Approving, Rejecting or Deferring a Change
Prerequisites
This chapter assumes you know what a change request contains and how its impact is assessed. It also assumes you know that a Change Control Board (CCB) is the group that holds decision authority, and that the change management plan sets the rules for who decides what. Here the focus is on the decision itself: the possible outcomes, how to choose among them, and how to record and act on the result.
What a decision does
A change request that has been assessed is still only a proposal. Nothing in the baselines, the plan or the deliverables may change until someone with authority decides. The decision is the control point of integrated change control. It turns an assessed request into one of three things: authorized work, a closed request, or a request parked for later.
A good decision has four properties:
- It is made by the person or body named in the change management plan.
- It rests on the impact assessment, not on who asked.
- It is recorded with a reason, the decision maker and the date.
- It is communicated to everyone the change affects.
The three outcomes
| Outcome | Meaning | What happens next |
|---|---|---|
| Approved | The change is authorized, possibly with conditions. | Work is planned and carried out, then baselines and plans are updated. |
| Rejected | The change will not be made. | The request is closed with the reason recorded. |
| Deferred | The change is not decided now but may return. | The request waits for a stated trigger or date, then goes back to review. |
A fourth reaction is common in practice: the board asks for more information. This is not a decision. The request stays in review while the requester or the assessor fills the gap. If you record "more information needed" as a decision, you create a request that looks resolved but has no outcome.
Approving
Approval authorizes the work and the changes to the plan that come with it. Approve when the benefit justifies the cost, the schedule effect and the risk, and when the change fits the project's objectives. Approval often carries conditions, and you should write them into the record. Examples:
- The sponsor must release the additional budget before work starts.
- The change must be delivered in the next release, not the current one.
- A named reviewer must sign off on the revised design.
An approval without a defined scope is a weak approval. If the board approves "SSO for the portal" but the request does not say which login providers are included, the team will later argue about what was authorized.
Rejecting
Reject when the change does not serve the project, the impact is too high for the benefit, it duplicates another request, or the request cannot be done within the project's constraints. A rejection must carry a reason. The reason matters for two purposes:
- The requester can see what would have to be different for a new request to succeed.
- The log shows later that the request was considered rather than ignored.
A rejection is not a verdict on the requester. The same change can be rejected today and approved in a later project phase when conditions are different. In that case the requester submits a new request that references the old one.
Deferring
Defer when the change may be worthwhile but cannot be decided or scheduled now. Typical reasons:
- A decision depends on an event, such as a contract renewal or a vendor answer.
- The change is valid, but the budget or team capacity is unavailable this period.
- The change belongs in a later phase or release.
A deferral needs a return condition: a date, a milestone or a named trigger. Without one, deferred requests pile up and silently become rejections. Assign someone to check the deferred list at each review point. When the trigger occurs, the request returns to review. It is reassessed, because the project may have changed since the original assessment.
The decision path
The state diagram shows the path a request takes after assessment. Note that a deferred request goes back to review and never straight to approval.
Enforcing the path in a tool
If you track change requests in a tool or a script, encode the allowed transitions so that nobody can skip a step. The following program implements the diagram and demonstrates both a valid path and a blocked one.
ALLOWED = {
"submitted": {"under_review"},
"under_review": {"approved", "rejected", "deferred"},
"deferred": {"under_review"},
"approved": {"implemented"},
"implemented": {"closed"},
"rejected": {"closed"},
}
def move(current: str, new: str) -> str:
if new not in ALLOWED.get(current, set()):
raise ValueError(f"Cannot move a change request from {current} to {new}")
return new
status = "submitted"
status = move(status, "under_review")
status = move(status, "approved")
print("Status is now:", status)
try:
move(status, "closed")
except ValueError as error:
print("Blocked:", error)The blocked move is the point. An approved change cannot be closed until it has been implemented, so an approved request cannot disappear without the work being done or formally cancelled. A real tool would add a transition from approved to a cancelled state if your process allows withdrawal. Keep that as an explicit, recorded path rather than a shortcut to closed.
