Sub topic 12
Triggers, Contingency Plans, and Reserves
Assume you understand the purpose of a risk register, can write cause-event-effect statements, and have scored risks using probability and impact. This chapter shows how to turn a selected response into an action plan that can be activated at the right time.
Define a trigger
A trigger is a measurable sign that a risk is becoming likely or has occurred. It tells the team when to stop monitoring and start responding.
Good triggers are observable and time-bound:
- The payment vendor misses two agreed test-environment delivery dates.
- Defect severity reaches 10 open critical defects during system testing.
- The migration rehearsal takes more than 36 hours.
- The forecast finish date moves within two weeks of the launch date.
“Watch the vendor closely” is not a useful trigger because different people will interpret it differently. A trigger should identify what will be measured, the threshold, and who will check it.
Build a contingency plan
A contingency plan describes the action taken if the trigger occurs. It should be specific enough that the owner can start without creating a new plan during a crisis.
For each important risk, record:
- Trigger: the measurable condition.
- Response: the action that reduces the threat or limits its effect.
- Decision authority: the person who can activate the plan.
- Start date or deadline: when the response must begin.
- Resources: people, suppliers, budget, or equipment needed.
- Communication: stakeholders who must be informed.
- Exit condition: when the contingency is complete.
For example, a migration risk might have this plan:
| Field | Example |
|---|---|
| Trigger | Rehearsal exceeds 36 hours |
| Response | Switch to the staged migration plan |
| Owner | Migration lead |
| Authority | Program manager |
| Resource | Two additional database engineers |
| Exit condition | A rehearsal completes within 24 hours |
The plan should also state what happens if the first response fails. That second step might require escalation to a sponsor or a change to scope.
Set aside reserves
A contingency reserve is budget or schedule held for identified risks. It supports planned responses or the consequences of risks that occur. It is usually controlled by the project manager within agreed governance rules.
A management reserve is separate. It covers unplanned work caused by uncertainty that was not identified in the risk register. The sponsor or another higher authority often controls it. Do not use either reserve to hide ordinary cost overruns or poor estimates.
Expected monetary value, or EMV, provides one input for estimating a reserve:
risks = [
{"id": "R-001", "probability": 0.40, "cost": 50000},
{"id": "R-003", "probability": 0.30, "cost": 20000},
]
reserve = sum(r["probability"] * r["cost"] for r in risks)
print(f"Initial EMV-based reserve estimate: ${reserve:,.0f}")This produces an estimate of $26,000. EMV is not a guaranteed bill. It averages uncertain outcomes. Review it alongside the risk distribution, response costs, dependencies, and the organization's reserve policy.
Common errors
- Choosing a trigger that is vague or impossible to measure.
- Assigning an owner without giving that person authority or resources.
- Creating a contingency plan but not recording its activation procedure.
- Treating the reserve as free project budget.
- Spending contingency funds without updating the register and forecast.
- Ignoring residual risks created by the response, such as vendor dependency or technical debt.
Review triggers during each risk meeting. When a threshold is reached, record the decision, expenditure, remaining exposure, and next review date.
Exercise
A supplier has missed one delivery date, but the agreed trigger is two missed dates. Should the team activate the contingency plan?
Show answer
Not yet, unless another agreed condition indicates that the risk is worsening. Record the missed date, increase monitoring, and activate the plan when the documented threshold is reached.