Sub topic 7
Reaction plans: what to do when the process drifts
A control chart tells you that something changed. It does not tell anyone what to do about it. The reaction plan connects the signal to a response. This chapter assumes you can read a run chart or control chart, that you know the difference between common-cause and special-cause variation, and that you have seen a control plan row with its fields. Here you will learn what a reaction plan must contain, how to write one that people follow, and how to test it before handover.
Why a signal needs a pre-agreed response
Without a written reaction plan, three things usually happen when a chart signals:
- Nobody notices, because nobody was told the chart is theirs.
- Someone notices and reacts differently each time, so the response depends on who is on shift.
- Everyone notices, argues about whether it is real, and the argument outlasts the drift.
A reaction plan removes the decision from the moment of stress. It is written during the Control phase, when the project team still understands the process and the owner can still challenge the wording.
A reaction plan has to answer five questions:
- What counts as a signal?
- Who is told, and how fast?
- What is the immediate action to protect the customer?
- Who investigates the cause, and by when?
- How is the outcome recorded and the plan updated?
Triggers: defining a signal
A trigger is the exact condition that starts the plan. Write it so that two people looking at the same chart reach the same answer.
For an individuals chart, common triggers are:
- A single point above the upper control limit or below the lower control limit.
- A run of eight consecutive points on the same side of the center line.
- A run of six points steadily rising or falling.
Each added rule catches smaller shifts sooner, but it also raises the false alarm rate. A false alarm costs the owner's time and teaches the team to ignore the chart. For most transactional processes, start with the first two rules and add others only when a real shift went undetected.
Triggers apply to different things, and your plan should say which one:
| Trigger type | What it watches | Typical response |
|---|---|---|
| Control chart signal | Statistical drift in the process | Investigate for a special cause |
| Specification breach | A single output outside the customer requirement | Contain the output, then investigate |
| Process input failure | A required input is missing or wrong | Stop and correct before continuing |
| Audit finding | A step is not being followed | Retrain or revise the standard work |
A control limit signal and a specification breach are not the same event. Limits describe what the process does. Specifications describe what the customer needs. A process can sit inside its limits and outside its specification, which means the process is stable but not capable. It can also trip a limit while every output still meets the specification. The plan should treat these cases differently.
Containment first, root cause second
The most useful structure in a reaction plan separates two kinds of action:
- Containment protects the customer right now. Examples are holding a batch, manually checking the next 20 invoices, or routing work to a backup path. It is fast, temporary, and does not need a diagnosis.
- Corrective action removes the cause. It needs investigation, and it ends with a change to the process, the standard work, or the control plan.
Mixing these up causes two common failures. Teams that skip containment keep shipping bad output while they investigate. Teams that stop at containment treat symptoms indefinitely, and the manual check quietly becomes permanent.
A containment action should have a stated end condition, such as "until the next 10 points are inside the limits."
Decision flow
The diagram shows a typical flow for a chart signal. Notice that the investigation can end in two different ways: finding a special cause, or deciding the signal was noise.
Writing the plan down
The control plan from earlier chapters has a single reaction_plan field. For anything beyond a simple characteristic, that field should point to a fuller record. The example below expands one reaction plan into its parts.
reaction_plan:
characteristic: Approval cycle time (days)
triggers:
- id: T1
rule: "One point above the upper control limit or below the lower control limit"
- id: T2
rule: "Eight consecutive points on one side of the center line"
notify:
who: Accounts Payable Manager
within: "1 working day"
containment:
action: "Team lead checks every invoice older than 3 days each morning"
ends_when: "Next 10 points are inside the limits"
investigation:
owner: Team lead
due: "2 working days after notification"
method: "Review workflow timestamps for the affected invoices; check staffing, system outages, and invoice volume"
escalation:
condition: "No cause found, or the signal repeats within 4 weeks"
to: Finance Director
record:
where: "Control log, one entry per signal"
fields: [date, trigger_id, cause, action, result]Three details matter here. Each person has a named role, not "the team." Each step has a time limit, so a signal cannot sit unattended. Escalation has a condition, which prevents both under-reaction and constant escalation.
