Sub topic 5
Assessing the impact of a change
This chapter assumes you know the basic project vocabulary (scope, schedule, cost, quality, risk). It also assumes you know what a project management plan and its baselines are, and that you have seen a change request record. Here you learn how to turn "someone wants this changed" into evidence the Change Control Board (CCB) can decide on.
Why impact assessment comes before the decision
A change request states what someone wants. It does not say what the change will cost the project. The impact assessment fills that gap. It compares the project as currently baselined with the project as it would look if the change were approved.
The assessment is an input to the decision, so it has to be complete and neutral. Two failures are common:
- Under-assessment. Only the obvious area is analyzed. A "small scope addition" gets approved, and the schedule, test effort and risk consequences appear later.
- Advocacy. The requester writes the assessment and it reads as a sales pitch. Assessments should come from the people who understand each area, reviewed by the project manager.
The areas to assess
Assess every change against the same checklist, even when you expect most areas to show "no impact". Recording "none" with a reason shows the area was considered, not skipped.
| Area | Question to answer | Typical evidence |
|---|---|---|
| Scope | What deliverables, requirements or work packages are added, changed or removed? | Work breakdown structure (WBS), requirements traceability matrix |
| Schedule | Which activities move, and does the critical path or the end date change? | Schedule model, float values, dependencies |
| Cost | What is the direct cost, the indirect cost and the effect on reserves? | Estimates, rate tables, budget and contingency |
| Quality | Does the change alter acceptance criteria, test effort or defect risk? | Quality plan, test plan, acceptance criteria |
| Risk | Which new risks appear, and which existing risks grow or shrink? | Risk register, risk scores |
| Resources | Who is needed, when, and are they available? | Resource calendars, skills matrix, contracts |
Stakeholder expectations and contract terms sometimes need a seventh check. A change can be cheap yet breach a vendor agreement or a regulatory commitment, so look for those constraints too.
A repeatable assessment process
- Clarify the request. Confirm what is asked and why. Many requests describe a solution ("add a button") when the need is something else ("let users resume a saved order"). Assess the need, then the proposed solution, and consider cheaper alternatives.
- Assign area owners. The scheduler assesses schedule, the cost analyst assesses cost, the test lead assesses quality, and so on. Set a deadline. The change management plan often fixes how many days an assessment may take.
- Assess against the current baselines. Use the approved baselines, not your memory of them. If earlier approved changes have not yet been merged into the baselines, include them. Otherwise you compare against a project that no longer exists.
- Check cross-area effects. One change spreads across areas. More scope means more testing, which means more resource demand. Added resources raise cost and may create a risk of onboarding delays.
- Combine and recommend. Produce one summary with the numbers, the assumptions and a recommendation. Include options such as approving as requested, approving a reduced version, or deferring.
Worked example: the SSO change
Take the change request CR-014 from earlier in this tutorial: single sign-on (SSO) for the customer portal. The record already lists its affected areas: scope, schedule, cost and risk. A full assessment checks all six and reveals more.
id: CR-014
impact:
scope: Adds one feature (SSO login) and 12 test cases; no existing feature removed
schedule: +3 weeks on the critical path (integration cannot start before identity provider access)
cost: +18000 direct (labor 15000, licence 3000); no indirect cost identified
quality: Adds security testing; acceptance criterion "login works with company accounts" added
risk: New dependency on the identity provider; risk R-22 raised, score 12
resources: Needs one security-aware developer for 3 weeks; none free until week 9
assumptions:
- Identity provider test environment is available by week 6
- No change to the existing password login
assessed_by: [Scheduler, Cost analyst, Test lead, Resource manager]The resource line is the kind of finding that a quick look misses. Nobody with the right skills is free until week 9, so the "+3 weeks" figure may be optimistic. The assessment should say so and either revise the schedule number or list the dependency as an assumption.
Schedule impact: float matters
An added activity does not always move the end date. It only does if it consumes more than the available total float, which is the time an activity can slip without delaying the project finish. On the critical path, float is zero.
def schedule_delay(added_days: int, total_float_days: int) -> int:
"""Days the project end date moves when work is added to a path."""
if added_days < 0 or total_float_days < 0:
raise ValueError("days must not be negative")
return max(0, added_days - total_float_days)
# 15 working days of new work on a path with 5 days of float
print(schedule_delay(15, 5)) # 10: the end date moves by 10 days
# The same work on a path with 20 days of float
print(schedule_delay(15, 20)) # 0: absorbed by float, but float is now used upThe second result needs care. A change that is "absorbed by float" still has a schedule impact. The path now has 5 days of float instead of 20, so any later slip hits the end date sooner. Record the remaining float in the assessment.
