Sub topic 9
Implementing Approved Changes and Updating Baselines
This chapter assumes you know the basic project vocabulary (scope, schedule, cost, quality, risk) and what a project management plan contains. It also assumes you have read the earlier chapters on change requests, impact assessment and the Change Control Board (CCB). The chapter covers what happens after the CCB records "approved": the change is carried out, the plan and baselines are revised, and everyone affected is told.
Approval is not the end of the process
An approved change request (CR) is permission to change the project. The work and the paperwork still have to happen. Two things commonly go wrong at this point.
- The team does the work but nobody updates the baselines. The plan then describes a project that no longer exists, and later variance reports compare actual results with an obsolete target.
- The baselines are updated but the work is done differently from what the CR described. The approved impact assessment no longer matches reality.
Both failures break traceability, the ability to explain why the project looks the way it does. Implementation is therefore controlled work. It follows the approved CR, it is verified, and it ends with a recorded baseline update.
The implementation flow
The decision, the work and the baseline update happen in a fixed order.
Step 1: Turn the decision into work
Start from the approved CR and its impact assessment. A CR that says "add single sign-on" is too vague to execute. Break it into concrete items:
- Work packages or backlog items, each with an owner.
- New or changed activities in the schedule, with their dependencies.
- Budget lines or reserve draws that cover the added cost.
- Updated risks, such as the new dependency on an identity provider in CR-014.
- Quality work: new test cases, acceptance criteria, reviews.
Keep the CR identifier on everything. If a task, a cost line and a test case all carry "CR-014", you can later reconstruct the full effect of that change.
Step 2: Respect the conditions of approval
The CCB often approves with conditions: a spending cap, a deadline, a requirement to re-review if the estimate grows. Record these conditions on the CR and treat them as limits. If the work will exceed what was approved, the original approval does not cover it. Raise a new CR or send the existing one back for re-review. Do not quietly absorb the overrun.
Step 3: Verify before you rebaseline
Verification asks whether the delivered change matches what the CR said it would deliver. It is separate from the routine quality checks on the rest of the project. Typical evidence includes test results, a review or demonstration, and a check that the affected deliverables meet their acceptance criteria. If verification fails, the CR stays open and the work returns to the team, as the loop in the diagram shows.
Updating the baselines
A baseline is the approved version of the scope, schedule or cost against which performance is measured. Only an approved change may alter a baseline. The update has two properties.
- It happens through change control. Nobody edits a baseline directly because a forecast looks bad.
- It preserves history. The earlier baseline version is kept, because you still need it to explain past variances and to audit decisions.
Which baseline changes depend on the change
Not every approved change touches every baseline. Use the impact assessment to decide.
| Approved change | Scope baseline | Schedule baseline | Cost baseline | Other documents to update |
|---|---|---|---|---|
| New feature added | Yes: new requirement, WBS element | Yes: new activities | Yes: added budget | Requirements, risk register, test plan |
| Deadline moved earlier | Rarely | Yes | Often (crashing adds cost) | Resource plan, risk register |
| Defect repair | No, if it restores the approved scope | Sometimes | Sometimes | Quality records, issue log |
| Reallocation of budget between work packages | No | No | Yes | Cost estimates, funding limits |
| Corrective action to recover from delay | No | Only if the target changes | Only if funding changes | Resource assignments, status reports |
A corrective action brings work back in line with the existing baseline, so it often leaves the baseline unchanged. That is why the CR type matters: it predicts how much updating is needed.
Rebaselining versus re-forecasting
These two are easy to confuse.
- A forecast is your current estimate of where the project will end up. It changes every reporting period, with no approval needed.
- A rebaseline replaces the target itself. It needs an approved change.
If you rebaseline to hide a variance that no approved change explains, your performance measures stop meaning anything. After a legitimate rebaseline, earned value and trend reports restart from the new baseline. Keep the old figures available, labeled by version.
