Sub topic 1
Baselines: What a Change Is Measured Against
Prerequisites
This chapter assumes you already know the following:
- Basic project management vocabulary: scope, schedule, cost, quality and risk.
- What a project management plan is, and that it contains subsidiary plans such as the scope management plan and the schedule management plan.
- Common project roles: sponsor, project manager and stakeholder.
You do not need to know anything about change requests yet. This chapter explains the thing every change request is compared against.
Why a change needs something to be measured against
A change is a difference between what was agreed and what is now wanted. If nothing was agreed, nothing can change. It would only be a new decision.
A baseline is the approved version of a plan component. You can only change it through a formal change control procedure. Once approved, the baseline becomes the reference point for two kinds of questions:
- Performance: is the project on track compared with the approved plan?
- Change: how far does a proposed request move the project away from the approved plan?
Without baselines, a team can say it is "a bit behind" or "slightly over", but it cannot show how far, or whether a request caused it. With baselines, you can state a variance as a number: "Forecast finish is 3 weeks after the baseline finish."
Before approval, a plan is a draft. You can edit a draft freely, and the project manager can rework it with the team. After approval, edits to the baseline must go through integrated change control. That is the point where change management starts.
The three core baselines
Three baselines are central in most projects. Each covers one major area.
| Baseline | What it fixes | Typical contents |
|---|---|---|
| Scope baseline | What the project will deliver | Approved project scope statement, work breakdown structure (WBS), WBS dictionary |
| Schedule baseline | When the work will happen | Approved schedule model: activities, dates, dependencies, critical path |
| Cost baseline | What the work will cost | Approved time-phased budget, excluding management reserve |
Scope baseline
The scope baseline has three parts that are approved together:
- The project scope statement describes the deliverables, acceptance criteria, assumptions and constraints.
- The work breakdown structure (WBS) is a hierarchy that divides the work into smaller pieces, down to work packages.
- The WBS dictionary gives details for each WBS element, such as a description, owner and acceptance criteria.
A change to any of these three parts changes the scope baseline. Adding a feature adds work packages to the WBS. Narrowing an acceptance criterion changes the WBS dictionary. Both need approval.
Schedule baseline
The schedule baseline is the approved version of the schedule model. It records planned start and finish dates for activities and milestones. Day-to-day schedule updates, such as marking an activity done or recording an actual start date, do not change the baseline. They are recorded against it. The baseline moves only when a change is approved. Re-planning to match reality without approval is one of the pitfalls covered in the last chapter.
Cost baseline
The cost baseline is the approved, time-phased budget. "Time-phased" means the budget is spread over the periods in which the money will be spent. It includes contingency reserves, which cover identified risks. It does not include management reserve, which is held for unknown, unplanned work. Using management reserve normally requires a change to the cost baseline, because it moves money from the reserve into the baseline.
Beyond the three: other baselines and plans
The three baselines above are often combined into the performance measurement baseline. This is the integrated reference used to measure cost and schedule performance, for example with earned value analysis.
Other plan components can also be baselined, depending on the organization and the project:
- Quality baseline, recording quality objectives and metrics.
- Risk baseline, recording the agreed risk thresholds and the initial risk assessment.
- Requirements baseline, recording the approved requirements.
- Other subsidiary plans, such as the communications or resource management plan, which are placed under change control once approved.
Not every project baselines everything. The change management plan, covered later in this tutorial, states which items are under formal control. A good rule is to baseline anything that other parts of the plan depend on, or that the customer has agreed to.
How baselines relate to the project management plan
The project management plan contains the baselines. It also contains the subsidiary plans that explain how each area will be managed. A single change often touches several of these.
The diagram shows two directions of flow. A request is measured against the current baselines. When it is approved, the baselines and plans are updated, and the updated version becomes the new reference for the next request.
How a baseline is set and versioned
Baselines are not permanent. They are fixed for a period, then replaced by an approved new version. The usual steps are:
- The team develops the plan component as a draft.
- Stakeholders with authority review it. This usually includes the sponsor and sometimes the customer.
- The component is formally approved and labelled as a baseline, with a version number and date.
- From then on, changes go through integrated change control.
- When a change is approved, a new version of the baseline is issued. The old version is kept.
Keeping old versions matters. It lets you show what was approved at any date, compare versions, and explain why a variance exists. If you overwrite the old version, you lose the history, and you can no longer tell a real overrun from a re-planned target.
A worked example
A team is building a customer portal. The approved baselines are:
- Scope baseline v1.0: 12 features, 41 work packages.
- Schedule baseline v1.0: finish on 2026-09-30.
- Cost baseline v1.0: 240,000 budget at completion.