Cost impact: direct, indirect and reserves
Break cost into parts so the CCB can see what it is paying for:
- Direct cost: labor, materials, licences and purchases caused by the change.
- Indirect cost: the cost of the assessment itself, extra management time, re-planning, retesting and retraining.
- Schedule-driven cost: if the end date moves, time-based costs (team salaries, rentals, hosting) continue for longer.
- Reserves: say whether the cost would be paid from contingency reserve (for identified risks) or management reserve (for unplanned work), or needs a budget increase. Management reserve normally needs approval to use, and spending it changes the budget.
def total_cost_impact(direct: float, indirect: float,
weekly_run_rate: float, delay_weeks: float) -> float:
"""Direct and indirect change cost plus the cost of running the project longer."""
return direct + indirect + weekly_run_rate * delay_weeks
# SSO: 18000 direct, 2000 indirect, team costs 9000 per week, 3 weeks delay
print(total_cost_impact(18000, 2000, 9000, 3)) # 47000The listed cost in CR-014 was 18000. With indirect cost and three extra weeks of team cost, the full impact is 47000, which is a different decision. Whether the weekly run rate applies depends on whether the team would otherwise be released or reassigned. State that assumption in the assessment.
Risk impact
Look in both directions. A change can add a risk (a new dependency on the identity provider), raise an existing one (a tight test window gets tighter), or reduce one (replacing an unsupported library). Add or update entries in the risk register, with probability, impact and an owner. If a risk response needs money or time, include it in the cost and schedule figures.
Quantifying uncertainty
Early assessments are estimates. Reflect that honestly:
- Give a range when you cannot give a number, such as "+2 to +4 weeks".
- List assumptions, so the CCB knows what must hold for the estimate to stay valid.
- Mark the confidence level. If a figure rests on an unconfirmed vendor quote, say so.
- Do not hide uncertainty by padding. If you add a buffer, say so and show its size.
Where an assessment would itself be costly, for example a detailed design study, the change management plan may allow a staged approach. The CCB first approves funds for the assessment, then decides on the change.
Edge cases
- Zero-impact changes. Some changes affect no baseline, such as a wording fix in an internal document. Check your change management plan. It may classify them as pre-approved or as changes the project manager can approve alone. Still log them.
- Bundled requests. If one request contains three separate changes, split it. A CCB that must accept or reject a bundle cannot approve the good part.
- Cumulative effect. Ten changes of two days each add up to four working weeks. Report the total approved change to date next to each new assessment so the CCB sees the trend.
- Competing changes. Two requests may both be fine alone but conflict, for example both needing the same developer in the same weeks. Assess each against the baseline plus the other if both are pending.
- Decreases. Descoping requests also need assessment. Removing a feature can break dependencies, reduce benefits promised in the business case, or trigger contract penalties.
Common mistakes in assessment
- Assessing only the area the requester mentions.
- Copying the requester's estimate without review.
- Ignoring indirect costs and the cost of retesting.
- Reporting "no schedule impact" because the work fits in float, without noting the float used.
- Omitting assumptions, so the numbers cannot be checked later.
- Letting the assessment drag on, so the change is made informally while the CCB waits.
What the assessment hands on
The finished assessment goes to the CCB with a recommendation. That recommendation is the next chapter's subject. Keep the assessment on file with the change request, because it explains the decision and is the reference for the baseline update after implementation. If implementation costs differ from the assessed figures, that difference is also a useful lesson for estimating later changes.
Exercise
A change request adds 12 working days of work to an activity path that has 8 working days of total float. The team costs 6000 per week (5 working days), and the direct cost of the change is 10000. Indirect cost is 1500. Using the approach in this chapter, what is the schedule delay, and what is the total cost impact if the delay is paid for at the team's weekly run rate?
Show answer
Schedule delay = max(0, 12 - 8) = 4 working days. At 5 working days per week this is 0.8 weeks. Schedule-driven cost = 6000 x 0.8 = 4800. Total cost impact = 10000 + 1500 + 4800 = 16300. The assessment should also note that all float on that path is now used up, and state the assumption that the team would otherwise be released or reassigned.
Exercise
A requester asks for a "quick addition" and proposes an impact of "scope: one extra report, nothing else". Name three other areas you would check before sending this to the CCB, and one question for each.
Show answer
Examples: Schedule - does the report's work sit on the critical path or use up float? Quality - what new test cases and acceptance criteria does the report need? Resources - who builds and tests it, and are they free in that period? Cost, risk, or contract terms are also valid choices if the question is specific.