Sub topic 4
Anatomy of a control plan
This chapter assumes you know the DMAIC phases, the difference between common-cause and special-cause variation, and what a critical-to-quality (CTQ) characteristic is. You should also be able to read a run chart or control chart. Earlier chapters covered why the Control phase exists and how to decide what to control. Here you build the document that holds those decisions.
What a control plan is
A control plan is a written record, kept with the process owner, of how each important characteristic of an improved process will be watched and what happens when it moves. It is a working document that the owner uses every week. It is not a project deliverable that gets filed and forgotten.
A good plan answers five questions for every controlled characteristic:
- What is being controlled, and what is the target?
- How is it measured, and how often?
- What tool decides whether the process is behaving normally?
- What happens when the signal says it is not?
- Who does that?
If any answer is missing, the plan has a gap that someone will fill with a guess during a bad week.
The fields of a control plan row
Each controlled characteristic gets one row, or one entry in a file. The fields below are the common core. Your organization may add columns, such as a part number, a revision date, or a link to a work instruction.
| Field | What it states | Example |
|---|---|---|
| Characteristic | The process output or input being controlled | Approval cycle time (days) |
| Specification | The target, limit, or tolerance | <= 3 days |
| Measurement method | The instrument, report, or procedure used | Workflow system timestamp report |
| Sample | How many items are measured and how they are chosen | All invoices |
| Frequency | How often a measurement or sample is taken | Weekly |
| Control method | The tool used to judge the data | Individuals control chart |
| Reaction plan | The actions taken on a bad signal | Owner reviews cause within 2 working days and logs the action |
| Responsible | The role that takes the action | Team lead |
The plan also needs a header with the process name, the process owner, and a version date. Without an owner's name, nobody is accountable for the plan.
A worked example
This entry controls the cycle time of an invoice approval process that the project reduced from about 7 days to about 3.
control_plan:
process: Invoice approval
owner: Accounts Payable Manager
items:
- characteristic: Approval cycle time (days)
specification: "<= 3 days"
measurement_method: Workflow system timestamp report
sample: All invoices
frequency: Weekly
control_method: Individuals control chart
reaction_plan: "If a point is outside the limits, the owner reviews the cause within 2 working days and logs the action."
responsible: Team leadRead it as a chain. The workflow report produces a number each week. The individuals chart compares that number with limits calculated from baseline data. A point outside the limits triggers the reaction plan. The team lead carries out the plan, and the owner reviews it.
Field-by-field guidance
Characteristic and specification
Choose characteristics that connect to the CTQs and to the root causes you fixed. Controlling the output, such as cycle time, shows whether the result held. Controlling a key input or process step, such as the share of invoices with a complete purchase order number, often gives an earlier warning. A plan commonly includes both.
State the specification as a number with a unit and a comparison. "Fast approval" cannot be checked. "<= 3 days" can.
Keep the specification separate from the control limits. The specification is what the customer needs. Control limits describe what the process actually does. A process can sit inside its control limits and still miss the specification, and the reverse can also happen.
Measurement method
Name the data source precisely, whether that is a report name, a gauge, or a form. Say who runs it and where the result is stored. The measurement system must be reliable over time, and a later chapter covers that. For now, check that the method in the plan is the same one you used to prove the improvement. If it is not, the new numbers may not be comparable with your baseline.
Sample size and frequency
These two fields decide how fast you will notice a problem and how much the monitoring costs. Use these rules as a starting point:
- Measure everything when the data is already captured automatically and costs nothing extra, as in the invoice example.
- Sample when measurement is destructive, slow, or manual. Take small samples at regular intervals, and keep each sample drawn from one short period so that variation inside a sample reflects common causes.
- Match frequency to how quickly the process can drift and how costly a late detection is. A weekly check suits a process whose bad output takes weeks to hurt. A process that produces defects every minute needs checks every hour or by the shift.
- Avoid frequencies that nobody can sustain. A daily chart that the team stops filling in by week three is worse than a weekly one that is always up to date.
Control method
The control method is the tool that separates normal variation from a real change. Options include:
- An individuals (I-MR) chart for single measurements, such as weekly cycle time.
- An X-bar and R chart for small samples taken at intervals.
- A p chart or c chart for proportions or counts of defects.
