Sub topic 6
Monitoring with control charts
This chapter assumes you know the DMAIC phases, the difference between common-cause and special-cause variation, and what a CTQ characteristic is. It also assumes you can read a run chart. Here you will learn how a control chart supports the control plan, how to calculate limits for an individuals chart, and how to avoid the mistakes that make charts useless after handover.
What a control chart does in the Control phase
A control plan names what to measure, how often, and who acts. A control chart supplies the rule for deciding when a new measurement needs action. It plots each measurement in time order against three lines:
- The center line, which is the process average.
- The upper control limit (UCL).
- The lower control limit (LCL).
The limits describe what the process does when only common-cause variation is present. A point outside them is a signal that something special has happened. That signal triggers the reaction plan, which is covered in a later chapter.
Control limits are not specification limits. A specification limit comes from the customer or the CTQ. A control limit comes from the process's own behavior. A process can sit inside its control limits and still miss the specification. It can also be outside the specification while perfectly stable.
| Line | Where it comes from | What it answers |
|---|---|---|
| Specification limit | Customer requirement or CTQ | Is the output acceptable? |
| Control limit | The process's own data | Has the process changed? |
| Target | Business or design goal | Where do we want to be? |
Do not draw specification limits on an individuals chart as if they were control limits. Mixing the two leads people to react to points that are normal variation, or to ignore real shifts that stay inside the specification.
Choosing a chart type
The data type decides the chart. Most Control phase work uses one of a few common charts.
| Data | Example | Typical chart |
|---|---|---|
| Continuous, one value per period | Weekly average approval time | Individuals and moving range (I-MR) |
| Continuous, small subgroups | Five fill weights per hour | Xbar-R |
| Count of defective items | Rejected invoices out of those checked | p chart |
| Count of defects | Errors per document | c or u chart |
The control plan example in this tutorial tracks approval cycle time with an individuals chart. That choice fits because the measurement is continuous and the plan records one value per week. When you cannot form meaningful subgroups, the individuals chart is the safe default.
Calculating individuals chart limits
An individuals (I) chart uses the moving range, which is the absolute difference between each point and the one before it. The average moving range, written MR-bar, estimates short-term variation.
The limits are:
- Center = the mean of the baseline values.
- UCL = center + 2.66 × MR-bar.
- LCL = center − 2.66 × MR-bar.
The constant 2.66 equals 3 ÷ 1.128. The value 1.128 is the factor (d2) that converts an average moving range of size 2 into an estimate of standard deviation. So the limits sit three estimated standard deviations from the center.
The following code calculates the limits from a baseline and then checks new points against two rules. The first rule is a point beyond a limit. The second is eight consecutive points on the same side of the center line, which signals a sustained shift.
def individuals_limits(values):
"""Return (lower, center, upper) control limits for an individuals (I) chart."""
moving_ranges = [abs(b - a) for a, b in zip(values, values[1:])]
mr_bar = sum(moving_ranges) / len(moving_ranges)
center = sum(values) / len(values)
# 2.66 = 3 / d2, where d2 = 1.128 for moving ranges of size 2
return center - 2.66 * mr_bar, center, center + 2.66 * mr_bar
def find_signals(values, lower, center, upper):
"""Return a sorted list of (index, rule) for each rule violation."""
found = []
run = 0
side = 0
for i, v in enumerate(values):
if v > upper or v < lower:
found.append((i, "beyond limits"))
current = 1 if v > center else -1 if v < center else 0
if current != 0 and current == side:
run += 1
else:
run = 1 if current != 0 else 0
side = current
if run == 8:
found.append((i, "8 in a row on one side of center"))
return sorted(found)
baseline = [2.8, 3.1, 2.9, 3.0, 3.2, 2.7, 3.0, 2.9]
lower, center, upper = individuals_limits(baseline)
print(f"LCL={lower:.2f} center={center:.2f} UCL={upper:.2f}")
new_points = [3.0, 3.1, 3.2, 3.1, 3.3, 3.0, 3.2, 3.1, 4.1]
for index, rule in find_signals(new_points, lower, center, upper):
print(f"Point {index}: {rule} -> follow the reaction plan")With this baseline the limits are about 2.30 and 3.60 around a center of 2.95. The last new point (4.1) is beyond the upper limit. The eight points before it are all above the center line, so the run rule also fires at index 7. That is an earlier warning than the limit breach, which is why teams combine rules.
