Sub topic 8
Keeping a Change Log
This chapter assumes you know the basic project vocabulary (scope, schedule, cost, quality, risk). It also assumes you know what a change request is and how a Change Control Board (CCB) decides on one. Here you will learn what a change log is, what it should record, and how to keep it useful for the life of the project.
What a change log is for
A change log is a record of every change request submitted on a project, together with its current status and its decision. It lists requests that were approved, rejected, deferred, and still open. It is the project's memory of how the plan moved away from its baseline and why.
The log serves four purposes:
- Traceability. Anyone can follow a requirement, a cost increase or a schedule slip back to the request and decision that caused it.
- Status visibility. The project manager can see which requests are waiting, which are approved but not yet implemented, and which are closed.
- Accountability. Each decision names who made it and when.
- Learning. Patterns in the log show where the project's requirements, estimates or stakeholder communication are weak.
The log differs from the change request itself. A change request is a full document with description, reason and impact analysis. The log is a summary index that points to those documents. Keep the detail in the request and keep the log short enough to scan.
Where the log sits in the process
Every request enters the log when it is submitted, not when it is decided. The decision updates the same entry. Implementation and closure update it again. The entry therefore changes over time, while the request it describes keeps its identity.
Notice that rejected requests stay in the log. Deleting them destroys the evidence that the request was considered. If the same idea returns six months later, the log shows what was decided and why.
What each entry should contain
The fields below are a practical minimum. Your change management plan may require more, and the plan's rules take precedence.
| Field | Purpose | Example |
|---|---|---|
| ID | Unique, never reused | CR-014 |
| Title | Short description | Add single sign-on to the customer portal |
| Requester | Who asked | Product owner |
| Date submitted | Starts the response clock | 2026-03-02 |
| Type | Corrective action, preventive action, defect repair, or update | Update |
| Status | Current position in the workflow | Approved |
| Impact summary | One line per affected area | +3 weeks, +18000 cost |
| Decision | Approved, rejected or deferred | Approved |
| Decided by | Person or body with authority | CCB |
| Decision date | When the decision was made | 2026-03-12 |
| Rationale | Why that decision was reached | Contract requires SSO |
| Link | Where the full request and assessment are stored | Tracker URL |
| Baseline version affected | Which baseline changed | Schedule baseline v3 |
The last field is often missed. Without it, you can see that a change was approved but not which baseline version absorbed it. That makes it hard to reconstruct what the plan said on a given date.
Entries should be written for a stranger
Write each entry so that a person who joins the project a year later can understand it. "Approved per call with Sam" fails this test. "Approved by CCB on 2026-03-12 because the customer contract now requires SSO; schedule baseline moved to v3" passes.
A log as structured data
You can keep the log in a spreadsheet, a tracker or a repository. Whatever the tool, use consistent fields. The record below shows a request after the CCB has decided. It follows the same fields as the request you wrote earlier, now with the decision fields filled in.
id: CR-014
title: Add single sign-on to the customer portal
requested_by: Product owner
date_submitted: 2026-03-02
type: change
areas_affected: [scope, schedule, cost, risk]
impact:
scope: Adds one new feature and its test cases
schedule: +3 weeks on the critical path
cost: +18000
risk: New dependency on the identity provider
status: approved
decision: approved
decided_by: Change Control Board
decision_date: 2026-03-12
rationale: Customer contract requires SSO; sponsor confirmed funding
baseline_affected: [scope baseline v2, schedule baseline v3, cost baseline v3]
link: https://tracker.example.com/CR-014The status and decision fields look similar but are not the same. A request that is approved and later implemented still has the decision "approved", while its status moves to "implemented" and then "closed". Keeping both fields lets you report decisions over time without losing the current state.
Keeping the log consistent with the workflow
A log is only trustworthy if its statuses follow the allowed workflow. If someone can set a request straight from "submitted" to "implemented", the log hides the fact that no one reviewed it. You can enforce the rules in a tracker with workflow settings, or in a small script that validates entries.
The following Python example checks a list of status updates against the allowed transitions. It reports every illegal jump it finds.
