Sub topic 8
Scoring and Ranking with a Risk Matrix
Prerequisites
This chapter assumes you understand project scope, schedule, budget, and stakeholders. You should also know how to record risks in a spreadsheet or tracking tool. We will use an existing risk statement and focus on scoring and ranking it.
Calculate a risk score
A risk score helps you compare risks consistently. The basic formula is:
Risk score = probability × impact
Probability describes how likely the risk is to occur. Impact describes how serious the result would be if it occurred. Use a scale from 1 to 5 for both values.
| Rating | Probability | Impact |
|---|---|---|
| 1 | Very unlikely | Minimal effect |
| 3 | Possible | Noticeable effect |
| 5 | Almost certain | Severe effect |
Define the terms before scoring. For example, “severe effect” might mean a delay of more than one month or a cost increase above $50,000. The exact boundaries should match your project.
A risk with probability 4 and impact 5 has a score of 20. A risk with probability 2 and impact 3 has a score of 6. The first risk normally deserves attention before the second.
Use the probability-impact matrix
A risk matrix displays the score visually. Probability usually appears on the vertical axis, and impact appears on the horizontal axis.
This simplified diagram shows rating bands, but a real matrix should show every probability-impact combination. Agree on the bands with your stakeholders. One possible policy is:
- Low: 1–4
- Medium: 5–14
- High: 15–25
These bands are not universal. A safety-critical project may treat a score of 8 as high. Risk appetite, which is the amount of uncertainty an organization is willing to accept, determines the thresholds.
Rank and review the results
Sort the register by score from highest to lowest. Then review the ranking with the project team. A score is a decision aid, not a fact. Two people may reasonably assign different ratings because they have different evidence.
risks = [
{"id": "R-001", "probability": 4, "impact": 4},
{"id": "R-002", "probability": 2, "impact": 3},
{"id": "R-003", "probability": 3, "impact": 5},
]
for risk in risks:
risk["score"] = risk["probability"] * risk["impact"]
for risk in sorted(risks, key=lambda item: item["score"], reverse=True):
print(risk["id"], risk["score"])This prints R-003 15, R-001 16, and R-002 6 in score order only if sorted correctly. In fact, the correct output order is R-001 16, R-003 15, then R-002 6.
Re-score risks when project conditions change. New information, completed mitigations, or a changed delivery date can alter probability or impact.
Exercise
A risk has probability 3 and impact 4. What is its score, and what should you do if the project uses High = 15–25?
Show answer
Its score is 12, so it is Medium under that policy. Confirm the ratings, record an owner and response, and monitor it rather than ignoring it.