Sub topic 4
Finding Risks: Workshops, Checklists, and Reviews
Assume you understand basic project scope, schedule, budget, and stakeholders. You should also be comfortable using a spreadsheet or tracking tool. This chapter focuses on discovering risks. Scoring and response planning happen after the initial discovery.
Start with a structured discovery cycle
Risk discovery works best as a repeated process rather than one meeting at project start. Use several sources because each source reveals different kinds of uncertainty.
- Review the project plan and identify activities with tight deadlines, unfamiliar technology, external dependencies, or limited resources.
- Run a workshop with people who understand different parts of the project.
- Compare the project against checklists from similar work.
- Review assumptions, decisions, contracts, and previous lessons.
- Interview specialists and stakeholders who may not attend the main workshop.
- Record possible risks without debating their scores during discovery.
- Remove duplicates and confirm that each entry describes a future uncertain event.
A useful workshop question is, “What could prevent us from meeting the project objective?” Ask follow-up questions about causes, warning signs, and effects. Include positive uncertainty when it matters. For example, a supplier might deliver early, creating an opportunity to release sooner.
Use workshops to expose hidden assumptions
Invite representatives from delivery, design, operations, finance, procurement, security, and affected business teams. The right participants depend on the project. A workshop with only project managers often misses operational and technical risks.
Prepare a simple agenda:
- Restate the project objectives and boundaries.
- Review major milestones, dependencies, and assumptions.
- Examine each workstream using “What could go wrong?” and “What are we taking for granted?”
- Capture each suggestion without assigning blame.
- Group related suggestions and identify missing owners or information.
A facilitator should separate discovery from solution design. If the group immediately proposes a fix, record the possible risk first. Otherwise, the proposed solution can hide the uncertainty that still needs management.
Apply checklists and reviews
Checklists prevent familiar risks from being forgotten. They should prompt thinking, not replace it. Organize them by category, such as scope, schedule, people, suppliers, technology, data, compliance, security, and adoption.
Document reviews provide evidence from the project itself. Examine:
- The work breakdown structure for complex or missing tasks.
- The schedule for dependencies and activities with no float.
- The budget for uncertain estimates and cost assumptions.
- Contracts for service levels, penalties, renewal dates, and responsibilities.
- The assumptions log for statements that have not been verified.
- Previous project reviews for recurring failure patterns.
| Discovery source | What it commonly reveals | Follow-up |
|---|---|---|
| Schedule review | Dependency, resource, and timing risks | Confirm the dependency and affected milestone |
| Contract review | Supplier and service-level risks | Check obligations, dates, and escalation terms |
| Stakeholder interview | Adoption or decision-making risks | Validate the concern with the affected group |
Validate before recording
A candidate belongs in the risk register when it describes an uncertain future event that could affect the project. An event that has already happened is an issue and should follow issue management. A fixed requirement or known limitation is a constraint. An unverified belief is an assumption that may also create a risk.
Before accepting an entry, check that it is distinct, understandable, and relevant to a project objective. Combine duplicates, preserve different consequences when they matter, and note missing information for later investigation. Do not reject a risk only because its probability seems low. Low-probability events may still deserve attention when their impact is severe.
Exercise
During a review, the team says, “The test environment is unavailable today.” Is this a risk, and what should you do next?
Show answer
It is an issue because it has already happened. Record it through issue management, then ask whether a future risk remains, such as repeated environment outages delaying testing.