risks:
risk["score"] = risk["probability"] * risk["impact"]
for risk in sorted(risks, key=lambda r: r["score"], reverse=True):
print(risk["id"], risk["kind"], risk["score"])This prints R-07 (12) first, then R-11 (8), then R-03 (10) sorted between them: the output order is R-07 12, R-03 10, R-11 8.
The probability-impact matrix
Many teams show the result as a grid, with probability on one axis and impact on the other. Each cell is colored by score band, for example low, medium, and high. Reading the grid is faster than reading a list of numbers. It also makes the team's thresholds visible, which the next chapter covers.
Edge cases and common errors
Equal scores are not equal risks
A risk with probability 5 and impact 2 scores 10. A risk with probability 2 and impact 5 also scores 10. They are very different. The first happens almost every time but is minor. The second is rare but could be severe, such as a safety failure. Multiplication hides this difference.
Many teams add a rule: any risk with an impact of 5 gets a review, whatever its score.
Ordinal numbers are not true measurements
The values 1 to 5 are labels in order. They are not equal steps. Impact "4" is not necessarily twice impact "2". Multiplying them gives a useful ranking, but a score of 12 is not "three times" a score of 4 in any real sense. Do not add scores across risks to get a total exposure.
Inconsistent scoring between people
Two people may rate the same risk differently. Reduce this by using defined scales, scoring in a group, and recording the reasoning next to the numbers.
Scoring impact on only one objective
A risk can affect cost, schedule, scope, and quality at once. A common approach is to take the highest impact across the objectives. Another is to score each objective separately. Pick one approach and use it for every risk.
Scores go stale
Probability and impact change as the project moves. A risk that was probable in planning may be nearly impossible once the work is done. Re-score risks at regular reviews.
When a score is not enough
Qualitative scores suit most projects. For large or high-value risks, teams may move to quantitative analysis. They then express impact in money and probability as a percentage. The expected monetary value is probability multiplied by impact in money. A 30% chance of a 50,000 loss has an expected value of 15,000.
Both methods use the same idea: combine how likely with how big.
Exercises
Exercise
Risk A has probability 4 and impact 3. Risk B has probability 2 and impact 5. Calculate both scores. Which risk would you look at more closely even though it does not have the higher score, and why?
Show answer
Risk A scores 4 × 3 = 12. Risk B scores 2 × 5 = 10. Risk A ranks higher. Risk B deserves a closer look because its impact is 5, the highest level. Multiplying hides that a rare but severe event could cause major harm, so many teams review every impact-5 risk regardless of score.
Exercise
A team has scored a risk as probability 3, impact 4. Three months later the supplier has already shipped the first batch on time. What should the team do with the score, and why?
Show answer
Re-score the risk. The shipped batch lowers the probability, so the score should fall below 12. Scores go stale as the project moves, so they must be reviewed at regular intervals and updated when events change the likelihood or impact.