Sub topic 11
Configuration Management and Change Control
This chapter covers how configuration management supports integrated change control. It assumes you know the basic vocabulary of scope, schedule, cost, quality and risk. It also assumes you know what a project management plan is and what roles such as sponsor, project manager and stakeholder do. You should already have seen how a change request moves through impact assessment, a Change Control Board (CCB) decision, and implementation with a baseline update.
Two Disciplines, One Goal
Change control decides whether a change should happen. Configuration management makes sure you always know exactly what the project's products and documents are, which version is current, and what state they are in.
The two are often confused because they share records and meetings. They answer different questions.
| Question | Discipline |
|---|---|
| Should we make this change? | Integrated change control |
| What exactly exists today, and in which version? | Configuration management |
| Who approved this version, and when? | Both: the decision comes from change control, the version record from configuration management |
| Does the delivered item match its approved description? | Configuration management (verification and audit) |
Without configuration management, an approved change has nothing precise to act on. People may edit the wrong copy of a document, build from an old design, or ship a version nobody approved. Without change control, configuration management only records whatever people did, with no check that it was permitted.
Key Terms
- A configuration item (CI) is any component you choose to place under formal control. Examples are a requirements specification, a design drawing, a source code module, a test plan, a server image, or a contract.
- A configuration is the set of CIs, with their versions, that together make up a product at a point in time.
- A version is an identified state of a CI. Each approved edit creates a new version.
- A configuration baseline is an approved, frozen set of CI versions. It is different from the scope, schedule and cost baselines, but it works the same way. You can only change it through a formal process.
- A configuration management system is the set of tools and procedures that stores CIs, tracks their versions and records their status. It sits inside the wider project management information system.
The Four Activities
Configuration management is usually described as four connected activities.
- Identification. Decide which items become CIs. Give each one a unique identifier, a version scheme and an owner. Over-identifying wastes effort, because every CI needs controlled edits. Under-identifying leaves important items uncontrolled. A common rule is to control anything that other work depends on, anything contractually required, and anything expensive to recreate.
- Control. Allow changes to CIs only through approved change requests. Check items out for editing and check them back in as new versions. Block direct edits to baselined items.
- Status accounting. Record and report the state of every CI: current version, pending change requests, approved changes not yet implemented, and history. This is the record people consult when they ask "what is the latest approved version?"
- Verification and audit. Check that each CI matches its documented requirements and that the records match reality. A functional audit confirms that the item performs as specified. A physical audit confirms that the item delivered is the one the records describe.
How the Two Processes Connect
A change request almost always names CIs. The impact assessment lists which items change. The CCB decision authorizes edits to those items. After implementation, configuration management records the new versions and re-establishes the configuration baseline.
The diagram shows the handoffs. Change control owns the decision steps. Configuration management owns the identification of affected items and the recording of results.
Traceability Through Identifiers
The link between the two is the identifier. The change log from the previous chapter records CR-014. The configuration records for each affected CI should cite CR-014 against the new version. With both records in place, you can answer two questions in either direction:
- Starting from a change request: which items did it alter, and in which versions?
- Starting from an item version: which approved change request produced it?
If a version has no change request behind it, someone changed a controlled item without approval. If a change request is marked implemented but no new version exists, the work was never recorded or never done.
Extending the Change Request Record
The change request from this tutorial can carry a field that names the configuration items. This makes the impact assessment concrete and gives configuration management a work list.
id: CR-014
title: Add single sign-on to the customer portal
areas_affected: [scope, schedule, cost, risk]
configuration_items:
- id: CI-REQ-007
name: Portal requirements specification
current_version: 2.3
planned_version: 2.4
- id: CI-DES-012
name: Portal authentication design
current_version: 1.1
planned_version: 2.0
- id: CI-TST-003
name: Portal regression test suite
current_version: 4.0
planned_version: 4.1
status: approvedThe request names three items. When the work is done, status accounting should show these items at their planned versions, each citing CR-014.
Checking Records Against Reality
A simple script can compare approved changes with version records. The following Python program flags mismatches in both directions. It runs as shown.
