Writing and classifying change requests
Prerequisites and scope
This chapter assumes you know the basic vocabulary of scope, schedule, cost, quality and risk. It also assumes you know what a project management plan is and what baselines are. It covers how to write a change request and how to classify it. Impact assessment, the Change Control Board (CCB) and the decision itself get their own chapters. Here they appear only where they affect how you write the request.
What a change request is
A change request is a formal, written proposal to alter something that is already under control. That can be a baseline, a project document, a deliverable, or the project management plan. It is the single entry point into integrated change control. Nothing is assessed, decided or implemented until a request exists.
Anyone with a stake in the project can raise a request: the sponsor, a team member, the customer, a vendor, or the project manager. The change management plan decides who may submit. The request itself must always be written, even when the idea first came up in a hallway or a meeting.
A change request is not an issue, a risk, or a work item inside the approved scope. An issue is a problem that exists now. A risk is an uncertain future event. A change request asks permission to alter what was agreed. One event can produce several records. A supplier failure is an issue. It may then lead to a change request to switch suppliers.
The four types
Change requests are classified by what they do to the plan or the product. The classification determines who reviews the request and which documents are touched.
| Type | Purpose | Example |
|---|---|---|
| Corrective action | Bring current performance back in line with the plan | Add two testers to recover a task that is running late |
| Preventive action | Make sure future performance stays in line with the plan | Add a weekly dependency check after a vendor delay was identified as likely |
| Defect repair | Fix a nonconforming component found in a deliverable | Fix a login page that fails its acceptance criteria |
| Update | Change a formally controlled document, plan or baseline | Add single sign-on to the scope baseline |
The first three keep the project on its existing course. The fourth changes the course. Updates are the type that most often moves a baseline, so they usually get the closest review.
Two points about classification cause confusion:
- Corrective and preventive actions aim at the plan as it stands. If the only way to recover is to change the plan itself, such as moving the finish date, you also need an update request.
- A defect repair changes the product so that it meets the requirements. It does not change the requirements. If the customer decides the defective behaviour is acceptable and wants the requirement relaxed, that is an update.
Some changes fit more than one branch. A request to fix a defect by redesigning a module may also change the schedule baseline. In that case, classify by the most controlled item affected. Here that is the baseline, so the request is an update. Then list the defect repair in the description. Alternatively, split it into two linked requests. Splitting is better when the parts could be decided differently, for example when the CCB might approve the repair and defer the redesign.
Anatomy of a good request
A request must let a reviewer decide without chasing the author for details. The minimum fields are listed here:
- Identifier. A unique, never reused number such as CR-014. The change log relies on it.
- Title. A short phrase that names the change, not the problem.
- Requester and date. Who asked, and when. This supports traceability and lets reviewers follow up.
- Type. One of the four types above.
- Reason. Why the change is needed. This is the business or technical driver, such as a contract clause, a defect, a regulation, or a cost overrun.
- Description. What exactly will change, including what stays the same.
- Areas affected. Which of scope, schedule, cost, quality, risk and resources it touches.
- Impact summary. Initial estimates for each affected area. The full assessment is covered in a later chapter. The request needs enough to start the review.
- Status and decision fields. Present from the start but empty until the decision is made.
Here is a complete request recorded as YAML. The decision fields are deliberately empty, because only the authorized decision-maker fills them in.
id: CR-014
title: Add single sign-on to the customer portal
requested_by: Product owner
date_submitted: 2026-03-02
type: update # corrective_action, preventive_action, defect_repair, or update
reason: Customer contract now requires SSO
description: >
Integrate the portal with the customer's identity provider.
Existing username and password login stays available for staff accounts.
areas_affected: [scope, schedule, cost, risk]
impact:
scope: Adds one new feature and its test cases
schedule: +3 weeks on the critical path
cost: +18000
risk: New dependency on the identity provider
status: submitted
decision: null
decided_by: null
decision_date: nullThe type here is update because the request adds to the scope baseline. A reviewer can see from the file why it is needed, what it costs, and that no decision has been made.
Writing quality
Most rejected or stalled requests fail for the same few reasons. Check your request against these points before you submit it.
- State the reason, not just the wish. "Add SSO" asks for something. "The customer contract now requires SSO" gives the CCB something to weigh.
- Be specific about what changes. "Improve reporting" cannot be estimated. "Add a monthly cost-variance report to the finance dashboard" can.
