Sub topic 10
Choosing a Response Strategy
This chapter assumes you understand project scope, schedule, budget, and stakeholders. You should also have a risk register with clear risk statements and probability-impact scores.
A response strategy defines how the team will handle a risk if it remains relevant. Choose the strategy before assigning detailed actions. The strategy should match the risk type, rating, cost of action, project objectives, and the organization’s risk appetite.
Responses for Threats
A threat is an uncertain event that could harm the project. The main response strategies are:
| Strategy | Use it when | Typical action |
|---|---|---|
| Avoid | The threat is severe and the team can change the plan to remove it | Replace an untested technology |
| Mitigate | The team can reduce the probability or impact | Build an early prototype |
| Transfer | Another party can take responsibility for the impact | Buy insurance or use a contract |
| Accept | Action costs more than the likely loss, or no practical action exists | Monitor the risk and prepare a contingency |
Avoidance changes the project so the uncertain event no longer applies. For example, a team might remove a complex feature rather than accept a high chance of missing the launch date.
Mitigation reduces probability, impact, or both. If a payment vendor may delay integration, the team could request early access to a test environment. This may not remove the risk, but it can expose problems sooner.
Transfer moves financial or operational responsibility to another party. A service contract, warranty, or insurance policy may transfer some consequences. Transfer does not necessarily remove the risk. The project team still needs to check whether the other party can perform.
Acceptance is a deliberate decision, not inaction. A team can accept a risk actively by creating a fallback plan or passively by monitoring it without planned action. Record the reason for acceptance.
Responses for Opportunities
An opportunity is an uncertain event that could benefit the project. Use these strategies:
- Exploit: Change the plan so the opportunity definitely occurs.
- Enhance: Increase its probability or benefit.
- Share: Work with another party that can capture the benefit more effectively.
- Accept: Take advantage of the benefit if it occurs, without spending effort to make it happen.
For example, if a reusable internal component could shorten development, the team might exploit the opportunity by making it part of the approved design.
Selecting and Recording a Strategy
Compare the expected benefit of an action with its cost and side effects. Consider these questions:
- Does the response address the cause, the event, or only the effect?
- Does it fit the project’s risk appetite and tolerance?
- Is the action affordable within the current budget and schedule?
- Who can authorize or complete the action?
- What risk remains after the response?
A response can create a new risk. For example, transferring payment integration to a vendor may introduce a contract-management risk. Record this secondary risk separately instead of hiding it in the original entry.
For each selected response, record the strategy, action, action owner, due date, trigger, and expected residual risk. The risk owner remains accountable for monitoring the risk, even when another person performs the action.
Exercise
A risk has a 20% chance of causing a one-week delay. A two-day prototype would reduce the chance to 5% and costs less than the delay. Which response fits best, and what action should be recorded?
Show answer
Mitigate. Record an action such as “Build and test the prototype by 10 June,” with an owner and due date.