change_requests = {
"CR-014": {
"status": "implemented",
"items": {"CI-REQ-007": "2.4", "CI-DES-012": "2.0"},
},
"CR-015": {
"status": "approved",
"items": {"CI-TST-003": "4.1"},
},
}
# What configuration management actually holds: item -> (version, change request cited)
versions = {
"CI-REQ-007": ("2.4", "CR-014"),
"CI-DES-012": ("2.0", "CR-014"),
"CI-TST-003": ("4.0", "CR-009"),
"CI-UI-021": ("1.3", None),
}
def audit(change_requests, versions):
findings = []
# Implemented changes must show the planned versions in the records.
for cr_id, cr in change_requests.items():
if cr["status"] != "implemented":
continue
for item, planned in cr["items"].items():
actual = versions.get(item)
if actual is None or actual[0] != planned or actual[1] != cr_id:
findings.append(f"{cr_id}: {item} does not show version {planned}")
# Every version should cite a change request.
for item, (version, cr_id) in versions.items():
if cr_id is None:
findings.append(f"{item} version {version} cites no change request")
elif cr_id not in change_requests and cr_id != "CR-009":
findings.append(f"{item} cites unknown request {cr_id}")
return findings
for line in audit(change_requests, versions):
print(line)The script reports one finding: CI-UI-021 version 1.3 cites no change request. The CR-009 exception stands in for an older request that is no longer in this small sample. Real tools query the change log and the version repository directly, but the logic is the same: every version needs an approved reason, and every implemented change needs a matching version.
Configuration Baselines and Releases
A configuration baseline is created at defined points, such as the end of design or a release. Teams label it with a name or tag, for example design-baseline-1 or release-2.0. Later edits then happen in new versions and never alter the labelled set.
Some practical rules:
- Baseline at decision points. Create a configuration baseline when a phase gate is passed or a release is cut, not at arbitrary times.
- Keep old baselines retrievable. You may need to rebuild a past release to reproduce a defect or satisfy an audit.
- Release only baselined versions. A deliverable handed to the customer should come from a labelled set of approved versions, so you can state exactly what was delivered.
- Keep the baselines consistent with each other. If the scope baseline changes because of an approved request, the matching requirements and design CIs must change in the same step. A new scope baseline with an old requirements specification is a stale baseline.
Edge Cases
Changes to items that are not baselined
Drafts and working notes do not need a change request. The project's change management plan should say at which point an item becomes controlled, for example when it is first reviewed and accepted. Before that point, editing is free. After it, every edit needs authority.
Minor changes
Many projects pre-authorize small changes to CIs, such as fixing a typo in an approved document, with no CCB review. The change management plan sets a threshold, and configuration management still records the new version. The edit is quick, but it is not untracked.
Emergency changes
An emergency edit may touch a controlled item before approval. Configuration management should still capture the new version at once, mark it as provisional, and link it to the emergency change request. The after-the-fact review then confirms it or reverses it. If the version was never recorded, a rollback becomes guesswork.
Parallel changes to the same item
Two approved requests may edit the same CI at the same time. Check-out rules, branching, or sequencing must prevent one overwriting the other. Impact assessment should look for overlap, because two individually small changes can conflict.
Third-party and contracted items
A supplier may hold CIs that your project depends on. The contract should require the supplier to follow compatible version identification and to notify you of changes. Otherwise your configuration records will describe a product that no longer matches what you receive.
Common Errors
- Treating configuration management as a tool purchase. A repository holds versions, but it does not decide which items are controlled, who may edit them, or how status is reported.
- Controlling too many items. Hundreds of trivial CIs produce a stream of requests and slow the project, so people start bypassing the process.
- Letting records drift. If check-ins are optional, the status accounting becomes wrong, and then nobody trusts it.
- Skipping audits. Records can look consistent while the delivered product differs. The physical audit catches that.
- Closing a change request before the records are updated. The request should close only after the new versions and baseline are recorded.
Summary Points
- Change control decides. Configuration management identifies, tracks and verifies what is being decided on.
- The four activities are identification, control, status accounting, and verification and audit.
- A shared identifier, such as
CR-014, links change log entries to item versions in both directions. - Emergency, minor, parallel and supplier changes all need explicit rules in the change management plan.
Exercise
A project's change log shows CR-021 as "implemented". The configuration records show the affected requirements document still at version 3.2, the version that existed before the request, and show no version citing CR-021. Name two possible explanations and the action you would take for each.
Show answer
Explanation 1: the work was done but the new version was never checked in or recorded. Action: locate the edited document, check it in as the next version citing CR-021, and update the baseline, then reinforce that a request cannot close before check-in. Explanation 2: the work was never done or was done on an uncontrolled copy, and the status was set to implemented in error. Action: reopen CR-021, find out what was actually delivered, and complete or redo the implementation under control. In both cases a physical audit should confirm which version the team and customer are actually using.
Exercise
Why can a project that has excellent change control but weak configuration management still ship an unapproved version of a deliverable?
Show answer
Change control only decides which changes are allowed. If configuration management does not control versions, people can edit or build from the wrong copy, or release an item that was never baselined. The decision was correct, but nothing ensures that the delivered item matches it. Identification, controlled check-in and check-out, status accounting and audit close that gap.