- Quantify the impact. "+3 weeks on the critical path" is useful. "Some delay" is not. If an estimate is rough, say so and give a range.
- Name the affected areas honestly. A change that adds a feature almost always touches more than scope. Leaving out risk or resources is a common way for a request to look cheaper than it is.
- Say what happens if it is not approved. This lets the CCB judge urgency and consequences.
- Keep one request to one change. A bundle forces the CCB to approve or reject everything together.
Tracking the request through its statuses
A change request moves through defined states. Allowing only valid transitions prevents the most damaging mistake in change control: implementing a change that was never approved. The rules below are written as a small state model. The same model can be a workflow in a tracking tool.
ALLOWED = {
"submitted": {"under_review"},
"under_review": {"approved", "rejected", "deferred"},
"deferred": {"under_review"},
"approved": {"implemented"},
"implemented": {"closed"},
"rejected": {"closed"},
}
def move(current: str, new: str) -> str:
if new not in ALLOWED.get(current, set()):
raise ValueError(f"Cannot move a change request from {current} to {new}")
return new
status = "submitted"
status = move(status, "under_review")
status = move(status, "approved")
# move(status, "closed") would raise ValueError: an approved change must be implemented firstThere is no path from submitted to implemented. A request has to pass through review and an explicit decision. A rejected request goes straight to closed, which keeps it in the record rather than deleting it. A deferred request returns to review later, for example when funding becomes available.
A submission check can sit in front of this model. A request with a missing mandatory field should be returned to the author, not sent to review.
REQUIRED = ["id", "title", "requested_by", "date_submitted", "type", "reason", "areas_affected"]
TYPES = {"corrective_action", "preventive_action", "defect_repair", "update"}
def validate(request: dict) -> list[str]:
problems = [f"missing field: {name}" for name in REQUIRED if not request.get(name)]
if request.get("type") and request["type"] not in TYPES:
problems.append(f"unknown type: {request['type']}")
return problems
example = {"id": "CR-015", "title": "Fix login timeout", "type": "defect_repair"}
print(validate(example))Running this prints the list of missing fields: requested_by, date_submitted, reason and areas_affected. An empty list means the request can go to review.
Edge cases
Changes the project manager may decide alone. The change management plan can set a threshold. Below it, the project manager approves a change without the CCB. A typical rule is a small cost or schedule change that stays within an agreed tolerance and leaves baselines untouched. Even then, the change is written down and logged. Only the approval route differs.
Verbal requests. A sponsor's spoken request in a corridor is a prompt to write a request, not authority to act. Record it, submit it, and let it follow the normal route.
Requests that arrive after the work is done. Sometimes a team makes a change first and asks later. Submit the request anyway. Mark it clearly as retroactive, assess it, and let the CCB accept or reverse the work. Do not hide it.
Withdrawn and duplicate requests. If a requester withdraws a request, close it with a reason. If two people submit the same change, link them and review once. Both identifiers stay in the log.
Requests that change the request process. If the change is to the change management plan itself, such as a new approval threshold, it is an update like any other. It still goes through review.
Common errors
- Choosing the type by how big the change feels, not by what it does to the plan.
- Writing the solution as the reason, such as "need a new server", instead of the driver, such as "response times exceed the contract limit".
- Submitting a request with only the scope impact filled in.
- Starting work while the request is still under review, because the change seems obviously right.
- Combining unrelated changes into one request so that a minor item rides through with a major one.
Exercise
During testing, the team finds that the invoice export drops the last row of every file, which breaks the agreed acceptance criteria. Separately, the customer now asks to have the export in a new file format that was not in the original scope. Which type is each change request, and should they be one request or two?
Show answer
The dropped row is a defect repair. A delivered component fails its requirements, and fixing it restores conformance without changing the requirement. The new file format is an update, because it adds to the scope baseline. They should be two requests, because the CCB may reasonably approve the repair at once and defer or reject the new format. Bundling them would force a single decision on two unrelated changes.
Exercise
A request reads: "Title: Fix schedule. Reason: We need more time. Areas affected: schedule." List three problems and say how you would correct each.
Show answer
First, the title names no change. Replace it with a specific title, such as "Extend UAT phase by two weeks". Second, the reason is a wish, not a driver. State why, for example "Test environment was unavailable for ten working days". Third, the affected areas are incomplete. Extending a phase also affects cost through extra staff time and may affect resources and risk. Add those areas with estimates. The request should also state a type, such as update, and describe exactly which baseline dates change.