A small model of baseline versioning
The following Python code shows the principle: each rebaseline produces a new immutable version that records the CR behind it, and old versions stay in the history.
from dataclasses import dataclass, replace
@dataclass(frozen=True)
class Baseline:
version: int
budget: int
duration_weeks: int
source_cr: str
def rebaseline(current: Baseline, cr_id: str, cost: int, weeks: int) -> Baseline:
"""Return a new baseline version; never modify the old one."""
return replace(
current,
version=current.version + 1,
budget=current.budget + cost,
duration_weeks=current.duration_weeks + weeks,
source_cr=cr_id,
)
history = [Baseline(version=1, budget=240000, duration_weeks=30, source_cr="initial")]
history.append(rebaseline(history[-1], "CR-014", cost=18000, weeks=3))
for b in history:
print(f"v{b.version}: budget={b.budget}, weeks={b.duration_weeks}, from {b.source_cr}")Running it prints:
v1: budget=240000, weeks=30, from initial
v2: budget=258000, weeks=33, from CR-014The numbers match the impact stated in CR-014 (+18000 cost, +3 weeks on the critical path). The dataclass is frozen, so a version cannot be edited after the fact. A real project keeps this history in a document management or planning tool, but the rule is the same.
A caveat on the model: adding the CR's weeks to the total duration is valid here only because the CR affects the critical path. A change on a path with float may not move the end date at all, so the schedule baseline should be recalculated from the network, not by adding numbers.
Updating the plan and project documents
The baselines are part of the project management plan. A change often also affects other parts of it. Check these in turn:
- Scope management and requirements documents. Add the new requirement, with traceability to its source.
- Schedule and cost documents. Update the schedule model, resource calendars, estimates and funding requirements.
- Risk register. Add risks that the change introduces, and close risks it removes.
- Quality plan and test cases. Include the new acceptance criteria.
- Communications and stakeholder documents. Reflect new stakeholders or new reporting needs.
- Contracts and procurement. Some changes need a contract amendment, which has its own approval path.
Document version numbers should move together. If the schedule is at version 3 and the cost plan is still built on version 2 assumptions, the plan contradicts itself.
Communicating the result
An approved change affects people who were not at the CCB meeting. Communicate it in a way that reaches them and gives them what they need to act.
- Who: the people named in the change management plan's distribution list, the work owners, and stakeholders whose deliverables, budget or dates moved.
- What: the CR identifier, the decision, the conditions, the new baseline version and its effective date, and what changed for the recipient.
- When: before the work starts for those who must act, and at baseline update for everyone else.
For a rejected or deferred CR, the requester still needs a reply with the reason. The same rule applies to a change that was approved for a different scope than requested.
Closing the loop
The final steps are administrative but essential.
- Update the change log with the implementation date, verification result and the baseline version produced.
- Link the CR to the changed work items, documents and baseline versions.
- Set the CR status to implemented, then closed, following the allowed transitions you saw in the status model.
- Record lessons that would improve the next change, such as an estimate that proved too low.
Closure also gives you a chance to compare actual effort with the estimate in the impact assessment. Consistent underestimates suggest that impact assessments need more input from the people who do the work.
Edge cases
- Partial implementation. If only part of a change can be delivered, do not rebaseline for all of it. Split the CR or open a follow-up CR for the remainder.
- Several approved CRs at once. Two changes may touch the same activity. Apply them in a defined order and check the combined effect on the critical path, because impacts that were small separately can add up.
- Change approved, then funds withdrawn. A CR may rely on funding that disappears. Take it back to the CCB. An approved CR with no funding is a baseline error waiting to happen.
- Retroactive documentation. If work was done before approval, document it honestly and treat it as a control failure to review. Do not backdate approval.
Exercise
A CCB approves CR-021, which adds a reporting module. The impact assessment estimated 5 weeks and 30000. Midway through, the developers find the work will take 8 weeks and cost 45000. What should the project manager do, and which baseline should show the figures now?
Show answer
Stop treating the original approval as sufficient, because the work now exceeds what the CCB approved. Send CR-021 back to the CCB (or raise a new CR) with the revised impact. Until it is re-approved, the schedule and cost baselines stay at their last approved version and the extra figures appear only in the forecast. After re-approval and verification, rebaseline to the new version (+8 weeks, +45000 in total for this change), record it in the change log, and tell the stakeholders.
Exercise
Why is a corrective action often implemented with no baseline update, while a new feature almost always needs one?
Show answer
A corrective action brings performance back in line with the existing baseline, so the target is unchanged. A new feature changes what the project is meant to deliver, so scope, and usually schedule and cost, need new approved targets.