ALLOWED = {
"submitted": {"under_review"},
"under_review": {"approved", "rejected", "deferred"},
"deferred": {"under_review"},
"approved": {"implemented"},
"implemented": {"closed"},
"rejected": {"closed"},
}
history = [
("CR-014", "submitted"),
("CR-014", "under_review"),
("CR-014", "approved"),
("CR-014", "implemented"),
("CR-015", "submitted"),
("CR-015", "implemented"), # skipped review and approval
]
def audit(history):
last = {}
problems = []
for cr_id, status in history:
previous = last.get(cr_id)
if previous is not None and status not in ALLOWED.get(previous, set()):
problems.append(f"{cr_id}: {previous} -> {status} is not allowed")
last[cr_id] = status
return problems
for line in audit(history):
print(line)Running it prints:
CR-015: submitted -> implemented is not allowedThis is the kind of check a project office can run before each status meeting. A single flagged line means work started without an approved decision.
Handling each decision outcome in the log
Each outcome needs slightly different bookkeeping.
Approved
Record the decision, the approver, the date, and the baselines that will change. Keep the status as "approved" until the work is done. An approved entry that stays open for weeks is a signal. Either the work is blocked or the team is not following the plan.
Rejected
Record the reason in enough detail that the requester understands it. Move the entry to "closed" once the requester has been told. Do not delete it.
Deferred
A deferred request is neither accepted nor refused. Record what condition or date will bring it back, such as "Review again after release 2 ships" or "Revisit at the next budget cycle". Without a revisit trigger, a deferred request becomes a forgotten one. Some teams add a revisit_on field and review all deferred entries at a fixed interval.
Reviewing the log
Writing entries is not enough. Review the log on a schedule, for example at each CCB meeting and at each phase gate. Look for the following.
- Stale open items. Requests in "submitted" or "under review" for longer than the response time in the change management plan.
- Approved but not implemented. These may be waiting on a dependency, or forgotten.
- Implemented but not closed. The baseline update or communication step may be missing.
- Clusters. Many requests from one stakeholder or against one deliverable often point to unclear requirements.
- Totals. The cumulative cost and schedule effect of approved changes. Many small changes can add up to a large shift that no single decision revealed.
The fifth check matters most for control. Each request may look small. The log is the only place where you can see their sum.
Access, history and retention
Decide who can read and who can edit the log. Most stakeholders should be able to read it, because open visibility discourages side agreements. Only the project manager or a designated change coordinator should edit statuses and decisions. Other people submit requests, and the coordinator updates the log.
Keep the history of edits. If someone corrects a decision date, the log should show the original value and the correction. Many trackers do this automatically. In a spreadsheet, add a notes column or use version history.
At project close, the log becomes part of the project records and a source of lessons learned. Archive it with the final baselines.
Emergency changes and the log
An emergency change may be implemented before the CCB can meet. The log entry must still exist. Create it as soon as possible, mark it as an emergency, name who authorized the action, and attach it to the next CCB agenda for after-the-fact review. A change that is implemented and never logged is the same as an informal approval.
Common mistakes
- Logging only approved changes. You lose the record of what was refused and why.
- Logging at decision time. Requests that never reach the CCB are never recorded, and the project cannot see how much informal work is happening.
- Vague rationale. "Approved" with no reason cannot support an audit or a later dispute.
- Reusing IDs. If CR-009 is deleted and a new request takes the number, older emails and documents point at the wrong request.
- No link to baselines. The log says what was approved but not which plan version changed.
- Letting the log drift from reality. Work is done, but statuses are not updated. The log then misreports the project.
Exercises
Exercise
A team's change log contains only approved requests. Name two problems this causes.
Show answer
First, rejected and deferred requests are lost, so if the same idea returns nobody can see that it was already considered or why it was refused. Second, the log cannot show how many requests the project receives or how much pressure for change it is under, which hides patterns such as unclear requirements. Requests that are still open are also invisible.
Exercise
CR-022 shows status "implemented", but the schedule baseline has not changed and the log has no "baseline affected" entry. What does this tell you, and what should you do?
Show answer
The change was probably built without the follow-up step of updating the baseline, so the plan no longer matches the work being done. Confirm with the project manager whether the approved impact (for example the extra weeks) was applied. If it was not, update the schedule baseline through the agreed process, record the new version in the log entry, communicate the update to stakeholders, and only then close the request.
Exercise
A request was deferred in March with the note "revisit later". In November nobody has looked at it. What was missing from the entry, and how do you prevent this?
Show answer
The entry had no revisit trigger, such as a date or an event like "after release 2". Add a revisit field to every deferred entry, and review all deferred items at a fixed interval, for example at each CCB meeting or phase gate.