Sub topic 14
Keeping the Register Alive: Review Cadence
Prerequisites and purpose
This chapter assumes you understand project scope, schedule, budget, stakeholders, and the basic fields in a risk register. You should also be comfortable editing a spreadsheet or tracking tool.
A risk register is useful only when it reflects the project’s current conditions. A review cadence is the planned rhythm for checking risks, updating records, and deciding when to escalate or close them. The cadence should match the project’s pace and risk level. A fast-moving deployment may need daily reviews. A stable internal project may need a weekly review.
Build a review loop
Use a short, repeatable process:
- Check for new risks caused by recent decisions, changes, or discoveries.
- Reassess the probability and impact of open risks.
- Check whether owners completed their actions.
- Look for triggers that have occurred.
- Escalate risks that exceed the team’s authority or tolerance.
- Close risks that are no longer possible or relevant.
- Record the decision, date, and next review date.
The risk owner prepares the update. The project manager facilitates the review and makes sure decisions are recorded. Stakeholders should see risks that affect their area, but they do not need every unchanged row at every meeting.
Choose the right cadence
| Project condition | Suggested review | Reason |
|---|---|---|
| Critical release or active incident | Daily | Conditions can change within hours |
| Normal delivery phase | Weekly | Frequent enough to support action |
| Stable project with low volatility | Biweekly | Reduces meeting overhead |
Use event-based reviews as well as calendar reviews. Reassess the register after a major scope change, supplier failure, approval delay, or technical discovery. A calendar review must not wait for the next meeting when a trigger occurs today.
Detect stale records
A simple check can identify risks that need attention. This example flags records whose next review date has passed.
from datetime import date
risks = [
{"id": "R-001", "owner": "A. Rivera", "next_review": "2026-11-25"},
{"id": "R-002", "owner": "J. Chen", "next_review": "2026-12-02"},
]
today = date.today()
for risk in risks:
review_date = date.fromisoformat(risk["next_review"])
if review_date < today:
print(f"{risk['id']} needs review; owner: {risk['owner']}")Record decisions, not just discussion
An update such as “discussed with team” does not show what changed. Record the new score, action, owner, due date, trigger, and decision rationale. Preserve the previous value when the change affects a major decision. This creates an audit trail and helps the team learn from repeated patterns.
Exercise
Exercise
A supplier risk has been rated High for three consecutive weekly reviews, but its owner has taken no action. What should the project manager do?
Show answer
Confirm the risk and proposed action with the owner, set a specific due date, and escalate it if the owner lacks authority or the action remains overdue. Record the decision and next review date in the register.