Sub topic 1
What Counts as a Risk
Prerequisites
Assume you understand basic project terms such as scope, schedule, budget, and stakeholder. You should also have some experience working with a project team and be comfortable using a spreadsheet or tracking tool.
A risk is an uncertain event or condition that could affect a project if it happens. The effect may be positive or negative, but project risk registers usually focus on threats that could harm scope, schedule, cost, quality, or objectives.
A risk has two important properties:
- It has not happened yet.
- Its occurrence and effect are uncertain.
For example, “The payment vendor may delay access to its test environment, which could postpone integration testing” is a risk. The delay might happen, but it has not happened yet.
Risk, Issue, Assumption, and Constraint
These terms describe different parts of project planning. Confusing them makes the register difficult to use.
| Term | Meaning | Example |
|---|---|---|
| Risk | An uncertain future event or condition | The vendor may miss a delivery date |
| Issue | A problem that has already happened or is happening now | The vendor missed yesterday’s delivery |
| Assumption | Something treated as true for planning, although it may not be proven | The vendor will provide test access in May |
| Constraint | A fixed limit that restricts the project | The launch must happen before 30 June |
An issue needs immediate management through an action, decision, or escalation. It should not remain recorded as a future risk. However, an issue can create new risks. If a vendor has already missed one delivery, another delay may become more likely.
An assumption can also generate a risk. If the project assumes that a specialist will be available, the specialist’s absence is a possible risk. A constraint is not automatically a risk. It becomes relevant to risk management when uncertainty surrounds the project’s ability to meet that constraint.
Use a Cause, Event, and Effect Model
A useful risk statement separates three parts:
- Cause: The existing fact or condition creating uncertainty.
- Event: What might happen.
- Effect: What the event could cause.
For example:
> Because the payment vendor has no sandbox service-level agreement, integration testing may be delayed, causing a two-week slip to launch.
This structure prevents vague entries such as “vendor risk” or “testing problem.” It also helps the team discuss evidence, consequences, and possible actions later.
Test Whether an Entry Belongs
Before adding an item to the register, ask:
- What is uncertain?
- What event might occur?
- Which project objective could it affect?
- Is the event still in the future?
- Can the team monitor or manage it?
If the event is already occurring, manage it as an issue. If the entry only names a general concern, rewrite it until the cause, event, and effect are clear.
Exercise
The project team has discovered that a required data set is incomplete. Is this a risk, an issue, an assumption, or a constraint? What related risk might be added?
Show answer
It is an issue because the problem already exists. A related risk could be that correcting the incomplete data will delay testing or increase project cost.