In March, the customer asks for single sign-on. The team estimates it adds one feature and 5 work packages, moves the finish by 3 weeks, and adds 18,000. This request is compared against v1.0 and the differences are stated clearly.
If the Change Control Board approves it, the team issues:
- Scope baseline v1.1: 13 features, 46 work packages.
- Schedule baseline v1.1: finish on 2026-10-21.
- Cost baseline v1.1: 258,000.
Version 1.0 stays on file. Later progress reports compare actual results with v1.1. If the request is rejected, nothing changes and v1.0 stays in force.
A short script can make this comparison explicit. This example is complete and runs as shown.
from datetime import date, timedelta
baseline_v1 = {
"features": 12,
"work_packages": 41,
"finish": date(2026, 9, 30),
"budget": 240_000,
}
change = {
"features": 1,
"work_packages": 5,
"schedule_days": 21,
"cost": 18_000,
}
def apply_change(baseline: dict, change: dict) -> dict:
"""Return a new baseline version. The old one is left untouched."""
return {
"features": baseline["features"] + change["features"],
"work_packages": baseline["work_packages"] + change["work_packages"],
"finish": baseline["finish"] + timedelta(days=change["schedule_days"]),
"budget": baseline["budget"] + change["cost"],
}
baseline_v1_1 = apply_change(baseline_v1, change)
print("v1.0:", baseline_v1)
print("v1.1:", baseline_v1_1)The function returns a new dictionary instead of modifying the old one. This mirrors the practice of keeping prior baseline versions.
Baselines versus current plans and forecasts
Beginners often confuse the baseline with the current plan. They are different.
| Item | Changes how often | Purpose |
|---|---|---|
| Baseline | Only through approved changes | Fixed reference for comparison |
| Current schedule or budget | Regularly, as work is updated | Shows the latest plan and actuals |
| Forecast | At each reporting period | Predicts the likely finish date or final cost |
A project can have a baseline finish of 30 September, a current plan of 5 October, and a forecast of 14 October. The gaps between those numbers carry information. If the baseline is silently moved to match the forecast, the gaps vanish and the problem is hidden.
Edge cases
Tolerances and thresholds
Some organizations define thresholds, which are limits within which the project manager may act without a formal change request. For example, a variance of up to 2% on a work package might be handled by the project manager alone. Thresholds belong in the change management plan or the relevant subsidiary plan. They must be approved in advance. They do not allow the project manager to approve any change alone.
Rebaselining
Rebaselining means replacing the baseline with a new one, usually because the old one is no longer a realistic reference. It needs formal approval. It happens most often after a major approved change, after a recovery plan, or when the sponsor accepts that the original plan cannot be met.
Rebaselining has a cost. It erases the visible variance, so performance indicators look better than they are in reality. Keep the original baseline on file, and report cumulative variance against the original as well as the current version where that matters to stakeholders.
Baselines in iterative projects
In agile and hybrid projects, the product backlog changes constantly, and that is normal. The fixed items are usually the iteration scope once it has started, the release commitment, the budget envelope, or contractual milestones. A later chapter covers how change is handled in these settings. For now, note that "no baseline" is a choice about what to fix, not the absence of any reference.
Contract-driven baselines
When a contract fixes scope, price or dates, the contract acts as a baseline too. A change that affects those terms may also need a formal contract amendment, in addition to approval by the Change Control Board.
Summary of the main points
- A baseline is an approved plan component that can be changed only through formal change control.
- The three core baselines are scope (statement, WBS, WBS dictionary), schedule and cost. Together the schedule and cost baselines form the basis of the performance measurement baseline.
- Progress updates and forecasts are recorded against baselines. They do not change them.
- Every approved change produces a new baseline version, and the old version is kept.
- Rebaselining and thresholds need rules agreed in advance.
Exercise
A project's cost baseline is 500,000. Halfway through, the team finds the work will cost 530,000 and the project manager edits the cost baseline to 530,000 so the report shows no variance. What is wrong with this, and what should have happened?
Show answer
The baseline was changed without an approved change request, so the 30,000 overrun is hidden and the baseline no longer shows what was agreed. The project manager should have kept 500,000 as the baseline, reported the 30,000 as a variance or forecast overrun, and submitted a change request if the cost increase needed approval. If the Change Control Board approved it, a new cost baseline version of 530,000 would be issued and the original version kept on file.
Exercise
Name the three parts of the scope baseline, and say which of these changes would require a change request: (a) marking an activity as complete, (b) adding a new work package to the WBS, (c) recording an actual start date that is two days late.
Show answer
The scope baseline consists of the project scope statement, the WBS and the WBS dictionary. Only (b) requires a change request, because it alters the approved scope baseline. Items (a) and (c) are progress records made against the baseline and do not change it, unless the late start causes a variance beyond the thresholds defined in the change management plan.