Sub topic 13
Residual and Secondary Risks
Assume you understand project scope, schedule, budget, stakeholders, and the basic fields in a risk register. This chapter focuses on what happens after a response is selected. A response can reduce a risk without removing it, and it can create new risks of its own.
Residual risk
A residual risk is the risk that remains after you apply a response. For example, a team may reduce the risk of delayed payment integration by adding a second test environment. The probability of delay may fall from 4 to 2, but the risk may still exist because the vendor's sandbox has no service-level agreement.
Record the residual risk separately from the original assessment. Include its new probability, impact, score, owner, and response. The original score explains why the response was chosen. The residual score shows whether more action or formal acceptance is needed.
| Risk state | Example | Register action |
|---|---|---|
| Before response | Vendor testing delay could slip launch | Score and prioritize the original risk |
| After response | A delay is less likely but could still slip launch | Record residual probability, impact, and owner |
| Accepted residual risk | Remaining delay is within the approved tolerance | Record the acceptance and monitor it |
A residual risk may be acceptable when it falls within the project's risk tolerance. Acceptance is an active decision, not an omission. Name who accepted it and state the conditions that would cause the decision to be revisited.
Secondary risk
A secondary risk is a new risk caused by implementing a response. It is different from the original risk.
Suppose a project transfers a hosting risk to a managed provider. The response may reduce the chance of infrastructure failure, but it can create a secondary risk: the provider's outage process may not meet the project's recovery target. The new risk needs its own statement, score, owner, and response.
Updating the register
During a response review, ask these questions:
- What exposure remains after the action?
- Did the response create a new cause, event, or effect?
- Has the risk owner changed?
- What trigger would show that the residual risk is increasing?
- Does the remaining exposure exceed the project's tolerance?
Use a linked identifier when creating a secondary risk. For example, R-001-S1 can show that the inconsistent test data came from the response to R-001. Do not hide it in the notes field. A separate entry makes ownership, escalation, and review possible.
Common errors include marking a risk closed when only its original form was reduced, treating a residual risk as proof that the response failed, and recording a secondary risk without assigning an owner. A response can work as intended and still leave exposure behind.
Exercise
A mitigation reduces a schedule risk from probability 4 and impact 4 to probability 2 and impact 4. The mitigation also requires a new supplier, which may introduce contract delays. What should the register contain?
Show answer
Keep the original score of 16, record the residual score of 8, document the mitigation and its owner, and create a separate secondary risk for supplier contract delays with its own assessment and owner.