Setting up the baseline correctly
The limits are only as good as the data behind them. Follow these rules when you compute them.
- Use data from the improved process, collected after the change has settled. Limits calculated from the old process describe a process that no longer exists.
- Use enough points. Many practitioners want at least 20 to 25 points. With very few points the limits are unstable, so mark them as provisional.
- Check the baseline for signals first. If it contains out-of-control points with known special causes, remove those points and recalculate.
- Freeze the limits once they are set. Do not recalculate them every time a new point arrives, or the limits will chase the data and hide shifts.
- Recalculate only after a deliberate process change, and record the reason.
The eight-point baseline in the code example is too short for real use. It is there to keep the arithmetic easy to follow.
Connecting the chart to the measurement system
A control chart cannot separate process variation from measurement noise. If the measurement method is poor, the limits become wide and real shifts stay hidden. Before you rely on a chart, confirm that the measurement system is adequate, as described in the previous chapter. For a timestamp report, check that the clock source and the field definitions stay the same. For manual inspection, check that inspectors apply the same criteria.
Rules for signals
A single rule catches large shifts but is slow to catch small ones. Common rules include:
- One point beyond the control limits.
- Eight consecutive points on one side of the center line.
- Six consecutive points steadily rising or falling.
Each added rule increases the chance of a false alarm. Choose a small set, write it into the control plan, and apply it the same way every time. The process owner should not have to decide in the moment which rules count.
Common errors
- Reacting to every point. Moving inside the limits is normal variation. Adjusting the process after each wiggle adds variation. This is called tampering.
- Treating limits as targets. Control limits do not tell you whether the process is good enough.
- Mixing populations. Combining data from two shifts, machines, or teams with different behavior produces limits that describe neither.
- Ignoring autocorrelation. If each value depends strongly on the previous one, as with a backlog that carries over, the standard limits give too many false alarms. Consider a different sampling interval or ask a statistician.
- Charts nobody reads. A chart without a named reviewer and a review date is decoration. The control plan should name who looks at it and when.
What to record in the control plan
For each charted characteristic, the control plan should state the chart type, the baseline period, the frozen limits, the signal rules, the review frequency, and the person who reviews the chart. This is the information the process owner needs when the project team leaves. Handing over a chart without these details means handing over a picture the owner cannot interpret.
Exercise
A team has an individuals chart for weekly approval time with center 2.95 days, average moving range 0.24 days, and frozen limits. Using the 2.66 constant, what are the limits to two decimals? Then say whether a new weekly value of 3.5 days triggers the reaction plan, and whether it meets the 3-day specification.
Show answer
UCL = 2.95 + 2.66 × 0.24 = 2.95 + 0.64 = 3.59 days. LCL = 2.95 − 0.64 = 2.31 days. A value of 3.5 is inside the limits, so it does not trigger the reaction plan, since it is within normal variation. It does exceed the 3-day specification, so the process is stable but not capable of always meeting the requirement. That is a process-improvement question, not a reaction-plan question.
Exercise
A process owner recalculates the control limits every week using the latest 20 points. After a slow upward drift over two months, no point ever falls outside the limits. What went wrong, and what should the control plan say?
Show answer
Recalculating each week lets the limits move with the data, so the drift is absorbed into the new center and limits. The plan should freeze limits from a stated baseline, recalculate only after a deliberate process change with a logged reason, and include a run rule (such as six points steadily rising or eight on one side of the center) to catch drift.