Checking triggers in code
Triggers should be mechanical enough to automate. The script below applies two of the rules to new data, using the limits formula from the chart chapter. The baseline gives a center near 2.95 days and limits near 2.30 and 3.60.
def individuals_limits(values):
"""Return (lower, center, upper) for an individuals chart."""
moving_ranges = [abs(b - a) for a, b in zip(values, values[1:])]
mr_bar = sum(moving_ranges) / len(moving_ranges)
center = sum(values) / len(values)
return center - 2.66 * mr_bar, center, center + 2.66 * mr_bar
def find_signals(points, lower, center, upper, run_length=8):
"""Return a list of (index, trigger_id) for each point that fires a trigger."""
found = []
for i, x in enumerate(points):
if x > upper or x < lower:
found.append((i, "T1"))
if i + 1 >= run_length:
window = points[i + 1 - run_length : i + 1]
if all(v > center for v in window) or all(v < center for v in window):
found.append((i, "T2"))
return found
baseline = [2.8, 3.1, 2.9, 3.0, 3.2, 2.7, 3.0, 2.9]
lower, center, upper = individuals_limits(baseline)
new_points = [3.1, 3.2, 3.3, 3.1, 3.4, 3.2, 3.3, 3.5]
for index, trigger in find_signals(new_points, lower, center, upper):
print(f"Point {index}: trigger {trigger} fired, follow the reaction plan")Every new point stays inside the limits, so T1 never fires. After the eighth point, all eight sit above the center line, so T2 fires. This is the shift that a limits-only check would miss. The process has moved to a slightly slower average, and the reaction plan gets the owner looking at it before the drift reaches a limit.
Keep the limits fixed from the baseline period. If you recalculate them every time a point arrives, the limits follow the drift and the signal disappears.
Common errors
- Vague reactions. "Investigate and take appropriate action" gives no one anything to do. Name the action, the person, and the deadline.
- Reacting to every point. Moving the process after each ordinary variation is tampering. It increases variation. Only a trigger starts the plan.
- No authority. If the person named in the plan cannot stop a batch or change a step, the plan fails at the first real signal. Check authority with the owner.
- No log. Without a record, you cannot see repeated causes, and the plan never improves.
- Changing limits quietly. Limits should be revised only after a verified process change, with the revision recorded.
Testing the plan before handover
The reaction plan belongs in the handover checklist for a reason. Before the process owner signs acceptance, run a walkthrough using a realistic signal, either a past data point or a made-up one. Ask the owner and the team lead to say aloud who they notify, what they do first, and where they record it. Gaps found here cost minutes. Gaps found during a real drift cost customer output.
Record what the walkthrough revealed and fix the plan. Then file the final version with the control plan.
Exercise
Exercise
A weekly individuals chart for call-handling time shows eight consecutive points above the center line, but no point is outside the control limits. The team lead says no action is needed because nothing is out of control. Is that correct, and what should the reaction plan require?
Show answer
The team lead is not correct if the reaction plan includes the run-of-eight trigger. Eight points on one side of the center line indicate a likely shift in the process mean, which is a special cause even though no point crossed a limit. The plan should require notifying the owner within the stated time, starting containment if the longer handling time harms customers, and investigating what changed (for example staffing, a system update, or call mix). The outcome should be logged. If the plan only includes the limit rule, this case shows a gap that should be added.
Exercise
Exercise
Name two differences between a containment action and a corrective action, and say why a containment action needs an end condition.
Show answer
Containment protects the customer immediately and is temporary and fast, while corrective action removes the cause and is a lasting change to the process, standard work, or control plan. Containment does not require a diagnosis, but corrective action does. A containment action needs an end condition because otherwise it becomes a permanent workaround, which adds cost and hides the fact that the cause was never fixed.