Recording the decision
The request record from the previous chapters has decision fields that were empty at submission. The board fills them in. Here is CR-014 after approval with conditions.
id: CR-014
title: Add single sign-on to the customer portal
requested_by: Product owner
date_submitted: 2026-03-02
type: change
reason: Customer contract now requires SSO
areas_affected: [scope, schedule, cost, risk]
impact:
scope: Adds one new feature and its test cases
schedule: +3 weeks on the critical path
cost: +18000
risk: New dependency on the identity provider
status: approved
decision: approved
decided_by: Change Control Board
decision_date: 2026-03-12
rationale: Contract requirement; no alternative meets the customer deadline
conditions:
- Sponsor releases 18000 from management reserve before work starts
- Identity provider test account is available by 2026-03-20The rationale and conditions fields are additions to the minimal template. Use them. The rationale lets a later reader understand the decision without attending the meeting. The conditions turn vague approval into checkable commitments.
Criteria for choosing
Boards decide more consistently when they agree on criteria in advance, ideally in the change management plan. A practical set:
- Does the change serve a project objective, a legal or contractual duty, or a necessary correction?
- Is the total impact acceptable across scope, schedule, cost, quality, risk and resources?
- Is there a cheaper or smaller way to reach the same goal?
- Is there capacity, funding and an owner to do it?
- What is the cost of not doing it, or of doing it later?
Work through the questions in order. A "no" on the first usually points to rejection. A "yes" on the first with a "no" on the fourth often points to deferral. A strong "yes" on all of them points to approval.
Authority and thresholds
Not every change goes to the full board. The change management plan usually sets thresholds, for example:
| Impact | Typical decision maker |
|---|---|
| Within a tolerance the project manager controls | Project manager |
| Beyond that tolerance, or touching a baseline | Change Control Board |
| Beyond the board's authority, such as a major budget increase | Sponsor or steering committee |
Apply the rule by the largest impact, not the average. A change that costs little but moves the delivery date past a contractual deadline belongs at the level that owns the deadline. When a decision exceeds the board's authority, the board's output is a recommendation to the higher level, and the request stays in review until that level answers.
Edge cases
- Conflict of interest. If the requester sits on the board, they should present the request and leave the vote. Record that they abstained.
- Split or conditional outcomes. A request with several parts can be approved in part. The clean way is to split it into separate requests so each has one outcome and one log entry. Approving "half" of a single request leaves unclear what is authorized.
- Changed circumstances. An approval can become invalid before work starts, for example if the funding condition fails. State in the record what happens then. The usual rule is that the request returns to review.
- Resubmission. A rejected request that returns with new facts is a new request that references the old one. Reopening the old record hides the history.
- Expired deferrals. Set a maximum deferral period. When it passes, the request is either reviewed again or closed as rejected, with a recorded reason.
- Timing. Decide within the time the plan allows. A request that waits weeks often decides itself, because the team starts the work informally or the opportunity is gone.
After the decision
The decision opens three follow-up actions, each handled in more detail elsewhere in the plan:
- Enter the outcome in the change log so it can be traced.
- Tell the requester and every stakeholder named in the impact assessment. Include the reason, not only the result.
- For approved changes, schedule the work and prepare the baseline and plan updates. For deferred changes, set the return trigger. For rejected changes, close the request.
Common mistakes
- Treating "we will look at it later" as a deferral without a trigger or owner.
- Approving without conditions the sponsor actually set, so the budget is not there when work starts.
- Rejecting without a reason, which pushes the same request back repeatedly.
- Letting the team start work on a request still in review.
- Deciding at the wrong level because the impact was judged on cost alone.
Exercise
A change request to add a new report type is assessed at +2 weeks and +9000. The board likes the idea but the sponsor says no budget exists until the next quarter begins. Which outcome fits, what must the record contain, and why should the request not be marked as rejected?
Show answer
Defer it. The change has merit, and the blocker is funding timing, not value. The record must state the reason (no budget until next quarter), a return trigger (the start of the next quarter, or the sponsor confirming funds), and an owner who checks the deferred list. When the trigger occurs, the request returns to under review and is reassessed, because schedule, cost and risk may have changed. Rejecting would close the request and lose the context, so the requester would have to start over without a link to the earlier assessment.