- A checklist or a poka-yoke device, where a device or step makes the error impossible and no chart is needed.
Pick the tool from the data type and the sample, not from habit. A later chapter covers chart choice in detail.
Reaction plan and responsible role
The reaction plan states who does what, by when, when the signal appears. "Investigate as needed" is not a plan. A usable one contains a trigger, an immediate containment action if product or service is affected, a time limit for finding the cause, and a place to record what was done. The role named in the responsible field must actually have the authority and time to act.
Calculating limits for the individuals chart
The control method column often says "individuals chart", so you should be able to produce its limits. The center line is the mean of the baseline data. The limits are the mean plus or minus 2.66 times the average moving range, where a moving range is the absolute difference between two consecutive points. The constant 2.66 equals 3 divided by 1.128, and 1.128 is the standard factor for moving ranges of size 2.
def individuals_limits(values):
"""Return (lower, center, upper) control limits for an individuals (I) chart."""
moving_ranges = [abs(b - a) for a, b in zip(values, values[1:])]
mr_bar = sum(moving_ranges) / len(moving_ranges)
center = sum(values) / len(values)
# 2.66 = 3 / d2, where d2 = 1.128 for moving ranges of size 2
return center - 2.66 * mr_bar, center, center + 2.66 * mr_bar
baseline = [2.8, 3.1, 2.9, 3.0, 3.2, 2.7, 3.0, 2.9]
lower, center, upper = individuals_limits(baseline)
new_value = 4.1
if new_value > upper or new_value < lower:
print("Out of control: follow the reaction plan")For this baseline the center is 2.95 and the average moving range is about 0.21. The limits come to roughly 2.39 and 3.51. A new weekly value of 4.1 falls above the upper limit, so the code prints the message and the reaction plan starts. Compute limits from a period when the process was stable after the improvement. Do not use data from before the change.
Checking a plan for gaps
A plan with a blank cell is the most common defect, so check for it before the handover. This short script tests each item for missing fields.
REQUIRED_FIELDS = [
"characteristic",
"specification",
"measurement_method",
"sample",
"frequency",
"control_method",
"reaction_plan",
"responsible",
]
def missing_fields(item):
"""Return the required fields that are absent or blank in a control plan item."""
return [f for f in REQUIRED_FIELDS if not str(item.get(f, "")).strip()]
item = {
"characteristic": "Approval cycle time (days)",
"specification": "<= 3 days",
"measurement_method": "Workflow system timestamp report",
"sample": "All invoices",
"frequency": "Weekly",
"control_method": "Individuals control chart",
"reaction_plan": "",
"responsible": "Team lead",
}
print(missing_fields(item))This prints ['reaction_plan']. The script only finds empty fields. A person still has to judge whether the content is specific enough.
Common errors
- Too many characteristics. A plan with 40 rows gets ignored. Control the few characteristics that protect the CTQs and the fixed root causes.
- Limits borrowed from the specification. Using the 3-day target as the control limit hides drift until the customer is already affected.
- No owner on the row. If "the team" is responsible, nobody is.
- Reaction plan written for the project team. The project team leaves at closure. The plan must name roles that remain.
- Stale plan. When the process changes, the plan changes with it, and the revision date shows that it did.
Exercise
A control plan row for "order entry errors per 100 orders" lists the specification as "low", the frequency as "when time allows", and the reaction plan as "investigate". Name three problems with this row and state how you would fix each.
Show answer
The specification "low" is not measurable, so replace it with a number such as "<= 2 errors per 100 orders". The frequency "when time allows" does not guarantee regular data, so set a fixed one such as weekly, on a sample of 100 orders. The reaction plan "investigate" has no trigger, time limit, or role, so rewrite it, for example: "If a point exceeds the upper control limit, the supervisor reviews the cause within 2 working days and logs the action." You should also add a control method, such as a p chart, and a responsible role.
Exercise
A team computes individuals chart limits from the baseline values 10, 12, 11, 13, 12. What are the lower and upper limits, using the 2.66 constant?
Show answer
The mean is (10 + 12 + 11 + 13 + 12) / 5 = 11.6. The moving ranges are 2, 1, 2 and 1, so the average moving range is 1.5. The limits are 11.6 - 2.66 × 1.5 = 7.61 and 11.6 + 2.66 × 1.5 = 15.59.